NEWS & EVENTS

Energization of the 220kV Van Ninh substation and connecting transmission line project, practically celebrating the success of EVN's 4th Party Congress

21/08/2025 15:14:24

On August 16th 2025, National Power Transmission Corporation (EVNNPT) and Power Transmission Project Management Board (NPTPMB) coordinated with related units to energize the 220kV Van Ninh Substation and connecting transmission line project, thereby helping to strengthen power supply assurance for Khanh Hoa province.

The completion and energization of the project is a practical action by EVNNPT and NPTPMB to celebrate the success of the 4th Congress of the Party Committee of Vietnam Electricity for the 2025-2030 term, celebrating the 80th anniversary of the August Revolution and National Day September 2nd.

Earlier, on August 14th 2025, Mr. Nguyen Ngoc Tan - Deputy General Director of EVNNPT, Chairman of the project owner-level acceptance council, chaired the council meeting, where council members unanimously agreed to energize the project.

Overview of the 220kV Van Ninh Substation

The project is owned by National Power Transmission Corporation (EVNNPT), managed and operated by NPTPMB, and handed over for operation to Power Transmission Company 3.

The project is built in Suoi Hang hamlet, Tu Bong commune, Khanh Hoa province.

The project has a scale of installing 01 transformer 220/110/22kV - 250MVA. The 220kV side uses a double busbar scheme with bypass busbar, including 10 bays. In this phase, equipment is installed for 06 bays (04 outgoing bays, 01 incoming bay and 01 bus coupler bay), using a double busbar system scheme. Reserve 01 bypass bay, 01 incoming bay for 250MVA transformer and 02 outgoing bays.

AT1 transformer at 220kV Van Ninh Substation

The 110kV side uses a double busbar scheme, including 15 bays. In this phase, equipment is installed for connection of 06 bays (04 outgoing bays, 01 incoming bay, 01 bus coupler bay). Reserve 06 outgoing bays, 01 incoming bay for 250MVA transformer, 01 bypass bay and 01 capacitor bay.

The 22kV side uses a unit scheme, with outdoor installed equipment to supply auxiliary power through the station's auxiliary transformer. The control, protection and measurement, communication and SCADA systems are equipped with integrated control systems using computers in accordance with EVN and EVNNPT regulations, protection and measurement equipment in accordance with current regulations.

For the connecting transmission line section, a 220kV transmission line, 04 circuits, approximately 250m long is built to connect to the 220kV Tuy Hoa - Nha Trang transmission line.

During implementation, the project faced many difficulties and challenges due to weather conditions with heavy rain. However, with close direction from EVNNPT leadership, along with the efforts of units participating in the project, the project has now been completed and energized meeting the set schedule.

Delegates witness the moment of project energization

After completion, the project has very important significance to meet load demand and ensure operation for 110kV substations in the region, especially providing power supply to Van Phong Economic Zone loads, ensuring stable power supply to meet the socio-economic development needs of Khanh Hoa province. Ensuring safe operation of power supply to loads in the northern region of Khanh Hoa province without overloading 110kV transmission lines and voltage drops below allowable voltage levels at 110kV stations in these areas in case of incidents on related 110kV transmission line circuits.

NPTPMB leadership together with fire prevention and fighting forces of Khanh Hoa Provincial Police took commemorative photos after successful project energization

NPT.COM.VN

Some images of EVNPECC4 participating in supervision and acceptance council meetings for energization of the 220kV Van Ninh Substation and connecting transmission line project:

220kV Van Ninh Substation and connecting transmission line project:

  • Project investor: National Power Transmission Corporation (EVNNPT);
  • Project management and operation: Power Transmission Project Management Board (NPTPMB);
  • Operating unit: Power Transmission Company 3;
  • Engineering and supervision unit: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Scale: installation of 01 transformer 220/110/22kV - 250MVA. The 220kV side uses a double busbar scheme with bypass busbar, including 10 bays. In this phase, equipment is installed for 06 bays (04 outgoing bays, 01 incoming bay and 01 bus coupler bay), using a double busbar system scheme. Reserve 01 bypass bay, 01 incoming bay for 250MVA transformer and 02 outgoing bays.

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096907

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice