NEWS & EVENTS

Energization of 220kV Do Luong - Nam Cam transmission line to celebrate the 5th EVNNPT Labor Union Congress

30/11/2025 04:55:46

At 1:05 PM on November 30th 2025, the National Power Transmission Corporation (EVNNPT) and the Central Vietnam Power Project Management Board (CPMB), in coordination with relevant units, successfully energized the 220kV Do Luong - Nam Cam transmission line project, celebrating the 5th EVNNPT Labor Union Congress for the 2025-2030 term.

This is a Class I energy project, with EVNNPT as the investor, CPMB managing and operating the project, and Power Transmission Company 1 taking over operation. The project was approved for investment policy by the People's Committee of Nghe An province, and the investor was approved under Decision No. 123/QD-UBND dated November 11th, 2024.

Representatives from CPMB and related units witnessing the project energization moment

The project was completed more than 1 month ahead of the approved investment schedule. This result was achieved through the determined involvement of local authorities and the joint efforts of the people in areas through which the project passes, along with the strong direction and management of EVNNPT and CPMB, and the efforts of contractors participating in the project.

The 220kV Do Luong - Nam Cam transmission line project was constructed in the communes of Thuan Trung, Bach Ha, Van Kieu, Phuc Loc, Thuan Linh, Nghi Loc, and Yen Trung in Nghe An province. 

The 220kV Do Luong - Nam Cam transmission line project was completed more than 1 month ahead of the approved investment schedule

The project scale includes construction of 2 circuits of 220kV transmission line from 220kV Do Luong  Substation to 220kV  Nam Cam Substation with a length of approximately 37 km. Specifically, the section from G4 - G6 (route length approximately 4 km) was constructed with 04 circuits to combine with the 2 circuits of the 110kV Do Luong - Nam Dan transmission line. The bay expansion section at 220kV  Do Luong Substation will install equipment for 2 bays of 220kV in the  220kV Do Luong Substation (existing) and connect the information system for the 220kV Do Luong - Nam Cam transmission line.

The 220kV Do Luong - Nam Cam transmission line project was completed more than 1 month ahead of the approved investment schedule

Upon completion, the project will meet the electricity demand for loads in the Central region, where a number of important existing and future industrial loads of Nghe An province are concentrated, contributing to promoting the socio-economic development of Nghe An province. The project strengthens the power grid connection between Northern Vietnam and Laos, contributing to resolving the power supply tension in the Northern region; Supporting transmission lines in the region to enhance safe and stable operation capability for the National power system; Reducing power losses in the transmission grid, increasing business production efficiency of EVN and EVNNPT.

The 220kV Do Luong - Nam Cam transmission line project was completed more than 1 month ahead of the approved investment schedule

The completion of the project is a practical action by EVNNPT and CPMB to celebrate the 5th EVNNPT Labor Union Congress for the 2025-2030 term. The Congress takes place on November 30th - December 1st, 2025, in Hanoi.

NPT.COM.VN

220kV Do Luong - Nam Cam Transmission Line Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management: Central Vietnam Power Project Management Board (CPMB);
  • Operating Unit: Power Transmission Company 1;
  • Supervision Consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • The project consists of 2 circuits of 220kV transmission line from 220kV Do Luong  Substation to 220kV Nam Cam  Substation with a length of approximately 37km, along with bay expansion items at 220kV Do Luong  Substation and information system connection for the 220kV Do Luong - Nam Cam transmission line.

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096778

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice