Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

18/09/2026 14:31:51

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

The Se San 3 Hydropower Plant Expansion Project has a designed capacity of 130 MW and an estimated annual electricity output of approximately 90.57 million kWh. The project aims to utilize excess water discharged during the flood season from the existing Se San 3 Hydropower Plant for power generation, thereby adding a source of clean electricity, increasing reserve capacity, and enhancing the flexibility and reliability of the power system.

Downstream area of the Se San 3 Hydropower Plant (Photo: Gia Lai Online Newspaper)

The project has a total investment of more than VND 3,486 billion, of which the investor’s equity contribution amounts to over VND 697 billion, accounting for 20%, while mobilized capital totals more than VND 2,789 billion, accounting for 80%. The project will require approximately 47.8 hectares of land and will have an operational term of 50 years from the date of investment policy approval.

According to the implementation schedule, from September 2026 to April 2027, EVN will complete relevant specialized agreements; carry out the appraisal of the feasibility study report and project design; negotiate and sign the power purchase agreement; and concurrently undertake procedures related to compensation, site clearance, land allocation, and land lease. Construction is expected to commence in May 2027, with completion and commissioning scheduled for June 2030.

The Gia Lai Provincial People’s Committee has requested EVN to coordinate with the relevant authorities of Gia Lai and Quang Ngai provinces to review and accurately determine the project’s scope, boundaries, and required land area, as well as to fully complete all procedures relating to land, forestry, environmental protection, compensation, assistance, and resettlement in accordance with applicable regulations.

In addition, the investor is required to ensure the full installation of monitoring and warning systems and to carry out flood discharge operations in accordance with approved procedures, thereby ensuring the safety of the project facilities and reservoir while minimizing impacts on downstream areas.

BAOGIALAI.COM.VN

(https://baogialai.com.vn/gia-lai-chap-thuan-chu-truong-dau-tu-nha-may-thuy-dien-se-san-3-mo-rong-post598982.html)

Se San 3 Hydropower Plant Expansion Project:

  • Investor: Vietnam Electricity (EVN); 
  • Investor’s Representative for Project Management: Power Project Management Board No. 2 (EVNPMB2);
  • Power Engineering Consulting Joint Stock Company 4 (PECC4) signed a contract with Power Project Management Board No. 2 (EVNPMB2) to implement Package No. TV02-SS3MR for the Se San 3 Hydropower Plant Expansion Project, covering the following consultancy services: surveys and preparation of the application dossier for investment policy approval; surveys and preparation of the Feasibility Study Report; surveys and preparation of technical design and detailed design; preparation of bidding documents; bid evaluation; and other specialized reports for the Project.

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251112

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4