NEWS & EVENTS

Construction Commencement of 500kV Binh Duong 1 Substation Project

14/11/2023 10:38:24

On November 13, 2023, in Binh Duong, the National Power Transmission Corporation (EVNNPT), the Central Power Projects Management Board (CPMB), in coordination with related entities, organized the construction commencement of 500kV Binh Duong 1 Substation Project.

This is a special level energy project, of Group B, constructed in An Binh commune, Phu Giao district, Binh Duong province. The location of 500kV Binh Duong 1 Substation was agreed upon by the People's Committee of Binh Duong province in Document No. 1562/UBND-KT dated April 1, 2020.

The project is invested by EVNNPT, with CPMB managing the project implementation, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) conducting construction surveys and engineering, the consortium of PC1 Thang Long and Alphanam E&C carrying out the construction, and Power Transmission Company 4 operating the project.

CPMB leaders and units participating in the project performed the construction ceremony

The main scope of the project includes the construction of a new 500/220kV substation with 2 x 500/220/35kV - 900MVA transformers, in this phase, 1 x 500/220/35kV - 900MVA transformer will be fully installed.

The 500kV side uses a 3/2 busbar scheme including 5 bays: 1 incoming feeder for the 500kV transformer and 4 outgoing feeders for 500kV lines; reserve 1 incoming feeder for the 500kV transformer, 4 outgoing feeders for 500kV lines and 2 bays for bus sectionalizer for current limiting reactors installation.

The 220kV side uses a double busbar scheme with bus-tie including 7 bays: 1 incoming feeder for the 220kV winding of the 500kV transformer, 1 bay for bus-coupler breakers, 1 bay for bus-tie breakers and 4 outgoing feeders for 220kV lines; reserve 1 incoming feeder for the 220kV winding of the 500kV transformer and 6 outgoing feeders for 220kV lines.

After completion, the project will help improve the reliability of power supply to Binh Duong province and the southern economic development region. It will support capacity and prevent overloads at 500kV Song May and Tan Dinh substations, ensuring the safe operation of the transmission system.

Perspective of 500kV Binh Duong 1 substation

The representative of the Central Power Projects Management Board said: “This is an important project to ensure electricity supply to Binh Duong province and surrounding provinces in the Southeast region. This is an area with rapid economic development and electricity growth rate. CPMB requires the units during construction to strictly comply with technical standards and procedures, properly manage occupational safety, health, environment, and ensure construction quality.”

Currently, site clearance for the project is basically completed. CPMB requests the construction contractors and supervision consultants to mobilize forces and closely coordinate with the project management unit and related units to ensure quality and progress, aiming to energize the project in 2024 as directed by EVNNPT.

500kV Binh Duong 1 Substation Project

Investor: EVNNPT

Project Management: CPMB

Survey and Engineering: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4)

Construction Contractor: Thang Long PC1 and Alphanam E&C Consortium

Operating entity: Power Transmission Company 4

NPT.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097066

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice