500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

30/04/2026 18:06:51

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Representatives of relevant units witnessed the energization milestone

The 500kV Hoa Binh Substation capacity upgrade project is classified as a special-grade energy project (Group B), with EVNNPT as the investor. NPTPMB acted on behalf of the investor in project management and execution, while Power Transmission Company No. 1 will take over operation. The project was implemented at the existing 500kV Hoa Binh Substation, located in Hoa Binh Ward, Phu Tho Province (formerly Tan Thinh Ward, Hoa Binh City, Hoa Binh Province).

The project scope includes replacing two existing 500/220/35kV transformers rated at 450MVA each with two new transformers rated at 900MVA each, thereby increasing the total station capacity to 1,800MVA. Phase 1, which involved replacing transformer AT2, was completed and energized at the end of 2025. Phase 2, involving the replacement of transformer AT1, was completed in April 2026 in accordance with directives from EVN and EVNNPT.

The newly installed transformer at 500kV Hoa Binh Substation has been successfully energized

As the existing transformers at the 500kV Hoa Binh Substation have frequently operated under overload conditions, this capacity upgrade plays a critical role in ensuring the safe operation of the power system. It also enhances transmission capability from hydropower sources in the Northwest region, contributing to a stable electricity supply for Phu Tho Province, Hanoi, and other northern provinces—especially during periods of peak demand. This is an urgent and strategically significant project for safeguarding national energy security.

According to NPTPMB, the construction process faced numerous challenges due to limited working space and the requirement to operate within an energized substation. In addition, hydropower plants in the region were running at full capacity, making outage scheduling for construction particularly difficult. However, thanks to the close direction of EVNNPT and effective coordination among dispatching levels, Power Transmission Company No. 1, and Hoa Binh Power Transmission, the project was implemented on schedule and completed in line with the directives of EVN and EVNNPT.

Leaders of the EVNNPT Labour Union presented gifts to encourage the participating construction units in 500kV Hoa Binh Substation capacity upgrade project

The successful energization of the 500kV Hoa Binh Substation capacity upgrade project is a meaningful initiative by EVNNPT and NPTPMB to celebrate the 51st anniversary of the Reunification of Vietnam (April 30th 1975 – April 30th 2026) and the 140th International Workers’ Day (May 1st 1886 – May 1st 2026).

NPT.COM.VN

500kV Hoa Binh Substation Capacity Upgrade Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management Representative: Power Transmission Project Management Board (NPTPMB);
  • Operator: Power Transmission Company No. 1;
  • Engineering & Supervision Consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Special-grade energy project (Group B), Scope: replacement of two existing 500/220/35kV transformers (450MVA each) with two 900MVA transformers, increasing total capacity to 1,800MVA. Phase 1 (AT2 replacement) completed and energized at the end of 2025; Phase 2 (AT1 replacement) completed in April 2026 in accordance with EVN and EVNNPT directives.

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251147

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4