NEWS & EVENTS

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

30/04/2026 18:06:51

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Representatives of relevant units witnessed the energization milestone

The 500kV Hoa Binh Substation capacity upgrade project is classified as a special-grade energy project (Group B), with EVNNPT as the investor. NPTPMB acted on behalf of the investor in project management and execution, while Power Transmission Company No. 1 will take over operation. The project was implemented at the existing 500kV Hoa Binh Substation, located in Hoa Binh Ward, Phu Tho Province (formerly Tan Thinh Ward, Hoa Binh City, Hoa Binh Province).

The project scope includes replacing two existing 500/220/35kV transformers rated at 450MVA each with two new transformers rated at 900MVA each, thereby increasing the total station capacity to 1,800MVA. Phase 1, which involved replacing transformer AT2, was completed and energized at the end of 2025. Phase 2, involving the replacement of transformer AT1, was completed in April 2026 in accordance with directives from EVN and EVNNPT.

The newly installed transformer at 500kV Hoa Binh Substation has been successfully energized

As the existing transformers at the 500kV Hoa Binh Substation have frequently operated under overload conditions, this capacity upgrade plays a critical role in ensuring the safe operation of the power system. It also enhances transmission capability from hydropower sources in the Northwest region, contributing to a stable electricity supply for Phu Tho Province, Hanoi, and other northern provinces—especially during periods of peak demand. This is an urgent and strategically significant project for safeguarding national energy security.

According to NPTPMB, the construction process faced numerous challenges due to limited working space and the requirement to operate within an energized substation. In addition, hydropower plants in the region were running at full capacity, making outage scheduling for construction particularly difficult. However, thanks to the close direction of EVNNPT and effective coordination among dispatching levels, Power Transmission Company No. 1, and Hoa Binh Power Transmission, the project was implemented on schedule and completed in line with the directives of EVN and EVNNPT.

Leaders of the EVNNPT Labour Union presented gifts to encourage the participating construction units in 500kV Hoa Binh Substation capacity upgrade project

The successful energization of the 500kV Hoa Binh Substation capacity upgrade project is a meaningful initiative by EVNNPT and NPTPMB to celebrate the 51st anniversary of the Reunification of Vietnam (April 30th 1975 – April 30th 2026) and the 140th International Workers’ Day (May 1st 1886 – May 1st 2026).

NPT.COM.VN

500kV Hoa Binh Substation Capacity Upgrade Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management Representative: Power Transmission Project Management Board (NPTPMB);
  • Operator: Power Transmission Company No. 1;
  • Engineering & Supervision Consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Special-grade energy project (Group B), Scope: replacement of two existing 500/220/35kV transformers (450MVA each) with two 900MVA transformers, increasing total capacity to 1,800MVA. Phase 1 (AT2 replacement) completed and energized at the end of 2025; Phase 2 (AT1 replacement) completed in April 2026 in accordance with EVN and EVNNPT directives.

Related article

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

EVN and its units actively respond to Earth Hour 2026 campaign

EVN and its units actively respond to Earth Hour 2026 campaign

In response to the Earth Hour 2026 Campaign launched by the Ministry of Industry and Trade, Vietnam Electricity (EVN) has proactively and effectively coordinated the unified implementation of a wide range of communication, advocacy, and execution activities nationwide, contributing to the strong dissemination of the message of efficient energy use and environmental protection.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2792634

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice