Construction commencement ceremony of Lao Cai - Vinh Yen 500KV transmission line, section passing through Yen Bai province

03/03/2025 16:11:22

On 3 March 2025 in Yen Bai, Vietnam Electricity, Power Project Management Board 1 held the Construction commencement ceremony of the Lao Cai - Vinh Yen 500KV transmission line, the section passing through Yen Bai province.

Attending the Construction commencement ceremony were Mr. Ngo Hanh Phuc - Vice Chairman of the Yen Bai Provincial People's Committee, Ms. Hoang Thi Thanh Binh - Member of the Provincial Party Committee, Vice Chairman of Yen Bai Provincial People's Council; leaders of Departments and Branches of Yen Bai province, representatives of the Party Committees and authorities of Luc Yen and Yen Binh districts and representatives of the people in the project area. Also attending the ceremony, were leaders of Vietnam Electricity, leaders of Power Project Management Board 1, and the contractor for construction package No. 4HH-DZ500LC (from VT149 to VT200) of the project.

The Lao Cai - Vinh Yen 500kV Transmission Line Project is a national key project. The Prime Minister has approved investment for this project. This is a double-circuit 500 kV transmission line work with a total length of 229.5km and 468 pole foundation locations. The project passes through 04 provinces including Lao Cai, Yen Bai, Phu Tho, and Vinh Phuc with the starting point being the Lao Cai 500kV substation and the ending point being the Vinh Yen 500kV substation. The total investment of the Project is over VND 7,410 billion, arranged from the loan capital of the Joint Stock Commercial Bank for Foreign Trade of Vietnam (Vietcombank) at 80% and the counterpart capital of EVN at 20% of the total investment (before tax).

After being put into operation, the line will release about 2,000 MW from hydropower plants in the Northwest region and neighboring provinces to the national grid and increase the ability to import electricity. At the same time, it creates a strong connection between areas in the power system; enhances the ability to operate safely and stably for the national power system; reduces power loss in the transmission grid; and increases the efficiency of EVN's electricity production and business.

The section passing through Yen Bai province alone is 90.06 km long, with 173 pole foundation locations (from VT102 to VT274), passing through 02 districts: Luc Yen and Yen Binh. The project contributes to ensuring energy sources for the province's medium and long-term development targets, increasing budget revenue, and creating job opportunities for local businesses and workers.

Speaking at the Construction commencement ceremony, a representative of Vietnam Electricity said that during the investment preparation and implementation of the project, EVN received attention and close direction from the Government, the Prime Minister, the Ministry of Industry and Trade, the Committee for Management of State Capital at Enterprises, along with the support and close coordination of the Provincial Party Committee, the People's Committees of Lao Cai, Yen Bai, Phu Tho and Vinh Phuc provinces, the Departments and Branches of the provinces; District Party Committees, People's Committees of 12 districts in the 4 provinces, the solidarity and consensus of the people in the Project area to accelerate the progress of compensation, support and resettlement.

Vietnam Electricity respectfully requests the leaders of the Provincial Party Committee, the Provincial People's Committee, the leaders of the Departments and Branches of Yen Bai province; The leaders of the districts and communes in the project area to continue to pay attention to and direct the implementation of compensation, support, and resettlement work, and promptly complete the handover of all the land for the pole foundations and the right-of-ways so that the Investor can organize the synchronous construction of the pole foundations on the entire route to meet the project's progress.

Vietnam Electricity assigns the task to the Power Project Management Board 1 and contractors to manage the project, organize the construction to ensure compliance with the requirements on quality and environment, focus resources and equipment to accelerate the progress, and strive to complete the project by the planned schedule.

Some pictures at the ceremony:

Lao Cai - Vinh Yen 500kV Transmission Line Project:

  • Investor: Vietnam Electricity;
  • Investor representative for project management and operation: Power Project Management Board 1;
  • Survey and Engineering Consultant: Consortium of Power Engineering Consulting Joint Stock Company 1 (EVNPECC1) and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Total investment: More than VND 7,410 billion;
  • Project area: Lao Cai, Yen Bai, Phu Tho and Vinh Phuc;
  • Construction commencement: March 2025;
  • Expected completion: Before 2 September  2025.

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251894

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4