Energization of the 220kV Vung Ang substation and connection line project

28/10/2025 19:08:21

With the successful energization of the 220kV connection line on October 25th, the National Power Transmission Corporation (EVNNPT) has officially completed the entire 220kV Vung Ang substation and connection line project (Ha Tinh Province).

The 220kV Vung Ang Substation is located in Trai Hamlet, Vung Ang Ward, Ha Tinh Province. The substation is designed for a capacity of two 250MVA transformers by 2030; in this phase, one 125MVA transformer has been installed. It is designed with three voltage levels: 220kV, 110kV, and 22kV. The connection line is 13.4 km long, passing through Vung Ang Ward and Song Tri Ward, Ha Tinh Province.

The 220kV Vung Ang Substation and connection line viewed from above. Photo: Le Linh

The 220kV Vung Ang Substation was energized on September 21st, 2025. However, the 220kV connection line encountered several obstacles during construction, as some households intentionally opposed and obstructed the contractor’s stringing work in the anchor span 06–08, which is about 600 meters long. The Ha Tinh Provincial authorities mobilized protection forces to support construction, demonstrating the province’s determination in implementing this key local project.

Upon completion, the 220kV Vung Ang substation and connection line project plays an important role in ensuring electricity supply for many critical loads in Ha Tinh Province, particularly the Vung Ang Economic Zone, which hosts several key industrial zones and manufacturing plants of the locality. The project also helps release the generation capacity of the Vung Ang Thermal Power Plant, reduces power losses, ensures operational safety of the power system, and enhances reliability and power supply quality — serving the province’s socio-economic and political development.

This project is also listed among EVN’s key urgent projects selected by the Vietnam General Confederation of Labour and the Vietnam Electricity (EVN) to promote the emulation campaign for energization completion in 2025. 

The project is invested by EVNNPT, managed and supervised on behalf of the investor by the Central Power Projects Management Board (CPMB), and will be operated by Power Transmission Company No.1 upon completion.

EVN.COM.VN

220kV Vung Ang substation and connection line project (Ha Tinh Province)

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management and Operation: Central Power Projects Management Board (CPMB);
  • Scope of work by Power Engineering Consulting Joint Stock Company 4 (EVNPECC4): Implementation of Package No. 1 under Consulting Contract No. 23/2021/HDTV-CPMB dated April 6th 2021: “Consulting services for surveys serving the preparation of Technical design and total cost estimate; preparation of  Technical design, detailed design, and bidding documents; environmental monitoring during construction; measurement and preparation of land parcel documents serving site clearance and compensation for the 220kV Vung Ang substation and connection line Project.” The contract was signed between CPMB and EVNPECC4.
  • The 220kV Vung Ang Substation is located in Trai Hamlet, Vung Ang Ward, Ha Tinh Province. The substation is designed for a capacity of two 250MVA transformers by 2030; in this phase, one 125MVA transformer has been installed. It includes three voltage levels: 220kV, 110kV, and 22kV. The 13.4 km connection line runs through Vung Ang Ward and Song Tri Ward, Ha Tinh Province.

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096772

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice