On March 9th, the Project Management Board (PMB) of the National Power Transmission Corporation (EVNNPT) coordinated with relevant units to commence the installation of the second transformer at 220kV Chu Se substation.

The "Installation of the second transformer at 220kV Chu Se Substation" project is invested by EVNNPT. Picture: Le Phuong/BNEWS/TTXVN

The project “Installation of the second transformer at 220kV Chu Se Substations" is invested by EVNNPT, with PMB acting on behalf of EVNNPT to manage project operations. PC1 Group Joint Stock Company – My Dinh will conduct the construction, and Power Engineering Consulting Joint Stock Company 2 will provide supervision service.

The project includes the following scopes:

  • Converting the 220kV Chu Se substation diagram from a triangle to a quadrangle configuration.
  • Installing a second 220kV transformer with a 1 x 125 MVA capacity.
  • Installing two 110kV outgoing circuits.
  • Installing a loop circuit breaker on the 110kV side.
  • Completing the double busbar scheme with a ring busbar.
  • Ensuring that the control and protection system aligns with the new substation configuration.

The construction will take place within the premises of the 220kV Chu Se substation located in Ia Pal commune, Chu Se district, Gia Lai province.

Mr. Nguyen Quang Anh, Deputy Director of PMB, stated that upon completion, the project would meet the increasing power demand, enhance the reliability, safety, and stability of the southern power grid in Gia Lai province, strengthen the interconnection of the regional power grid, improve reliability, safety, and reduce losses in the transmission grid.

The "Installation of the second transformer at 220kV Chu Se Substation" project will also facilitate the transmission of power from hydropower plants and renewable energy sources in the area to the national power system.

Project: Installation of  the second transformer at 220kV Chu Se Substation

Investor: National Power Transmission Corporation (EVNNPT)

Project Management Representative: National Power Transmission Project Management Board (NPTPMB)

Contractor: PC1 Group Joint Stock Company – My Dinh

Engineering Consultancy: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4)

Supervision Consultancy: Power Engineering Consulting Joint Stock Company 2 (EVNPECC2)

bnews.vn

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827321

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice