NEWS & EVENTS

Completion of the 220kV Tuong Duong Substation and Interconnection Line

17/05/2022 00:00:00

On May 16th, at 21:45, the Central Power Projects Management Board (CPMB), coordinating with relevant units, organized the acceptance and energization of the 220kV Tuong Duong Substation and Interconnection Line.

The National Power Transmission Corporation invests in the project, with CPMB responsible for project management and Power Transmission Company 1 for operation. The project involves the construction of a new substation with a capacity of 02 220/110/22kV-125MVA transformers, with the installation of one transformer in this phase.

The 220kV section is designed in a "Ring Bus" configuration consisting of 13 bays, 9 bays installed in this phase and 4 bays as a backup. The 110kV section is designed in a "Double Bus with Transfer Busbar" configuration and has reserved land for future development into a "Double Bus with Ring Busbar" configuration. It comprises 16 bays, 6 installed in this phase and 10 bays as a backup. The 22kV section utilizes a block diagram with outdoor equipment for self-supplying power through the substation's transformers.

As for the 220kV interconnection line, a double circuit transmission line is constructed to connect the 220kV Tuong Duong Substation to the existing 220kV Tuong Duong - Ban Ve - Do Luong transmission line.

Upon completion, the project will import electricity from hydropower plants in Nam Mo (Laos) to Vietnam under the agreement between the two governments. It will also accommodate the capacity release from small and medium-sized hydropower plants in the southwestern area of Nghe An province, which are currently under preparation for construction. Furthermore, it will enhance the reliability of the power supply to the load in Nghe An province and ensure the safe operation of the power system.

The project has been implemented since August 2021, facing significant disruptions due to prolonged rainy weather, leading to a suspension of construction for over a month. The construction site also had to halt operations for 14 days due to COVID-19 restrictions imposed by local authorities.

Additionally, the scheduling of power outages for construction purposes encountered difficulties due to the high electricity demand during the hot season. However, CPMB and the on-site construction unit have overcome these challenges to complete the project on schedule, meeting the set requirements and being ready to receive imported electricity from Laos to Vietnam after the completion of the 220kV Nam Mo - Tuong Duong transmission line (expected to be completed by the end of June 2022).

220kV Tuong Duong Substation and Interconnection Line:

  • Construction Location: Tuong Duong District, Nghe An Province;
  • Commencement: August 2021, and completion in May 2022.
  • Investor: National Power Transmission Corporation;
  • Project Management: Central Power Projects Management Board (CPMB);
  • EPC Contractor: Advanced Information Technologies Corporation
  • Supervision Consulting Unit: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4).

Source: dientungaynay.vn

 

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251496

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4