Energizing the second component of the 500kV circuit 3 transmission line project

19/06/2024 14:33:10

At 2:35 AM on June 18th 2024, at the 500kV Pho Noi substation, The Northern Vietnam Power Projects Management Board (NPMB) collaborated with related units to successfully energize the expansion of bays 585 and 586 at the 500kV Pho Noi substation and the transmission line section from the two expanded bays to position 319 of the 500kV circuit 3 transmission line project, Nam Dinh I TPP - Pho Noi section, two days ahead of the schedule required by EVNNPT.

Project participating units witnessed the energization moment at the 500kV Pho Noi substation

The bay expansion component at the 500kV Pho Noi substation is part of the 500kV Nam Dinh I TPP - Pho Noi transmission line project, which is invested by the National Power Transmission Corporation (EVNNPT) and managed by NPMB on behalf of EVNNPT.

The engineering consulting component was undertaken by Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) ); Minh Quang Mechanical Electrical Joint Stock Company was responsible for construction and equipment installation; National Power Transmission Services Company handled computer configuration, and Power Transmission Company 1 served as the electrical supervision consultant and will be the operating unit.

The bay expansion component at the 500kV Pho Noi substation was constructed on the reserve land area for two 500kV transmission line bays within the existing 500kV Pho Noi Substation premises.

Overview of the 500kV Pho Noi substation and the bay expansion section

The energization of the bay expansion component at the 500kV Pho Noi substation prepares for the energization of 2 circuits of the 500kV circuit 3 transmission line, Nam Dinh I TPP - Pho Noi section, aimed at strengthening power system interconnection, enhancing stability, and ensuring safe power supply. Additionally, it helps increase stability reserve on the North-Central interface, combined with the 500kV circuit 3 transmission line, Quang Trach - Quynh Luu - Thanh Hoa - Nam Dinh I TPP section, contributing to creating a strong link from the power source centers in North Central Vietnam to the load centers in the Northern region. This is an important basis for safe, reliable, stable, and optimal operation of the power system, helping to reduce power system operation costs; Transmitting power from thermal power plants in the North Central region as well as renewable energy plants in the North Central and surrounding areas into the national power system, supplying electricity to load centers in the Northern region.

This is the second component of the 500kV circuit 3 transmission line project to be energized (the first was the expansion of the 500kV Quang Trach substation). The completion of this component is an important motivation for the entire construction site to be determined to complete the 500kV circuit 3 transmission line project, meeting the directive requirements of the Prime Minister.

Previously, on June 16th 2024, the Investor's Acceptance Council met to agree on the energization plan for the bay expansion component at the 500kV Pho Noi substation
The bay expansion component at the 500kV Pho Noi substation at night

Video of the Morning Financial Business News - June 18th, 2024 (VTV) reporting on the energization of the second component of the 500kV circuit 3 transmission line project can be viewed here.

Energization of the Reactor and Capacitor Installation Project to ensure the loading capacity of the 500kV circuit 3 transmission lines from Quang Trach to Pho Noi, at the 500kV Pho Noi substation

Along with energizing the expanded bay section to position 319 of the 500kV circuit 3 transmission line project, Nam Dinh I TPP - Pho Noi section, the Reactor and Capacitor Installation Project to ensure the loading capacity of the 500kV circuit 3 transmission lines from Quang Trach to Pho Noi, with the component of installing 02 500kV - 128MVAr reactors at the 500kV Pho Noi substation, was also successfully energized and put into operation.

The component is invested by EVNNPT, with Power Transmission Company 1 representing EVNNPT in project management, EVNPECC4 responsible for engineering; National Power Transmission Services Company handling construction, equipment installation, and computer configuration, and EVN International Joint Stock Company (EVNINTERNATIONAL) as the supervision consultant.

Overview of 02 reactors installed at the 500kV Pho Noi substation

EVNPECC4 - Substation Engineering Centre 

NPT.COM.VN

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827402

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice