NEWS & EVENTS

220kV Tuong Duong Substation capacity doubled

06/10/2025 19:41:58

At 0:52 AM on October 3rd 2025, the National Power Transmission Corporation (EVNNPT) and the National Power Transmission Projects Management Board (NPTPMB), coordinating with relevant units, energized the Project for Installation of the second transformer at the 220kV Tuong Duong Substation, thereby increasing the substation's capacity from 125MVA to 250MVA.

This is a Class I energy project, Group C, invested by the National Power Transmission Corporation, with NPTPMB responsible for project management and Power Transmission Company 1 for operation.

NPTPMB coordinated with relevant units to energize transformer AT2 at the 220kV Tuong Duong Substation

The project is implemented on the reserved land of the existing 220kV Tuong Duong Substation in Tam Quang commune, Nghe An province.

The project involves the installation of one 220/110/22kV-125MVA transformer AT2.

On the 220kV side, equipment is installed for one 220kV busbar bay of transformer AT2.

On the 110kV side, equipment is installed for one 110kV busbar bay of transformer AT2 at bay E04, one transfer bay at bay E05, installation of 3-phase disconnectors on busbar C19 (bays E01, E08, E14, E16), and completion of the double bus with transfer busbar configuration on the 110kV side.

Transformer AT2 at the 220kV Tuong Duong Substation has been successfully energized

The control, protection and metering systems, communication and SCADA systems have been invested synchronously for the control, protection and metering systems for transformer AT2, newly installed bays and existing bays to suit the new configuration, in compliance with the regulations of Vietnam Electricity, EVNNPT and in accordance with current codes and regulations. Construction and fire protection items have been implemented in accordance with the project scope.

Previously, the investor-level acceptance council chaired by EVNNPT Deputy General Director Nguyen Ngoc Tan held a meeting and the council unanimously approved the project energization

Upon completion, the project will enhance the connection to import electricity from the Nam Mo hydropower plant clusters (Laos) to Vietnam under the agreement between the two governments; release the capacity of small and medium-sized hydropower plants in the southwestern area of Nghe An province that have been and are being prepared for construction investment; and improve the reliability of power supply to the load in Nghe An province.

EVNNPT Deputy General Director Nguyen Ngoc Tan inspected the project progress before energization

Mr. Vo Luong Nhan - Deputy Director of NPTPMB said: During the implementation process, the project faced many challenges due to rainy and flood weather in the area, especially the impacts of recent typhoons No. 5 and No. 10. In addition, scheduling power outages for project construction also encountered many difficulties due to the requirement for high power generation during the flood season. However, with the close direction of EVNNPT and NPTPMB leadership and the units participating in the Project, the Project has now been completed on schedule and is ready to enhance the reception of imported electricity from Laos to Vietnam after the completion of the 220kV Tuong Duong - Do Luong and Do Luong - Nam Cam transmission lines in the near future.

Installation of the second transformer at the 220kV Tuong Duong Substation:

  • Investor: National Power Transmission Corporation (EVNNPT);
  • Project Management: National Power Transmission Projects Management Board (NPTPMB);
  • Operation: Power Transmission Company 1;
  • Engineering Consulting Unit: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Supervision Consulting Unit: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Construction Location: The project is implemented on the reserved land of the existing 220kV Tuong Duong Substation in Tam Quang commune, Nghe An province.
  • The project involves the installation of one 220/110/22kV-125MVA transformer AT2. On the 220kV side, equipment is installed for one 220kV busbar bay of transformer AT2. On the 110kV side, equipment is installed for one 110kV busbar bay of transformer AT2 at bay E04, one transfer bay at bay E05, installation of 3-phase disconnectors on busbar C19 (bays E01, E08, E14, E16), and completion of the double bus with transfer busbar configuration on the 110kV side.

NPT.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096767

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice