NEWS & EVENTS

220kV Tuong Duong Substation capacity doubled

06/10/2025 19:41:58

At 0:52 AM on October 3rd 2025, the National Power Transmission Corporation (EVNNPT) and the National Power Transmission Projects Management Board (NPTPMB), coordinating with relevant units, energized the Project for Installation of the second transformer at the 220kV Tuong Duong Substation, thereby increasing the substation's capacity from 125MVA to 250MVA.

This is a Class I energy project, Group C, invested by the National Power Transmission Corporation, with NPTPMB responsible for project management and Power Transmission Company 1 for operation.

NPTPMB coordinated with relevant units to energize transformer AT2 at the 220kV Tuong Duong Substation

The project is implemented on the reserved land of the existing 220kV Tuong Duong Substation in Tam Quang commune, Nghe An province.

The project involves the installation of one 220/110/22kV-125MVA transformer AT2.

On the 220kV side, equipment is installed for one 220kV busbar bay of transformer AT2.

On the 110kV side, equipment is installed for one 110kV busbar bay of transformer AT2 at bay E04, one transfer bay at bay E05, installation of 3-phase disconnectors on busbar C19 (bays E01, E08, E14, E16), and completion of the double bus with transfer busbar configuration on the 110kV side.

Transformer AT2 at the 220kV Tuong Duong Substation has been successfully energized

The control, protection and metering systems, communication and SCADA systems have been invested synchronously for the control, protection and metering systems for transformer AT2, newly installed bays and existing bays to suit the new configuration, in compliance with the regulations of Vietnam Electricity, EVNNPT and in accordance with current codes and regulations. Construction and fire protection items have been implemented in accordance with the project scope.

Previously, the investor-level acceptance council chaired by EVNNPT Deputy General Director Nguyen Ngoc Tan held a meeting and the council unanimously approved the project energization

Upon completion, the project will enhance the connection to import electricity from the Nam Mo hydropower plant clusters (Laos) to Vietnam under the agreement between the two governments; release the capacity of small and medium-sized hydropower plants in the southwestern area of Nghe An province that have been and are being prepared for construction investment; and improve the reliability of power supply to the load in Nghe An province.

EVNNPT Deputy General Director Nguyen Ngoc Tan inspected the project progress before energization

Mr. Vo Luong Nhan - Deputy Director of NPTPMB said: During the implementation process, the project faced many challenges due to rainy and flood weather in the area, especially the impacts of recent typhoons No. 5 and No. 10. In addition, scheduling power outages for project construction also encountered many difficulties due to the requirement for high power generation during the flood season. However, with the close direction of EVNNPT and NPTPMB leadership and the units participating in the Project, the Project has now been completed on schedule and is ready to enhance the reception of imported electricity from Laos to Vietnam after the completion of the 220kV Tuong Duong - Do Luong and Do Luong - Nam Cam transmission lines in the near future.

Installation of the second transformer at the 220kV Tuong Duong Substation:

  • Investor: National Power Transmission Corporation (EVNNPT);
  • Project Management: National Power Transmission Projects Management Board (NPTPMB);
  • Operation: Power Transmission Company 1;
  • Engineering Consulting Unit: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Supervision Consulting Unit: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Construction Location: The project is implemented on the reserved land of the existing 220kV Tuong Duong Substation in Tam Quang commune, Nghe An province.
  • The project involves the installation of one 220/110/22kV-125MVA transformer AT2. On the 220kV side, equipment is installed for one 220kV busbar bay of transformer AT2. On the 110kV side, equipment is installed for one 110kV busbar bay of transformer AT2 at bay E04, one transfer bay at bay E05, installation of 3-phase disconnectors on busbar C19 (bays E01, E08, E14, E16), and completion of the double bus with transfer busbar configuration on the 110kV side.

NPT.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251324

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4