NEWS & EVENTS

Ensuring power supply for Thai Binh province in hot season of 2024 and following years

27/04/2024 11:13:35

At 9:35 a.m. on 27th April  2024, the National Power Transmission Project Management Board (NPTPMB) in coordination with relevant units energized successfully the project of installing the second 220kV transformer at 220kV Thai Thuy substation (Thai Binh province).

The project is invested by the National Power Transmission Corporation (EVNNPT), managed by NPTPMB, and operated by Power Transmission Company 1, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) provided engineering consulting services for the project.

Các đơn vị tham gia dự án chứng kiến thời khắc đóng điện máy biến áp AT2 – Trạm biến áp 220kV Thái Thụy
National Power Transmission Project Management Board in coordination with relevant units witnessed the energization of the second 220kV transformer at 220kV Thai Thuy  substation.

Project scale: Installation of one 220/110/22kV - 250MVA AT2 transformer (increasing the total capacity of the substation to 2x250 MVA), installation of equipment for 4 bays of 110kV transmission line. This is a grade I, group C energy project located within the existing 220kV Thai Thuy substation in Thai Do commune, Thai Thuy district, Thai Binh province, with a total investment of more than VND 110 billion.

Once completed, the project helps ensure a stable, long-term, reliable power supply for the socio-economic development of Thai Binh province and surrounding areas, while preventing overloading of the 220kV Thai Thuy substation.

AT2 transformer at 220kV Thai Thuy substation

According to Mr. Vo Luong Nhan, Deputy Director of NPTPMB, the project was originally scheduled for energization in the third quarter of 2024. However, due to the rapid increase in electricity demand in Thai Binh province, the existing AT1 transformer at the 220kV Thai Thuy Substation was consistently operating at full load, reaching 90% of its capacity. Therefore, the leaders of EVN and EVNNPT directed NPTPMB to accelerate the project completion in April 2024 in order to ensure a stable power supply for Thai Binh province, and to meet the growing electricity needs of the local and businesses in the region during the hot season.  

During the project implementation, the project faced significant manpower challenges due to the concentration of construction resources on the 500kV circuit-3 transmission line project.

With the urgent nature of the project, NPTPMB and the participating units have been highly focused, working day and night, increasing construction machinery; Organized construction in 3 shifts, 4 teams, 24/7, through holidays following the spirit of implementing the 500kV circuit-3 transmission line project in order to meet the project completion schedule in April 2024.

Prior to energization, the investor-level acceptance council held a meeting to agree on the project’s energization

During the project implementation, the project has received full attention and support from local authorities of Thai Binh province, the direction of EVN and EVNNPT leaders, and the coordination of the Northern Load Dispatch Center, the attention and support of specialized departments, units under EVNNPT such as NPTS, PTC1, Ninh Binh Power Transmission and the tireless efforts of the entire project team, which helped the project reach the finish line sooner than planned.

The completion of the project is a practical action of NPTPMB to celebrate the 49th anniversary of National Reunification (April 30th 1975 - April 30th 2024) and the 138th International Labor Day (May 1st).

Installation of the 2nd 220kV transformer at the 220kV Thai Thuy Substation (Thai Binh)

Project investor: National Power Transmission Corporation (EVNNPT)

Project management: NPTPMB

Operator: Power Transmission Company 1

Engineering consulting unit: EVNPECC4

Project scale: Installing 01 transformer AT2 220/110/22 kV - 250 MVA (increasing the total capacity of the Substation to 2x250 MVA), installing equipment for 04 110kV transmission line bays. This is a grade-I, group C energy project located within the existing 220kV Thai Thuy substation in Thai Do commune, Thai Thuy district, Thai Binh province with a total investment of over 110 billion VND.

NPT.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097163

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice