NEWS & EVENTS

500kV Monsoon - Thanh My transmission line project was successfully energized to import electricity from Laos to Vietnam

24/01/2025 08:56:45

At 22:43 on 23 January  2025, the 500kV  Monsoon - Thanh My  transmission line project (section in Vietnam) was successfully energized. This is a key transmission grid project, serving the import of electricity from the Monsoon wind power plant (in Laos) to Vietnam, adding 600MW of electricity to the national power system from 2024 to 2025.

Representatives of Investor and Contractor witnessing successful energization of 500kV Monsoon - Thanh My transmission line project

The 500kV Monsoon-Thanh My transmission line project (section in Vietnam) is invested by Vietnam Electricity (EVN). The Power Project Management Board 2 (EVNPMB2) is assigned to represent the Investor. The part of the work located in Vietnam is built in Nam Giang district, Quang Nam province with a length of about 44.71 km, the total investment of the project is more than VND 1,100 billion. This is a double-circuit transmission line work, connecting the Monsoon Wind Power Plant cluster (in Laos) to the 500kV Thanh My substation in Quang Nam province.

The project started on 30 September 2023 and was completed by the approved design. 90/90 concrete foundation positions, 90/90 steel poles, and 28/28 anchorage spans were completed.

In the past, the project construction process encountered many difficulties due to rugged terrain, severe weather, etc. However, with the efforts of Power Project Management Board 2 and many units on the construction site, the project part in Vietnam was completed 40 days ahead of the power generation milestone of the Monsoon wind power project (in Laos, expected to be completed in early March 2025).

The 500kV Monsoon - Thanh My transmission line can transmit a maximum capacity of up to about 2,500MW, contributing to improving the operational capacity of the national power system by importing electricity from Laos. Shortly, after the Monsoon wind power plant project (Laos side) is completed, this transmission line project will receive imported electricity from Laos with a capacity of 600MW, and the expected average annual electricity output is about 1.7 billion kWh.

Some photos about The 500kV Monsoon - Thanh My  transmission line:

The 500kV Monsoon-Thanh My transmission line project (section in Vietnam) 

  • Investor: EVN;

  • Investor's Representative: EVNPMB2;

  • Site supervision consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);

  • Project scale: built in Nam Giang district, Quang Nam province with a length of about 44.71 km, the total investment of the project is more than VND 1,100 billion. This is a double-circuit transmission line work, connecting the Monsoon Wind Power Plant cluster (in Laos) to the 500kV Thanh My substation in Quang Nam province.

EVN.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097045

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice