NEWS & EVENTS

Energization of 500kV circuit-3 Nam Dinh 1 – Pho Noi transmission line

20/08/2024 14:34:13

At 17:30, August 19th 2024, the National Power Transmission Corporation, the Northern Power Project Management Board (NPMB) coordinated with relevant units to successfully energize 2 circuits of 500kV circuir-3 transmission line, Nam Dinh 1 - Pho Noi section.

The completion and energization of the 500kV Nam Dinh 1 TPP - Pho Noi transmission line meeting the requirements and instructions of the Prime Minister is a great motivation for the entire construction site of the 500kV circuit-3 transmission line project to complete acceptance and inauguration in the coming days according to the direction of the Prime Minister.

The 500kV Nam Dinh 1 TPP - Pho Noi transmission line project is approximately 127km long, passing through the provinces of Nam Dinh, Thai Binh, Hai Duong and Hung Yen, including 334 foundation locations and 144 anchor spans. The project was implemented from January 18th 2024 and was agreed to be energized by the Investor's Acceptance Council on August 16th 2024.

Leaders of EVNNPT, NPMB and related units witnessed the moment of energizing the 500kV Nam Dinh 1 TPP - Pho Noi transmission line project

During the implementation process, the project has always received the attention and direction of the Prime Minister, ministries, sectors and leaders of Vietnam Electricity. Along with that is the support of authorities at all levels where the project passes through; the consensus and joint efforts of the people who have given up land for the project and participated in supporting the construction of the foundation excavation phase.

According to the leaders of EVNNPT, in addition to favorable factors, the project implementation process encountered many difficulties and challenges. One of them is that the transmission line passes through many areas of ponds, fields, and crosses many large rivers, so the weak geology requires the construction of 109 pile foundation locations. The total length of piles driven is about 500,000 meters. In addition, due to many anchor spans, there are many 2-leg tower locations, which takes more time to construct. The line has 4 tower locations with a height of 145 meters (the entire circuit-3 transmission line has 7 similar tower locations), weighing more than 400 tons. These are river crossings, and construction encountered many difficulties due to rain and wind conditions.

The 500kV circuit-3 transmission line, Nam Dinh I TPP - Pho Noi section was completed and energized on the afternoon of August 19th 2024

Along with that, the massive steel production posed a significant risk that exceeded the capabilities of the manufacturers. In response, EVNNPT together with NPMB and contractors have worked hard, implementing specific solutions to speed up the production progress.

Strictly following the Prime Minister's directive with the spirit of "only discussing work, not delays", "overcoming the heat, conquering rain", working "3 shifts, 4 teams", "eat up, sleep quickly", engineers and workers of the units participating in the project have worked with the highest spirit and responsibility to bring the project to the finish line on time.

Also, according to the leader of EVNNPT, in order to meet the progress as directed by the Prime Minister, in a short period of time, many work items have been deployed simultaneously such as construction and installation, erection, wire pulling, installation of positioning frames, technical calibration. Therefore, in addition to the main workforce of EVNNPT units and construction contractors, EVN has called on and mobilized 5 Power Generation Joint Stock Corporations to participate in supporting the construction with a large number of qualified, experienced and skilled workers. Additionally, EVN also received support from Viettel Group, Vietnam Oil and Gas Group, Vietnam Posts and Telecommunications Group... to participate in supporting the construction of tower and wire pulling.

Furthermore, implementing the direction of the Prime Minister, the provincial Youth Unions where the 500kV circuit-3 transmission line project passes through have coordinated with EVN/EVNNPT to establish teams with thousands of volunteer youth union members. The focus is to work with local authorities to propagate and mobilize people to hand over the route corridor; support the demolition of houses and cutting down trees in the corridor; support traffic regulation when pulling wires across traffic crossings; encourage and give gifts to boost the spirit of workers at the construction site.

The project, once completed, will help reduce the load and avoid overloading of existing 500kV transmission lines, ensuring the N-1 criterion. The line also helps to increase the stable transmission reserve on the North-Central interface, combined with the 500kV Quang Trach - Quynh Luu - Thanh Hoa - Nam Dinh 1 sections, contributing to supplementing capacity from power sources in the North Central region to the load center in the North.

The 500kV circuit-3 Nam Dinh 1 TPP - Pho Noi transmission line project:

- Project investor: National Power Transmission Corporation (under EVN);

- Investor representative: Northern Power Project Management Board;

- Engineering entities: Consortium of Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) and Power Engineering Consulting Joint Stock Company 2;

- Operator: Power Transmission Company 1;

- This is a special energy project, group A;

- Commencement date: January 18th 2024;

- Energization date: August 19th 2024.

Refer here for more information of the 500kV circuit-3 Quang Trach - Pho Noi transmission line. 

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3252042

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4