500kV circuit 3 transmission line from Quang Trach to Pho Noi: Success from entire political system strength

29/08/2024 11:20:45

After more than 6 months of construction, the 500kV circuit 3 transmission line from Quang Trach to Pho Noi (including 4 sections) with a length of over 500km has been completed. This achievement is considered unprecedented compared to previous 500kV transmission line construction works.

On August 29, Vietnam Electricity (EVN) and the National Power Transmission Corporation (EVNNPT) held the inauguration ceremony of the 500kV circuit 3 transmission line projects from Quang Trach (Quang Binh) to Pho Noi (Hung Yen). The inauguration ceremony was held in a combination of live and online formats.

Overcoming many challenges

The 500kV circuit 3 transmission line projects scale with a total length of 519km, starting at Quang Trach Power Center (Quang Binh province), and ending at Pho Noi 500kV Substation (Hung Yen province). The total investment capital is over VND 22,300 billion (nearly USD 1 billion).

Delegates attending Inauguration ceremony at main bridge broadcasting- Pho Noi 500kV Substation

The project has a large volume of compensation for site clearance, spanning 211 communes/wards of 43 districts/towns in 9 provinces, with a total land acquisition area of ​​about 183 hectares, affecting 5,248 households and 96 organizations, of which 167 households have to relocate and resettle...

"Finishing" with lightning-fast progress

The 500kV circuit 3 transmission line project from Quang Trach to Pho Noi is a key and urgent project, of great significance to increase the power transmission capacity through the 500kV system from the Central to the North with a capacity of currently 2,500MW to 5,000MW, improving the stability of power system operations, increasing power supply to the North in 2025 and the following years, reducing the risk of full-loading and overloading of existing 500kV transmission lines and substations, contributing to ensuring national energy security.

After only nearly 5 months since the decision to implement, the projects have been approved by the Prime Minister for investment policy/investment policy adjustment. This is a record time, demonstrating the drastic support and participation of ministries, branches, and localities and the close attention and direction of the Government and the Prime Minister.

EVN President and CEO Nguyen Anh Tuan reporting at inauguration ceremony of 500kV circuit 3 transmission line projects from Quang Trach to Pho Noi

In addition, the project has a very large volume of construction and materials, equipment, and accessories supply (226 packages), but with the concentration of all resources and highly specialized human resources, after about 60 days, contractor selection work was completed, and signed in accordance with regulations.

With the attention and direction of the Prime Minister, ministries, and branches, the drastic participation of the provinces, and the consensus and support of the people of 9 provinces, the work of forest use purpose converting and forest impacting to open temporary roads and works for construction, site and right-of-way clearance is also ensured to be synchronized with the project’s construction progress.

The 500kV circuit 3 transmission line is a double-circuit line that passes through many different terrains, so the construction volume is much larger than other implemented lines. Specifically, the total number of poles is 1,177 with 705,000m3 of concrete, 209,000 tons of steel (for foundations and poles); and 503 spans with a total length of conductors, optical and lightning cables of 14,000m2, etc. However, with the highest determination and solidarity, the project was completed in a record construction time of more than 6 months (it usually takes 3 to 4 years to be implemented for projects of similar scale and volume).

Currently, EVN is directing EVNNPT, project management boards, and construction contractors to focus on human resources and equipment to urgently complete the restoration work, restore the site, and clean the environment in September 2024.

It can be affirmed that this is a project with a large construction volume, and many difficulties and challenges, but with a new mindset, method, and approach compared to that of the previous, the project implementation time has been significantly shortened, meeting the project completion progress requirements as directed by the Prime Minister. This is unprecedented with previous 500kV transmission line construction works.

Success from combined strength

At the ceremony, EVN Vice President Nguyen Anh Tuan shared: if the 500kV circuit 1 transmission line was built with the spirit of daring to do and taking responsibility, the 500kV circuit 2 transmission line was built with the spirit of promoting internal strength and demonstrating national self-reliance, then the 500kV circuit 3 transmission line project was built with the spirit of promoting the combined strength of the joining hands of the entire political system from ministries, branches, and local authorities at all levels, and people to unanimously resolved difficulties and innovated ways of doing things.

500kV circuit 3 transmission line, section crossing Lam River - Photo: Thanh Vinh

That is the direct, drastic, regular, and continuous attention and direction of the Prime Minister, Deputy Prime Ministers, the State Steering Committee for important national and key energy projects, the Ministry of Industry and Trade, and the State Capital Management Committee at Enterprises, the effective participation of the entire political system, local authorities at all levels, and socio-political organizations.

The project also promotes the combined strength of socio-political organizations, the Vietnam People's Army and Public Security forces, state-owned corporations, the Vietnam Fatherland Front, the Central Committee of the Ho Chi Minh Communist Youth Union, and local Women's Unions, together with EVN/EVNNPT and contractors, to coordinate closely and effectively, determined to bring the project to the finish line on schedule, with 23,000 officers and workers participating in the project.

With the completion of 4 sections of the 500kV circuit 3 transmission line project from Quang Trach to Pho Noi, Vietnam Power sector has completed the construction and put into operation 4 circuits of 500kV power transmission lines from North to South with a length of each line of more than 1,500km, making an important contribution to ensuring national energy security, serving socio-economic development, and national defense and security.

The 500kV circuit-3 transmission line project from Quang Trach to Pho Noi

- Project investor: National Power Transmission Corporation (under EVN);

- Total investment: About 22,300 billion VND;

- Scale: Consists of 2 circuits of 500kV transmission lines with a total length of about 519km. The starting point is the 500kV Quang Trach switchyard (Quang Binh province), and the end point is the 500kV Pho Noi substation (Hung Yen province);

- Engineering Consultants: Power Engineering Consulting Joint Stock Company 1,2,4 and Institute of Energy;

Progress of completion and energization of 4 sections of 500kV circuit 3 transmission line from Quang Trach to Pho Noi:

Nam Dinh I - Thanh Hoa 500kV transmission line: June 30, 2024;

Nam Dinh I - Pho Noi 500kV transmission line: August 19, 2024;

Quynh Luu - Thanh Hoa 500kV transmission line: August 19, 2024;

Quang Trach - Quynh Luu 500kV transmission line: August 27, 2024.

View more information about the 500kV circuit-3 transmission line project from Quang Trach to Pho Noi here.

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3252048

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4