Efforts to Complete the Construction of the 220kV Bo Y Switching Substation and Interconnection in March 2023

13/03/2023 11:12:35

The project for the 220kV Bo Y Switching Substation and Interconnection (in Ngoc Hoi district, Kon Tum province) is gradually reaching completion. The Power Project Management Board 2 (EVNPMB2) is working to ensure the project's completion in March 2023.

The 220kV Bo Y Switching Substation and Interconnection Project is reaching completion

The project, assigned by Vietnam Electricity (Investor) to the EVNPMB2, aims to import electricity from the Nam Kong 1, 2, and 3 hydropower plants in Laos to Vietnam.

According to the EVNPMB2’s representative, the switching substation construction has completed all excavation, foundation work, control building, and diesel house. 122/134 equipment support structures have been completed, and construction has progressed for 5 of 6 cable trench sections. Other auxiliary items, such as guardhouses, fences, internal roads, and more, are also being expedited. Overall, the construction work progress has reached approximately 97%.

Regarding the interconnection, Kon Tum Power Transmission has completed the section with 2 circuits (Nam Kong 3 - Bo Y) and undergone technical acceptance testing. The section with 4 circuits (from the 220kV Bo Y Switching Substation to the Xekaman 1-Pleiku 2 220kV Transmission Line) has already pulled cables for 4 out of 7 spans and is continuing the cable pulling for the remaining spans. EVNPMB2 assesses that the current situation can meet the deadline for energization before March 31, 2023.

The project commenced in April 2022 and encountered numerous difficulties during implementation. For instance, many sections of the transmission lines pass through natural forests, requiring complex procedures for construction. Additionally, 2/3 of the switching substation area is on hills, while the remaining portion is in a valley. Thus, building a 300-meter-long retaining wall with a height exceeding 30 meters and reinforcing it significantly is necessary to ensure safe conditions. Furthermore, the region's prolonged and heavy rainfall is one of the main challenges affecting the project's progress.

On March 9, 2023, during an inspection of the construction site, Mr. Khuong The Anh - Deputy Head of EVNPMB2, acknowledged the diligent efforts of the EVNPMB2 and the construction contractors in pushing forward the construction progress despite facing various difficulties. So far, the project has completed a significant amount of the set workload and met the requirements of Vietnam Electricity.

Mr. Khuong The Anh requested the EVNPMB2 to continue closely supervising the contractors, expedite the completion of related tasks, and strengthen the workforce and equipment for swift construction progress. However, it is emphasized that quality and safety should not be compromised due to the project's timeline.

The 220kV Bo Y Switching Substation and Interconnection Project:

  • Investor: Vietnam Electricity (EVN)
  • Project Management: The Power Project Management Board 2 (PMB2)
  • Engineering and Supervision Consultant: Power Engineering Consulting Joint Stock Company 4(EVNPECC4)
  • Contractor Consortium: Vietnam Machinery Installation Corporation, PCC4 and TOJI Group Corporation
  • Total Investment: 181 billion VND
  • Location: Ngoc Hoi District, Kon Tum Province
  • Commencement: April 2022
  • Expected Completion: March 2023

Scope:

  • Construction of a new 220kV Bo Y Switching Substation, consisting of 10 bays (6 bays to be installed in this phase).
  • Construction of a 6km-long 220kV transmission line (double circuit) connecting the 220kV Bo Y Switching Substation to the 220kV transmission line of the Nam Kong 2 and 3 Substations (Laos).
  • Construction of a 0.8km-long 220kV transmission line (4-circuit) connecting the 220kV Bo Y Switching Substation to the 220kV Xekaman 1 (Laos) - Pleiku 2 transmission line

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251892

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4