NEWS & EVENTS

Energization of the first 220kV GIS substation project in Danang City

01/10/2024 08:27:36

At 20:37 on September 30th 2024, the Central Power Projects Management Board (CPMB), in coordination with relevant units, successfully energized the 220kV Hai Chau substation and 220kV Hoa Khanh – Hai Chau transmission line project. This is the first GIS substation project of Danang City to be completed and energized.

The 220kV Hai Chau substation and 220kV Hoa Khanh – Hai Chau transmission line project was implemented in Danang City, invested by National Power Transmission Corporation (EVNNPT), managed by CPMB, and operated by Power Transmission Company 2.   Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) is the engineering consultant for the project. Accordingly, Substation Engineering Centre - EVNPECC4 applied BIM model for engineering the project.

Representatives of CPMB and relevant units witnessed the energizing moment of 220kV Hai Chau Substation

The project involves constructing a new 220/110/22kV GIS substation with an installed capacity of 2x250MVA, with one 250MVA transformer installed in this phase. It also includes the construction of 220kV double-circuit Hoa Khanh - Hai Chau transmission line, which is nearly 10 km long. Of this, the underground cable section is over 7.3 km long (it is also the first underground cable line in Danang City) and the overhead line section is nearly 2.6 km long. Additionally, a 22kV underground cable (121m long) is built to supply power to the 220kV Hai Chau substation.

During implementation, the project faced numerous difficulties and obstacles related to land clearance and compensation, especially for the 220kV Hai Chau substation due to a business entity's delay in handing over the land for construction. The overhead and underground 220kV transmission lines also encountered difficulties related to compensation plans and land prices. Moreover, the project faced obstacles related to the intersection of transportation routes, leading to significant delays in land handover. The construction process was also hindered by the pandemic, natural disasters such as storms, and prolonged floods, …

3D image of 220kV Hai Chau Substation
220kV Hai Chau Substation

However, thanks to the close direction of National Power Transmission Corporation’s leaders, the support of local authorities and people in the project areas, as well as the efforts of CPMB and participating units, the project was completed on schedule.

The completion of the project helps to enhance the power supply capacity, meet the load growth demand of Danang City, and strengthen the interconnection, improve the safety, reliability, stability in operation, and power quality. The project helps to meet the N-1 criterion and reduce power losses of the regional power system.

Previously, the investor-level acceptance council had a meeting and agreed to energize the project

It is known that GIS substations, which include gas-insulated switchgear (GIS) using SF6 gas, are an advanced technology that is widely applied in many countries worldwide. The advantages of GIS substations include saving space, reducing land and equipment costs, ensuring safe operation, and extending maintenance intervals.

220kV Hai Chau Substation and 220kV Hoa Khanh – Hai Chau transmission line project

Investor: National Power Transmission Corporation (EVNNPT)

Management: Central Power Projects Management Board (CPMB)

Operation: Power Transmission Company 2

Scale: constructing a new 220/110/22kV GIS substation with an installed capacity of 2x250MVA, with one 250MVA transformer installed in this phase. It also includes the construction of 220kV double-circuit Hoa Khanh - Hai Chau transmission line, which is nearly 10 km long. Of this, the underground cable section is over 7.3 km long (it is also the first underground cable line in Danang City) and the overhead line section is nearly 2.6 km long. Additionally, a 22kV underground cable (121m long) is built to supply power to the 220kV Hai Chau substation.

Engineering consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4)

EVNPECC4 ’s video in applying BIM model for engineering 220kV Hai Chau substation and 220kV Hoa Khanh - Hai Chau transmission line:

NPT.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097143

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice