NEWS & EVENTS

Bringing electricity to Con Dao: Extending sea-across journey of Vietnam's power engineers

24/07/2025 14:29:55

In mid-July, barges loaded with equipment continued tirelessly crossing the sea waves to build the national power grid connecting to Con Dao. During the journey of hundreds of kilometers across the sea, the team of engineers and workers is working day and night to complete one of the most special energy projects.

Urgent need

Con Dao Special Zone, under Ho Chi Minh City, holds significant importance in national defense, security, and sovereignty over islands and seas, and is also a high-value destination in terms of history, culture, and tourism. However, the island's current electricity system mainly relies on diesel with a capacity of over 11MW. Therefore, the need for investment in infrastructure to provide electricity to Con Dao is urgent.

EVN Vice President Nguyen Tai Anh (4th from right) inspects cable connection tunnel construction and concrete cable trench at Con Dao on July 17, 2025

The project to supply power from the national grid to Con Dao has a total investment of over VND 4,923 billion, with Vietnam Electricity (EVN) as the investor, and the Power Project Management Board 3 as the project management representative. The 110kV transmission line bringing electricity from the mainland to Con Dao is over 100km long, with about 80km of submarine cable.

By mid-July, the construction of the overhead line on the Soc Trang coast had basically completed all 32 foundation poles, and steel poles were being installed. The submarine cable section is divided into two parts, with the first section of 41km completed on July 7, 2025, and the second section, 39km long, is currently being worked on by construction units to pull the cables. At Con Dao, all cable connection tunnels and concrete cable trenches along the route have been completed by the contractor. The submarine cable section and the 110/22kV GIS substation are in the process of cable installation and equipment setup. Efforts are being made to complete the installation as soon as possible, in order to move on to the testing and commissioning phase for energizing the entire line.

Crossing waves, bringing electricity to island

Pole 32 location at sea off the Soc Trang coast, taken on July 17, 2025

Phu Xuan Company is the contractor for package 04XL-DZCD, which includes positions 28-32 at sea. To date, the company has completed 100% of the work on package 04XL as per the contract schedule.

Mr. Tran Ngoc Dung, Deputy Director of the Project Management Board and Director of the Project Management Division, said, "The contractors are working hard to ensure the overall schedule. Despite rough seas, heavy rain, or difficulties with transportation, all contractors are determined to bring electricity to the island as promised."

EVN.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096896

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice