Energizing 220kV Dak Ooc switching substation to support electricity import from Laos to Vietnam

29/05/2024 16:29:26

At 11:37am on May 28th, Power Project Management Board 2 in coordination with relevant units energized the 220kV Dak Ooc switching substation, to facilitate the grid connection from Nam Emoun Hydropower Plant (Laos) to the Vietnamese power system.

The 220kV Dak Ooc switching substation is part of the 220kV Dak Ooc switching substation and 220kV transmission lines project to connect the Nam Emoun Hydropower Plant to the Vietnamese power system.

The Dak Ooc switching substation is located in La Dee commune, Nam Giang district, Quang Nam province. The substation has a construction scale of 10 bays of 220kV, with equipment installation for 6 bays in this phase.

The project is invested by EVN, with the Power Project Management Board 2 (EVNPMB2) representing the investor to manage the project. Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in implementing Package No. 05 (TV-04): Consulting on technical design and construction cost estimation appraisal; Construction supervision consulting for the 220kV Dak Ooc switching substation and 220kV transmission lines to connect the Nam Emoun Hydropower Plant (Laos) to the Vietnamese power system.

Mr. Nguyen Duc Minh - Deputy Director of EVNPMB2 (in the middle) directed the energization of the project and presented gifts to encourage the employees

The transmission line connections include: A 220kV double-circuit transmission line (with one circuit strung) from the Nam Emoun Hydropower Plant to the 220kV Dak Ooc switching substation (the section on Vietnamese territory), about 13.4km length; construction of a 4-circuit 220kV transmission line, with a length of about 1.9km from the 220kV Dak Ooc switching substation to the transition point into the existing 220kV Xekaman 3 - Thanh My double-circuit transmission line; construction of a 22kV power supply line for construction and self-consumption from the local grid to the 220kV Dak Ooc switching substation, about 1.077km length.

220kV Dak Ooc switching substation

Starting construction on July 25th, 2022, overcoming many difficulties during the construction process, the 220kV Dak Ooc switching substation project has been successfully energized. It is expected that the transmission line connections will be completed and energized in August 2024.

 EVNPECC4 participated in implementing Package No. 05 (TV-04) during the implementation of the 220kV Dak Ooc switching Substation project

When the project is put into operation, it will contribute to transmitting electricity from the Nam Emoun Hydropower Plant (Laos) to the Vietnamese power system, implementing the energy cooperation policy between the two countries.

EVN.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097152

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice