NEWS & EVENTS

Energizing the second component of the 500kV circuit 3 transmission line project

19/06/2024 14:33:10

At 2:35 AM on June 18th 2024, at the 500kV Pho Noi substation, The Northern Vietnam Power Projects Management Board (NPMB) collaborated with related units to successfully energize the expansion of bays 585 and 586 at the 500kV Pho Noi substation and the transmission line section from the two expanded bays to position 319 of the 500kV circuit 3 transmission line project, Nam Dinh I TPP - Pho Noi section, two days ahead of the schedule required by EVNNPT.

Project participating units witnessed the energization moment at the 500kV Pho Noi substation

The bay expansion component at the 500kV Pho Noi substation is part of the 500kV Nam Dinh I TPP - Pho Noi transmission line project, which is invested by the National Power Transmission Corporation (EVNNPT) and managed by NPMB on behalf of EVNNPT.

The engineering consulting component was undertaken by Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) ); Minh Quang Mechanical Electrical Joint Stock Company was responsible for construction and equipment installation; National Power Transmission Services Company handled computer configuration, and Power Transmission Company 1 served as the electrical supervision consultant and will be the operating unit.

The bay expansion component at the 500kV Pho Noi substation was constructed on the reserve land area for two 500kV transmission line bays within the existing 500kV Pho Noi Substation premises.

Overview of the 500kV Pho Noi substation and the bay expansion section

The energization of the bay expansion component at the 500kV Pho Noi substation prepares for the energization of 2 circuits of the 500kV circuit 3 transmission line, Nam Dinh I TPP - Pho Noi section, aimed at strengthening power system interconnection, enhancing stability, and ensuring safe power supply. Additionally, it helps increase stability reserve on the North-Central interface, combined with the 500kV circuit 3 transmission line, Quang Trach - Quynh Luu - Thanh Hoa - Nam Dinh I TPP section, contributing to creating a strong link from the power source centers in North Central Vietnam to the load centers in the Northern region. This is an important basis for safe, reliable, stable, and optimal operation of the power system, helping to reduce power system operation costs; Transmitting power from thermal power plants in the North Central region as well as renewable energy plants in the North Central and surrounding areas into the national power system, supplying electricity to load centers in the Northern region.

This is the second component of the 500kV circuit 3 transmission line project to be energized (the first was the expansion of the 500kV Quang Trach substation). The completion of this component is an important motivation for the entire construction site to be determined to complete the 500kV circuit 3 transmission line project, meeting the directive requirements of the Prime Minister.

Previously, on June 16th 2024, the Investor's Acceptance Council met to agree on the energization plan for the bay expansion component at the 500kV Pho Noi substation
The bay expansion component at the 500kV Pho Noi substation at night

Video of the Morning Financial Business News - June 18th, 2024 (VTV) reporting on the energization of the second component of the 500kV circuit 3 transmission line project can be viewed here.

Energization of the Reactor and Capacitor Installation Project to ensure the loading capacity of the 500kV circuit 3 transmission lines from Quang Trach to Pho Noi, at the 500kV Pho Noi substation

Along with energizing the expanded bay section to position 319 of the 500kV circuit 3 transmission line project, Nam Dinh I TPP - Pho Noi section, the Reactor and Capacitor Installation Project to ensure the loading capacity of the 500kV circuit 3 transmission lines from Quang Trach to Pho Noi, with the component of installing 02 500kV - 128MVAr reactors at the 500kV Pho Noi substation, was also successfully energized and put into operation.

The component is invested by EVNNPT, with Power Transmission Company 1 representing EVNNPT in project management, EVNPECC4 responsible for engineering; National Power Transmission Services Company handling construction, equipment installation, and computer configuration, and EVN International Joint Stock Company (EVNINTERNATIONAL) as the supervision consultant.

Overview of 02 reactors installed at the 500kV Pho Noi substation

EVNPECC4 - Substation Engineering Centre 

NPT.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251864

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4