Energization of the 500kV Quang Trach - Doc Soi Transmission Line (Circuit 3)

02/06/2022 00:00:00

At 19:19 on May 31st, the National Power Transmission Company (EVNNPT) and the Central Power Project Management Board (EVNCPMB) coordinated with relevant units to energize the 500kV Quang Trach - Doc Soi transmission line (circuit 3) and the 500kV Quang Trach Distribution Yard.

The 500kV Quang Trach - Doc Soi Transmission Line in Quang Binh Province

The 500kV Quang Trach - Doc Soi transmission line project, along with the 500kV Quang Trach Distribution Yard, are part of the 500kV transmission line project circuit 3 (Vung Ang - Quang Trach - Doc Soi - Pleiku 2).

The project is invested by EVNNPT, with EVNCPMB managing the project. The joint venture between Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) and the Energy Institute - Power Engineering Consulting Joint Stock Company No 1 provides engineering consulting. Power Transmission Company No.2 provides supervision and operational acceptance.

According to EVNNPT, the energization of the project holds significant importance in enhancing the 500kV power transmission capacity of the national grid system, capacity releasing for renewable energy sources in the region, and ensuring power supply for the southern region, Quang Binh, Quang Tri, Thua Thien Hue, Quang Nam, Quang Ngai, Da Nang, and surrounding areas.

The completion of this project also acts as a driving force to accelerate the progress of the entire 500kV transmission line project (circuit 3).

Mr. Bui Van Kien, Deputy General Director of EVNNPT, stated that the project implementation encountered various objective factors, such as COVID-19 outbreaks in 2020 and 2021, floods in 2020, land clearance and compensation difficulties.

The moment of energizing the 500kV transmission line Quang Trach - Doc Soi (single circuit) at 16h35 May 31st

The project has received regular attention and guidance from the Government, the Prime Minister, ministries, departments, the National Steering Committee for Power Development, and Vietnam Electricity in addressing and resolving obstacles related to land clearance.

The strong involvement of local authorities along the transmission line route has provided the necessary ground for the project implementation.

EVNNPT, EVNCPMB and specialized departments have been present on-site to focus on construction management, problem-solving, and timely handling of any difficulties that arise during the construction process. In some cases, there were reinforcements, additional workforce, equipment for the cable-pulling teams, and timely mobilization of materials during construction process.

During the technical and transmission line corridor acceptance, EVNNPT coordinated with the supervision and engineering consulting units with the principle of "where the construction goes, the acceptance must be completed." Completing the cable-pulling work signifies fulfilling the conditions for energizing and operating the project.

After completing the 500kV Quang Trach - Doc Soi transmission line project, EVNNPT and EVNCPMB will continue allocating resources to complete the remaining 500kV transmission line (circuit 3), the Vung Ang - Quang Trach section.

Source: baochinhphu.vn

Related article

APPRECIATION LETTER 50 YEARS OF COMPANIONSHIP - TRUST BUILDING

APPRECIATION LETTER 50 YEARS OF COMPANIONSHIP - TRUST BUILDING

Dear Valued Clients, Partners and Shareholders On the occasion of the 50th Anniversary of Power Engineering Consulting Joint Stock Company 4 (PECC4), We would like to extend our heartfelt gratitude for your trust, partnership, and invaluable support throughout our journey of growth and development.

French Embassy and AFD visited 500kV Binh Duong 1 substation, recognizing successful cooperation with EVNNPT

French Embassy and AFD visited 500kV Binh Duong 1 substation, recognizing successful cooperation with EVNNPT

Recently, a delegation from the French Embassy in Vietnam and the French Development Agency (AFD) held a working session with the National Power Transmission Corporation (EVNNPT) and visited the 500kV Binh Duong 1 Substation.

Training on the BIM Software Ecosystem for EVNPECC4's Professional Consulting Engineers

Training on the BIM Software Ecosystem for EVNPECC4's Professional Consulting Engineers

Continuing its efforts to provide training and enhance the skills required to use software supporting surveying and engineering consulting activities, on 19th June 2026, Power Engineering Consulting Joint Stock Company No. 4 (EVNPECC4) signed a training contract with the Research and Development of Software in Construction (RDSIC) under the Hanoi University of Civil Engineering to organize Building Information Modeling (BIM) training courses for EVNPECC4's professional consulting engineers.

PRESS RELEASE

PRESS RELEASE

To: Valued Customers, Partners, Shareholders, Investors, and Employees of Power Engineering Consulting Joint Stock Company 4 (PECC4)

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2927442

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice