Efforts to Complete the Construction of the 220kV Bo Y Switching Substation and Interconnection in March 2023

13/03/2023 11:12:35

The project for the 220kV Bo Y Switching Substation and Interconnection (in Ngoc Hoi district, Kon Tum province) is gradually reaching completion. The Power Project Management Board 2 (EVNPMB2) is working to ensure the project's completion in March 2023.

The 220kV Bo Y Switching Substation and Interconnection Project is reaching completion

The project, assigned by Vietnam Electricity (Investor) to the EVNPMB2, aims to import electricity from the Nam Kong 1, 2, and 3 hydropower plants in Laos to Vietnam.

According to the EVNPMB2’s representative, the switching substation construction has completed all excavation, foundation work, control building, and diesel house. 122/134 equipment support structures have been completed, and construction has progressed for 5 of 6 cable trench sections. Other auxiliary items, such as guardhouses, fences, internal roads, and more, are also being expedited. Overall, the construction work progress has reached approximately 97%.

Regarding the interconnection, Kon Tum Power Transmission has completed the section with 2 circuits (Nam Kong 3 - Bo Y) and undergone technical acceptance testing. The section with 4 circuits (from the 220kV Bo Y Switching Substation to the Xekaman 1-Pleiku 2 220kV Transmission Line) has already pulled cables for 4 out of 7 spans and is continuing the cable pulling for the remaining spans. EVNPMB2 assesses that the current situation can meet the deadline for energization before March 31, 2023.

The project commenced in April 2022 and encountered numerous difficulties during implementation. For instance, many sections of the transmission lines pass through natural forests, requiring complex procedures for construction. Additionally, 2/3 of the switching substation area is on hills, while the remaining portion is in a valley. Thus, building a 300-meter-long retaining wall with a height exceeding 30 meters and reinforcing it significantly is necessary to ensure safe conditions. Furthermore, the region's prolonged and heavy rainfall is one of the main challenges affecting the project's progress.

On March 9, 2023, during an inspection of the construction site, Mr. Khuong The Anh - Deputy Head of EVNPMB2, acknowledged the diligent efforts of the EVNPMB2 and the construction contractors in pushing forward the construction progress despite facing various difficulties. So far, the project has completed a significant amount of the set workload and met the requirements of Vietnam Electricity.

Mr. Khuong The Anh requested the EVNPMB2 to continue closely supervising the contractors, expedite the completion of related tasks, and strengthen the workforce and equipment for swift construction progress. However, it is emphasized that quality and safety should not be compromised due to the project's timeline.

The 220kV Bo Y Switching Substation and Interconnection Project:

  • Investor: Vietnam Electricity (EVN)
  • Project Management: The Power Project Management Board 2 (PMB2)
  • Engineering and Supervision Consultant: Power Engineering Consulting Joint Stock Company 4(EVNPECC4)
  • Contractor Consortium: Vietnam Machinery Installation Corporation, PCC4 and TOJI Group Corporation
  • Total Investment: 181 billion VND
  • Location: Ngoc Hoi District, Kon Tum Province
  • Commencement: April 2022
  • Expected Completion: March 2023

Scope:

  • Construction of a new 220kV Bo Y Switching Substation, consisting of 10 bays (6 bays to be installed in this phase).
  • Construction of a 6km-long 220kV transmission line (double circuit) connecting the 220kV Bo Y Switching Substation to the 220kV transmission line of the Nam Kong 2 and 3 Substations (Laos).
  • Construction of a 0.8km-long 220kV transmission line (4-circuit) connecting the 220kV Bo Y Switching Substation to the 220kV Xekaman 1 (Laos) - Pleiku 2 transmission line

EVN.COM.VN

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827325

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice