NEWS & EVENTS

Energization of 220kV Do Luong - Nam Cam transmission line to celebrate the 5th EVNNPT Labor Union Congress

30/11/2025 04:55:46

At 1:05 PM on November 30th 2025, the National Power Transmission Corporation (EVNNPT) and the Central Vietnam Power Project Management Board (CPMB), in coordination with relevant units, successfully energized the 220kV Do Luong - Nam Cam transmission line project, celebrating the 5th EVNNPT Labor Union Congress for the 2025-2030 term.

This is a Class I energy project, with EVNNPT as the investor, CPMB managing and operating the project, and Power Transmission Company 1 taking over operation. The project was approved for investment policy by the People's Committee of Nghe An province, and the investor was approved under Decision No. 123/QD-UBND dated November 11th, 2024.

Representatives from CPMB and related units witnessing the project energization moment

The project was completed more than 1 month ahead of the approved investment schedule. This result was achieved through the determined involvement of local authorities and the joint efforts of the people in areas through which the project passes, along with the strong direction and management of EVNNPT and CPMB, and the efforts of contractors participating in the project.

The 220kV Do Luong - Nam Cam transmission line project was constructed in the communes of Thuan Trung, Bach Ha, Van Kieu, Phuc Loc, Thuan Linh, Nghi Loc, and Yen Trung in Nghe An province. 

The 220kV Do Luong - Nam Cam transmission line project was completed more than 1 month ahead of the approved investment schedule

The project scale includes construction of 2 circuits of 220kV transmission line from 220kV Do Luong  Substation to 220kV  Nam Cam Substation with a length of approximately 37 km. Specifically, the section from G4 - G6 (route length approximately 4 km) was constructed with 04 circuits to combine with the 2 circuits of the 110kV Do Luong - Nam Dan transmission line. The bay expansion section at 220kV  Do Luong Substation will install equipment for 2 bays of 220kV in the  220kV Do Luong Substation (existing) and connect the information system for the 220kV Do Luong - Nam Cam transmission line.

The 220kV Do Luong - Nam Cam transmission line project was completed more than 1 month ahead of the approved investment schedule

Upon completion, the project will meet the electricity demand for loads in the Central region, where a number of important existing and future industrial loads of Nghe An province are concentrated, contributing to promoting the socio-economic development of Nghe An province. The project strengthens the power grid connection between Northern Vietnam and Laos, contributing to resolving the power supply tension in the Northern region; Supporting transmission lines in the region to enhance safe and stable operation capability for the National power system; Reducing power losses in the transmission grid, increasing business production efficiency of EVN and EVNNPT.

The 220kV Do Luong - Nam Cam transmission line project was completed more than 1 month ahead of the approved investment schedule

The completion of the project is a practical action by EVNNPT and CPMB to celebrate the 5th EVNNPT Labor Union Congress for the 2025-2030 term. The Congress takes place on November 30th - December 1st, 2025, in Hanoi.

NPT.COM.VN

220kV Do Luong - Nam Cam Transmission Line Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management: Central Vietnam Power Project Management Board (CPMB);
  • Operating Unit: Power Transmission Company 1;
  • Supervision Consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • The project consists of 2 circuits of 220kV transmission line from 220kV Do Luong  Substation to 220kV Nam Cam  Substation with a length of approximately 37km, along with bay expansion items at 220kV Do Luong  Substation and information system connection for the 220kV Do Luong - Nam Cam transmission line.

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827113

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice