NEWS & EVENTS

500kV circuit-3 transmission line project, Nam Dinh I TPP - Thanh Hoa section is ready for energization

28/06/2024 10:15:38

The investor's Acceptance committee for the 500kV circuit-3 transmission line project, Nam Dinh I TPP - Thanh Hoa section had a meeting on the afternoon of June 27th 2024, in Thanh Hoa province. Mr. Luu Viet Tien - Deputy General Director of the National Power Transmission Corporation (EVNNPT), Chairman of the Acceptance committee, confirmed that the project has met all conditions and is ready for energization.

The meeting was attended by Mr. Le Van Cuong - Standing Member of the Acceptance committee, Deputy Head of the Steering Committee for EVNNPT's 500kV circuit-3 transmission line project, members of the Acceptance committee including representatives from the Northern Vietnam Power Project Management Board (NPMB), Power Transmission Company 1, construction contractors, engineering consultants, supervision consultants, adjustment testing, construction testing, equipment and material suppliers, and the operating unit.

Mr. Luu Viet Tien - EVNNPT Deputy General Director and Chairman of the Acceptance committee gave a speech at the meeting

Mr. Luu Viet Tien - EVNNPT Deputy General Director acknowledged the efforts of the NPMB, the project management and operation unit, the units participating in the construction of the project, who have overcome all difficulties in construction conditions and unpredictable weather in recent times to bring the project to completion.

EVNNPT Deputy General Director – Mr. Luu Viet Tien said: The 500kV Nam Dinh I TPP - Thanh Hoa transmission line project is a component project of the 500kV circuit-3 transmission line project that has completed construction according to the approved engineering documents, organized acceptance in accordance with current State regulations on construction quality management, ensuring conditions for putting the project into operation. The project has met all conditions and is ready for energization.

Members of the project acceptance committee met on the afternoon of June 27th, 2024

Mr. Luu Viet Tien - EVNNPT Deputy General Director requested NPMB to coordinate with relevant units to energize the project safely. Through acceptance, there are still some minor issues that do not affect energization; NPMB will lead the coordination with relevant units to continue addressing these before handing over the project.

Once completed, the project will help reduce load and avoid overload for existing 500kV transmission lines, ensuring N-1 criteria, especially when transmission capacity is high on the North - Central interface (at times when Northern hydropower plants generate low output). The transmission line also helps increase transmission stability reserve on the North - Central interface, in combination with the 500kV Quang Trach - Quynh Luu - Thanh Hoa - Nam Dinh I TPP - Pho Noi transmission lines, contributing to supplementing power from sources in the North Central region to the load center in the Northern region.

The 500kV Nam Dinh I TPP - Thanh Hoa transmission line project is about 74.4 km length with 180 tower foundation positions, passing through Nam Dinh, Ninh Binh, and Thanh Hoa provinces. The project commenced construction at the end of October 2023.

To date, the 500kV circuit-3 transmission line project, Nam Dinh I TPP - Thanh Hoa section has been completed and is ready for energization

According to NPMB, as of June 27th, 2024, the foundation, grounding, and steel towers have been constructed according to the approved design and have been closely supervised during construction, ensuring quality and technical requirements. The conductors, ground wires, fiber optic cables, and accessories have been installed according to the approved design and manufacturer's guidelines, with close supervision during construction, ensuring quality as per approved design requirements.

The corridor of the route ensures safety distances according to Decree 14/2014/ND-CP dated February 26th 2014, and Decree 51/2020/ND-CP dated April 21st 2020, on amending and supplementing some articles of Decree 14/2014/ND-CP of the Government on high-voltage power grid safety protection.

NPMB has organized the construction of the project according to the approved design documents, compiled project completion documents, and organized acceptance of project items in accordance with legal regulations.

500kV Nam Dinh I Thermal Power Plant - Thanh Hoa transmission line project:

- Investor: National Power Transmission Corporation (under EVN)

- Investor's representative: Northern Power Project Management Board

- Engineering consultant: Consortium of Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) and Institute of Energy.

- This is a special grade, group A energy project;

- Scale: 74.4 km length including 2 circuits, with 180 tower positions;

- Construction commencement: October 2023;

- Energization date: Expected on June 30th 2024.

NPT.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097141

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice