With the successful energization of the 220kV connection line on October 25th, the National Power Transmission Corporation (EVNNPT) has officially completed the entire 220kV Vung Ang substation and connection line project (Ha Tinh Province).

The 220kV Vung Ang Substation is located in Trai Hamlet, Vung Ang Ward, Ha Tinh Province. The substation is designed for a capacity of two 250MVA transformers by 2030; in this phase, one 125MVA transformer has been installed. It is designed with three voltage levels: 220kV, 110kV, and 22kV. The connection line is 13.4 km long, passing through Vung Ang Ward and Song Tri Ward, Ha Tinh Province.

The 220kV Vung Ang Substation and connection line viewed from above. Photo: Le Linh

The 220kV Vung Ang Substation was energized on September 21st, 2025. However, the 220kV connection line encountered several obstacles during construction, as some households intentionally opposed and obstructed the contractor’s stringing work in the anchor span 06–08, which is about 600 meters long. The Ha Tinh Provincial authorities mobilized protection forces to support construction, demonstrating the province’s determination in implementing this key local project.

Upon completion, the 220kV Vung Ang substation and connection line project plays an important role in ensuring electricity supply for many critical loads in Ha Tinh Province, particularly the Vung Ang Economic Zone, which hosts several key industrial zones and manufacturing plants of the locality. The project also helps release the generation capacity of the Vung Ang Thermal Power Plant, reduces power losses, ensures operational safety of the power system, and enhances reliability and power supply quality — serving the province’s socio-economic and political development.

This project is also listed among EVN’s key urgent projects selected by the Vietnam General Confederation of Labour and the Vietnam Electricity (EVN) to promote the emulation campaign for energization completion in 2025. 

The project is invested by EVNNPT, managed and supervised on behalf of the investor by the Central Power Projects Management Board (CPMB), and will be operated by Power Transmission Company No.1 upon completion.

EVN.COM.VN

220kV Vung Ang substation and connection line project (Ha Tinh Province)

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management and Operation: Central Power Projects Management Board (CPMB);
  • Scope of work by Power Engineering Consulting Joint Stock Company 4 (EVNPECC4): Implementation of Package No. 1 under Consulting Contract No. 23/2021/HDTV-CPMB dated April 6th 2021: “Consulting services for surveys serving the preparation of Technical design and total cost estimate; preparation of  Technical design, detailed design, and bidding documents; environmental monitoring during construction; measurement and preparation of land parcel documents serving site clearance and compensation for the 220kV Vung Ang substation and connection line Project.” The contract was signed between CPMB and EVNPECC4.
  • The 220kV Vung Ang Substation is located in Trai Hamlet, Vung Ang Ward, Ha Tinh Province. The substation is designed for a capacity of two 250MVA transformers by 2030; in this phase, one 125MVA transformer has been installed. It includes three voltage levels: 220kV, 110kV, and 22kV. The 13.4 km connection line runs through Vung Ang Ward and Song Tri Ward, Ha Tinh Province.

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251337

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4