NEWS & EVENTS

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

30/04/2026 18:06:51

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Representatives of relevant units witnessed the energization milestone

The 500kV Hoa Binh Substation capacity upgrade project is classified as a special-grade energy project (Group B), with EVNNPT as the investor. NPTPMB acted on behalf of the investor in project management and execution, while Power Transmission Company No. 1 will take over operation. The project was implemented at the existing 500kV Hoa Binh Substation, located in Hoa Binh Ward, Phu Tho Province (formerly Tan Thinh Ward, Hoa Binh City, Hoa Binh Province).

The project scope includes replacing two existing 500/220/35kV transformers rated at 450MVA each with two new transformers rated at 900MVA each, thereby increasing the total station capacity to 1,800MVA. Phase 1, which involved replacing transformer AT2, was completed and energized at the end of 2025. Phase 2, involving the replacement of transformer AT1, was completed in April 2026 in accordance with directives from EVN and EVNNPT.

The newly installed transformer at 500kV Hoa Binh Substation has been successfully energized

As the existing transformers at the 500kV Hoa Binh Substation have frequently operated under overload conditions, this capacity upgrade plays a critical role in ensuring the safe operation of the power system. It also enhances transmission capability from hydropower sources in the Northwest region, contributing to a stable electricity supply for Phu Tho Province, Hanoi, and other northern provinces—especially during periods of peak demand. This is an urgent and strategically significant project for safeguarding national energy security.

According to NPTPMB, the construction process faced numerous challenges due to limited working space and the requirement to operate within an energized substation. In addition, hydropower plants in the region were running at full capacity, making outage scheduling for construction particularly difficult. However, thanks to the close direction of EVNNPT and effective coordination among dispatching levels, Power Transmission Company No. 1, and Hoa Binh Power Transmission, the project was implemented on schedule and completed in line with the directives of EVN and EVNNPT.

Leaders of the EVNNPT Labour Union presented gifts to encourage the participating construction units in 500kV Hoa Binh Substation capacity upgrade project

The successful energization of the 500kV Hoa Binh Substation capacity upgrade project is a meaningful initiative by EVNNPT and NPTPMB to celebrate the 51st anniversary of the Reunification of Vietnam (April 30th 1975 – April 30th 2026) and the 140th International Workers’ Day (May 1st 1886 – May 1st 2026).

NPT.COM.VN

500kV Hoa Binh Substation Capacity Upgrade Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management Representative: Power Transmission Project Management Board (NPTPMB);
  • Operator: Power Transmission Company No. 1;
  • Engineering & Supervision Consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Special-grade energy project (Group B), Scope: replacement of two existing 500/220/35kV transformers (450MVA each) with two 900MVA transformers, increasing total capacity to 1,800MVA. Phase 1 (AT2 replacement) completed and energized at the end of 2025; Phase 2 (AT1 replacement) completed in April 2026 in accordance with EVN and EVNNPT directives.

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096609

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice