Ensuring power supply for Thai Binh province in hot season of 2024 and following years

27/04/2024 11:13:35

At 9:35 a.m. on 27th April  2024, the National Power Transmission Project Management Board (NPTPMB) in coordination with relevant units energized successfully the project of installing the second 220kV transformer at 220kV Thai Thuy substation (Thai Binh province).

The project is invested by the National Power Transmission Corporation (EVNNPT), managed by NPTPMB, and operated by Power Transmission Company 1, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) provided engineering consulting services for the project.

Các đơn vị tham gia dự án chứng kiến thời khắc đóng điện máy biến áp AT2 – Trạm biến áp 220kV Thái Thụy
National Power Transmission Project Management Board in coordination with relevant units witnessed the energization of the second 220kV transformer at 220kV Thai Thuy  substation.

Project scale: Installation of one 220/110/22kV - 250MVA AT2 transformer (increasing the total capacity of the substation to 2x250 MVA), installation of equipment for 4 bays of 110kV transmission line. This is a grade I, group C energy project located within the existing 220kV Thai Thuy substation in Thai Do commune, Thai Thuy district, Thai Binh province, with a total investment of more than VND 110 billion.

Once completed, the project helps ensure a stable, long-term, reliable power supply for the socio-economic development of Thai Binh province and surrounding areas, while preventing overloading of the 220kV Thai Thuy substation.

AT2 transformer at 220kV Thai Thuy substation

According to Mr. Vo Luong Nhan, Deputy Director of NPTPMB, the project was originally scheduled for energization in the third quarter of 2024. However, due to the rapid increase in electricity demand in Thai Binh province, the existing AT1 transformer at the 220kV Thai Thuy Substation was consistently operating at full load, reaching 90% of its capacity. Therefore, the leaders of EVN and EVNNPT directed NPTPMB to accelerate the project completion in April 2024 in order to ensure a stable power supply for Thai Binh province, and to meet the growing electricity needs of the local and businesses in the region during the hot season.  

During the project implementation, the project faced significant manpower challenges due to the concentration of construction resources on the 500kV circuit-3 transmission line project.

With the urgent nature of the project, NPTPMB and the participating units have been highly focused, working day and night, increasing construction machinery; Organized construction in 3 shifts, 4 teams, 24/7, through holidays following the spirit of implementing the 500kV circuit-3 transmission line project in order to meet the project completion schedule in April 2024.

Prior to energization, the investor-level acceptance council held a meeting to agree on the project’s energization

During the project implementation, the project has received full attention and support from local authorities of Thai Binh province, the direction of EVN and EVNNPT leaders, and the coordination of the Northern Load Dispatch Center, the attention and support of specialized departments, units under EVNNPT such as NPTS, PTC1, Ninh Binh Power Transmission and the tireless efforts of the entire project team, which helped the project reach the finish line sooner than planned.

The completion of the project is a practical action of NPTPMB to celebrate the 49th anniversary of National Reunification (April 30th 1975 - April 30th 2024) and the 138th International Labor Day (May 1st).

Installation of the 2nd 220kV transformer at the 220kV Thai Thuy Substation (Thai Binh)

Project investor: National Power Transmission Corporation (EVNNPT)

Project management: NPTPMB

Operator: Power Transmission Company 1

Engineering consulting unit: EVNPECC4

Project scale: Installing 01 transformer AT2 220/110/22 kV - 250 MVA (increasing the total capacity of the Substation to 2x250 MVA), installing equipment for 04 110kV transmission line bays. This is a grade-I, group C energy project located within the existing 220kV Thai Thuy substation in Thai Do commune, Thai Thuy district, Thai Binh province with a total investment of over 110 billion VND.

NPT.COM.VN

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827412

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice