NEWS & EVENTS

Energizing 220kV Dak Ooc switching substation to support electricity import from Laos to Vietnam

29/05/2024 16:29:26

At 11:37am on May 28th, Power Project Management Board 2 in coordination with relevant units energized the 220kV Dak Ooc switching substation, to facilitate the grid connection from Nam Emoun Hydropower Plant (Laos) to the Vietnamese power system.

The 220kV Dak Ooc switching substation is part of the 220kV Dak Ooc switching substation and 220kV transmission lines project to connect the Nam Emoun Hydropower Plant to the Vietnamese power system.

The Dak Ooc switching substation is located in La Dee commune, Nam Giang district, Quang Nam province. The substation has a construction scale of 10 bays of 220kV, with equipment installation for 6 bays in this phase.

The project is invested by EVN, with the Power Project Management Board 2 (EVNPMB2) representing the investor to manage the project. Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in implementing Package No. 05 (TV-04): Consulting on technical design and construction cost estimation appraisal; Construction supervision consulting for the 220kV Dak Ooc switching substation and 220kV transmission lines to connect the Nam Emoun Hydropower Plant (Laos) to the Vietnamese power system.

Mr. Nguyen Duc Minh - Deputy Director of EVNPMB2 (in the middle) directed the energization of the project and presented gifts to encourage the employees

The transmission line connections include: A 220kV double-circuit transmission line (with one circuit strung) from the Nam Emoun Hydropower Plant to the 220kV Dak Ooc switching substation (the section on Vietnamese territory), about 13.4km length; construction of a 4-circuit 220kV transmission line, with a length of about 1.9km from the 220kV Dak Ooc switching substation to the transition point into the existing 220kV Xekaman 3 - Thanh My double-circuit transmission line; construction of a 22kV power supply line for construction and self-consumption from the local grid to the 220kV Dak Ooc switching substation, about 1.077km length.

220kV Dak Ooc switching substation

Starting construction on July 25th, 2022, overcoming many difficulties during the construction process, the 220kV Dak Ooc switching substation project has been successfully energized. It is expected that the transmission line connections will be completed and energized in August 2024.

 EVNPECC4 participated in implementing Package No. 05 (TV-04) during the implementation of the 220kV Dak Ooc switching Substation project

When the project is put into operation, it will contribute to transmitting electricity from the Nam Emoun Hydropower Plant (Laos) to the Vietnamese power system, implementing the energy cooperation policy between the two countries.

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251880

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4