NEWS & EVENTS

Completion of the 220kV Tuong Duong Substation and Interconnection Line

17/05/2022 00:00:00

On May 16th, at 21:45, the Central Power Projects Management Board (CPMB), coordinating with relevant units, organized the acceptance and energization of the 220kV Tuong Duong Substation and Interconnection Line.

The National Power Transmission Corporation invests in the project, with CPMB responsible for project management and Power Transmission Company 1 for operation. The project involves the construction of a new substation with a capacity of 02 220/110/22kV-125MVA transformers, with the installation of one transformer in this phase.

The 220kV section is designed in a "Ring Bus" configuration consisting of 13 bays, 9 bays installed in this phase and 4 bays as a backup. The 110kV section is designed in a "Double Bus with Transfer Busbar" configuration and has reserved land for future development into a "Double Bus with Ring Busbar" configuration. It comprises 16 bays, 6 installed in this phase and 10 bays as a backup. The 22kV section utilizes a block diagram with outdoor equipment for self-supplying power through the substation's transformers.

As for the 220kV interconnection line, a double circuit transmission line is constructed to connect the 220kV Tuong Duong Substation to the existing 220kV Tuong Duong - Ban Ve - Do Luong transmission line.

Upon completion, the project will import electricity from hydropower plants in Nam Mo (Laos) to Vietnam under the agreement between the two governments. It will also accommodate the capacity release from small and medium-sized hydropower plants in the southwestern area of Nghe An province, which are currently under preparation for construction. Furthermore, it will enhance the reliability of the power supply to the load in Nghe An province and ensure the safe operation of the power system.

The project has been implemented since August 2021, facing significant disruptions due to prolonged rainy weather, leading to a suspension of construction for over a month. The construction site also had to halt operations for 14 days due to COVID-19 restrictions imposed by local authorities.

Additionally, the scheduling of power outages for construction purposes encountered difficulties due to the high electricity demand during the hot season. However, CPMB and the on-site construction unit have overcome these challenges to complete the project on schedule, meeting the set requirements and being ready to receive imported electricity from Laos to Vietnam after the completion of the 220kV Nam Mo - Tuong Duong transmission line (expected to be completed by the end of June 2022).

220kV Tuong Duong Substation and Interconnection Line:

  • Construction Location: Tuong Duong District, Nghe An Province;
  • Commencement: August 2021, and completion in May 2022.
  • Investor: National Power Transmission Corporation;
  • Project Management: Central Power Projects Management Board (CPMB);
  • EPC Contractor: Advanced Information Technologies Corporation
  • Supervision Consulting Unit: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4).

Source: dientungaynay.vn

 

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096938

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice