Energization of 220kV Do Luong - Nam Cam transmission line to celebrate the 5th EVNNPT Labor Union Congress

30/11/2025 04:55:46

At 1:05 PM on November 30th 2025, the National Power Transmission Corporation (EVNNPT) and the Central Vietnam Power Project Management Board (CPMB), in coordination with relevant units, successfully energized the 220kV Do Luong - Nam Cam transmission line project, celebrating the 5th EVNNPT Labor Union Congress for the 2025-2030 term.

This is a Class I energy project, with EVNNPT as the investor, CPMB managing and operating the project, and Power Transmission Company 1 taking over operation. The project was approved for investment policy by the People's Committee of Nghe An province, and the investor was approved under Decision No. 123/QD-UBND dated November 11th, 2024.

Representatives from CPMB and related units witnessing the project energization moment

The project was completed more than 1 month ahead of the approved investment schedule. This result was achieved through the determined involvement of local authorities and the joint efforts of the people in areas through which the project passes, along with the strong direction and management of EVNNPT and CPMB, and the efforts of contractors participating in the project.

The 220kV Do Luong - Nam Cam transmission line project was constructed in the communes of Thuan Trung, Bach Ha, Van Kieu, Phuc Loc, Thuan Linh, Nghi Loc, and Yen Trung in Nghe An province. 

The 220kV Do Luong - Nam Cam transmission line project was completed more than 1 month ahead of the approved investment schedule

The project scale includes construction of 2 circuits of 220kV transmission line from 220kV Do Luong  Substation to 220kV  Nam Cam Substation with a length of approximately 37 km. Specifically, the section from G4 - G6 (route length approximately 4 km) was constructed with 04 circuits to combine with the 2 circuits of the 110kV Do Luong - Nam Dan transmission line. The bay expansion section at 220kV  Do Luong Substation will install equipment for 2 bays of 220kV in the  220kV Do Luong Substation (existing) and connect the information system for the 220kV Do Luong - Nam Cam transmission line.

The 220kV Do Luong - Nam Cam transmission line project was completed more than 1 month ahead of the approved investment schedule

Upon completion, the project will meet the electricity demand for loads in the Central region, where a number of important existing and future industrial loads of Nghe An province are concentrated, contributing to promoting the socio-economic development of Nghe An province. The project strengthens the power grid connection between Northern Vietnam and Laos, contributing to resolving the power supply tension in the Northern region; Supporting transmission lines in the region to enhance safe and stable operation capability for the National power system; Reducing power losses in the transmission grid, increasing business production efficiency of EVN and EVNNPT.

The 220kV Do Luong - Nam Cam transmission line project was completed more than 1 month ahead of the approved investment schedule

The completion of the project is a practical action by EVNNPT and CPMB to celebrate the 5th EVNNPT Labor Union Congress for the 2025-2030 term. The Congress takes place on November 30th - December 1st, 2025, in Hanoi.

NPT.COM.VN

220kV Do Luong - Nam Cam Transmission Line Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management: Central Vietnam Power Project Management Board (CPMB);
  • Operating Unit: Power Transmission Company 1;
  • Supervision Consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • The project consists of 2 circuits of 220kV transmission line from 220kV Do Luong  Substation to 220kV Nam Cam  Substation with a length of approximately 37km, along with bay expansion items at 220kV Do Luong  Substation and information system connection for the 220kV Do Luong - Nam Cam transmission line.

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251358

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4