NEWS & EVENTS

Efforts to Complete the Construction of the 220kV Bo Y Switching Substation and Interconnection in March 2023

13/03/2023 11:12:35

The project for the 220kV Bo Y Switching Substation and Interconnection (in Ngoc Hoi district, Kon Tum province) is gradually reaching completion. The Power Project Management Board 2 (EVNPMB2) is working to ensure the project's completion in March 2023.

The 220kV Bo Y Switching Substation and Interconnection Project is reaching completion

The project, assigned by Vietnam Electricity (Investor) to the EVNPMB2, aims to import electricity from the Nam Kong 1, 2, and 3 hydropower plants in Laos to Vietnam.

According to the EVNPMB2’s representative, the switching substation construction has completed all excavation, foundation work, control building, and diesel house. 122/134 equipment support structures have been completed, and construction has progressed for 5 of 6 cable trench sections. Other auxiliary items, such as guardhouses, fences, internal roads, and more, are also being expedited. Overall, the construction work progress has reached approximately 97%.

Regarding the interconnection, Kon Tum Power Transmission has completed the section with 2 circuits (Nam Kong 3 - Bo Y) and undergone technical acceptance testing. The section with 4 circuits (from the 220kV Bo Y Switching Substation to the Xekaman 1-Pleiku 2 220kV Transmission Line) has already pulled cables for 4 out of 7 spans and is continuing the cable pulling for the remaining spans. EVNPMB2 assesses that the current situation can meet the deadline for energization before March 31, 2023.

The project commenced in April 2022 and encountered numerous difficulties during implementation. For instance, many sections of the transmission lines pass through natural forests, requiring complex procedures for construction. Additionally, 2/3 of the switching substation area is on hills, while the remaining portion is in a valley. Thus, building a 300-meter-long retaining wall with a height exceeding 30 meters and reinforcing it significantly is necessary to ensure safe conditions. Furthermore, the region's prolonged and heavy rainfall is one of the main challenges affecting the project's progress.

On March 9, 2023, during an inspection of the construction site, Mr. Khuong The Anh - Deputy Head of EVNPMB2, acknowledged the diligent efforts of the EVNPMB2 and the construction contractors in pushing forward the construction progress despite facing various difficulties. So far, the project has completed a significant amount of the set workload and met the requirements of Vietnam Electricity.

Mr. Khuong The Anh requested the EVNPMB2 to continue closely supervising the contractors, expedite the completion of related tasks, and strengthen the workforce and equipment for swift construction progress. However, it is emphasized that quality and safety should not be compromised due to the project's timeline.

The 220kV Bo Y Switching Substation and Interconnection Project:

  • Investor: Vietnam Electricity (EVN)
  • Project Management: The Power Project Management Board 2 (PMB2)
  • Engineering and Supervision Consultant: Power Engineering Consulting Joint Stock Company 4(EVNPECC4)
  • Contractor Consortium: Vietnam Machinery Installation Corporation, PCC4 and TOJI Group Corporation
  • Total Investment: 181 billion VND
  • Location: Ngoc Hoi District, Kon Tum Province
  • Commencement: April 2022
  • Expected Completion: March 2023

Scope:

  • Construction of a new 220kV Bo Y Switching Substation, consisting of 10 bays (6 bays to be installed in this phase).
  • Construction of a 6km-long 220kV transmission line (double circuit) connecting the 220kV Bo Y Switching Substation to the 220kV transmission line of the Nam Kong 2 and 3 Substations (Laos).
  • Construction of a 0.8km-long 220kV transmission line (4-circuit) connecting the 220kV Bo Y Switching Substation to the 220kV Xekaman 1 (Laos) - Pleiku 2 transmission line

EVN.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097075

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice