NEWS & EVENTS

Energization of the 220kV Van Ninh substation and connecting transmission line project, practically celebrating the success of EVN's 4th Party Congress

21/08/2025 15:14:24

On August 16th 2025, National Power Transmission Corporation (EVNNPT) and Power Transmission Project Management Board (NPTPMB) coordinated with related units to energize the 220kV Van Ninh Substation and connecting transmission line project, thereby helping to strengthen power supply assurance for Khanh Hoa province.

The completion and energization of the project is a practical action by EVNNPT and NPTPMB to celebrate the success of the 4th Congress of the Party Committee of Vietnam Electricity for the 2025-2030 term, celebrating the 80th anniversary of the August Revolution and National Day September 2nd.

Earlier, on August 14th 2025, Mr. Nguyen Ngoc Tan - Deputy General Director of EVNNPT, Chairman of the project owner-level acceptance council, chaired the council meeting, where council members unanimously agreed to energize the project.

Overview of the 220kV Van Ninh Substation

The project is owned by National Power Transmission Corporation (EVNNPT), managed and operated by NPTPMB, and handed over for operation to Power Transmission Company 3.

The project is built in Suoi Hang hamlet, Tu Bong commune, Khanh Hoa province.

The project has a scale of installing 01 transformer 220/110/22kV - 250MVA. The 220kV side uses a double busbar scheme with bypass busbar, including 10 bays. In this phase, equipment is installed for 06 bays (04 outgoing bays, 01 incoming bay and 01 bus coupler bay), using a double busbar system scheme. Reserve 01 bypass bay, 01 incoming bay for 250MVA transformer and 02 outgoing bays.

AT1 transformer at 220kV Van Ninh Substation

The 110kV side uses a double busbar scheme, including 15 bays. In this phase, equipment is installed for connection of 06 bays (04 outgoing bays, 01 incoming bay, 01 bus coupler bay). Reserve 06 outgoing bays, 01 incoming bay for 250MVA transformer, 01 bypass bay and 01 capacitor bay.

The 22kV side uses a unit scheme, with outdoor installed equipment to supply auxiliary power through the station's auxiliary transformer. The control, protection and measurement, communication and SCADA systems are equipped with integrated control systems using computers in accordance with EVN and EVNNPT regulations, protection and measurement equipment in accordance with current regulations.

For the connecting transmission line section, a 220kV transmission line, 04 circuits, approximately 250m long is built to connect to the 220kV Tuy Hoa - Nha Trang transmission line.

During implementation, the project faced many difficulties and challenges due to weather conditions with heavy rain. However, with close direction from EVNNPT leadership, along with the efforts of units participating in the project, the project has now been completed and energized meeting the set schedule.

Delegates witness the moment of project energization

After completion, the project has very important significance to meet load demand and ensure operation for 110kV substations in the region, especially providing power supply to Van Phong Economic Zone loads, ensuring stable power supply to meet the socio-economic development needs of Khanh Hoa province. Ensuring safe operation of power supply to loads in the northern region of Khanh Hoa province without overloading 110kV transmission lines and voltage drops below allowable voltage levels at 110kV stations in these areas in case of incidents on related 110kV transmission line circuits.

NPTPMB leadership together with fire prevention and fighting forces of Khanh Hoa Provincial Police took commemorative photos after successful project energization

NPT.COM.VN

Some images of EVNPECC4 participating in supervision and acceptance council meetings for energization of the 220kV Van Ninh Substation and connecting transmission line project:

220kV Van Ninh Substation and connecting transmission line project:

  • Project investor: National Power Transmission Corporation (EVNNPT);
  • Project management and operation: Power Transmission Project Management Board (NPTPMB);
  • Operating unit: Power Transmission Company 3;
  • Engineering and supervision unit: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Scale: installation of 01 transformer 220/110/22kV - 250MVA. The 220kV side uses a double busbar scheme with bypass busbar, including 10 bays. In this phase, equipment is installed for 06 bays (04 outgoing bays, 01 incoming bay and 01 bus coupler bay), using a double busbar system scheme. Reserve 01 bypass bay, 01 incoming bay for 250MVA transformer and 02 outgoing bays.

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827233

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice