NEWS & EVENTS

Bringing electricity to Con Dao: Extending sea-across journey of Vietnam's power engineers

24/07/2025 14:29:55

In mid-July, barges loaded with equipment continued tirelessly crossing the sea waves to build the national power grid connecting to Con Dao. During the journey of hundreds of kilometers across the sea, the team of engineers and workers is working day and night to complete one of the most special energy projects.

Urgent need

Con Dao Special Zone, under Ho Chi Minh City, holds significant importance in national defense, security, and sovereignty over islands and seas, and is also a high-value destination in terms of history, culture, and tourism. However, the island's current electricity system mainly relies on diesel with a capacity of over 11MW. Therefore, the need for investment in infrastructure to provide electricity to Con Dao is urgent.

EVN Vice President Nguyen Tai Anh (4th from right) inspects cable connection tunnel construction and concrete cable trench at Con Dao on July 17, 2025

The project to supply power from the national grid to Con Dao has a total investment of over VND 4,923 billion, with Vietnam Electricity (EVN) as the investor, and the Power Project Management Board 3 as the project management representative. The 110kV transmission line bringing electricity from the mainland to Con Dao is over 100km long, with about 80km of submarine cable.

By mid-July, the construction of the overhead line on the Soc Trang coast had basically completed all 32 foundation poles, and steel poles were being installed. The submarine cable section is divided into two parts, with the first section of 41km completed on July 7, 2025, and the second section, 39km long, is currently being worked on by construction units to pull the cables. At Con Dao, all cable connection tunnels and concrete cable trenches along the route have been completed by the contractor. The submarine cable section and the 110/22kV GIS substation are in the process of cable installation and equipment setup. Efforts are being made to complete the installation as soon as possible, in order to move on to the testing and commissioning phase for energizing the entire line.

Crossing waves, bringing electricity to island

Pole 32 location at sea off the Soc Trang coast, taken on July 17, 2025

Phu Xuan Company is the contractor for package 04XL-DZCD, which includes positions 28-32 at sea. To date, the company has completed 100% of the work on package 04XL as per the contract schedule.

Mr. Tran Ngoc Dung, Deputy Director of the Project Management Board and Director of the Project Management Division, said, "The contractors are working hard to ensure the overall schedule. Despite rough seas, heavy rain, or difficulties with transportation, all contractors are determined to bring electricity to the island as promised."

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251505

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4