EVN and Phu Tho Province discussed the implementation of 500kV Lao Cai - Vinh Yen Transmission Line

13/12/2024 17:06:29

On December 13th, in Phu Tho province, EVN Vice President - Mr. Pham Hong Phuong met with Phu Tho Provincial People's Committee Vice Chairman - Mr. Nguyen Thanh Hai regarding preparations for implementing the 500kV Lao Cai - Vinh Yen transmission line project in the province.

Phu Tho Provincial People's Committee Vice Chairman – Mr. Nguyen Thanh Hai affirmed that the province would cooperate with EVN to implement the project

A key national energy project

EVN Vice President - Mr. Pham Hong Phuong stated that to ensure "electricity takes the lead" in serving socio-economic development and people's livelihood needs, EVN has continuously invested in electrical infrastructure projects across the country. In 2024, under the direction of the Party, Government, Prime Minister, with support from ministries, localities, and citizens, EVN completed the 500kV circuit-3 Quang Trach - Pho Noi transmission line in just over 6 months of construction. This remarkable achievement has created momentum and inspiration for citizens, businesses, and the entire political system in implementing key national projects, continuing the country's infrastructure development into a new era. In that spirit, for the 500kV Lao Cai - Vinh Yen transmission line project, the State Steering Committee for national important programs, projects in energy sector has directed adjustment of the project schedule: aiming to commence construction before April 30th 2025, and complete construction within 6 months to celebrate the Party Congress at all levels.

EVN Vice President - Mr. Pham Hong Phuong delivered the remarks

Deputy Director of Power Project Management Board 1 (EVNPMB1) – Mr. Do Quang Khai reported that the total length of the 500kV Lao Cai - Vinh Yen transmission line is 229.26km passing through 4 provinces: Lao Cai, Yen Bai, Phu Tho, and Vinh Phuc. The project section through Phu Tho province is 41.16 km long, with 95 tower locations, total permanent land acquisition of 10.63 hectares, and an estimated 102 households requiring resettlement.

Therein, the section through Doan Hung District spans 22.82 km, encompassing 48 tower foundation locations and requiring the permanent acquisition of 4.9 hectares of land. It passes through 8 communes: Bang Luan, Phu Lam, Phuc Lai, Tay Coc, Ngoc Quan, Yen Kien, Tieu Son, and Minh Tien. A total of 57 households are affected by the safety corridor and require resettlement.

The section through Thanh Ba district is 5.84 km long, comprising 17 tower foundation locations requiring permanent land acquisition of 2.67 hectares, passing through 2 communes (Dai An and Quang Yen), with 32 households affected by the safety corridor requiring resettlement.

The section through Phu Ninh district is 12.5 km long, comprising 30 tower foundation locations requiring permanent land acquisition of 3.07 hectares, passing through 5 communes (Tram Than, Lien Hoa, Le My, Trung Giap, and Tri Quan), with 13 households affected by the safety corridor requiring resettlement.

At the meeting, EVN/EVNPMB1 also informed Phu Tho Provincial People's Committee about the project's land use requirements and forest land use conversion policy.

To timely implement the project with its urgent schedule, EVN/EVNPMB1 will establish a forward steering committee for project implementation in Phu Tho province specifically and other provinces where the project passes through, to coordinate and direct resolution of local issues promptly.

The meeting took place at Phu Tho Provincial People's Committee headquarters

“Focus on solutions, not excuses”

To meet the project's urgent schedule, EVN greatly needs local cooperation in implementing site clearance work. In phase 1, ground clearance is needed for contractors to begin construction from April 30th 2025; in the next phase, corridor handover is required to complete before September 30th 2025, to meet project energization and safe operation requirements.

During project design and implementation, EVN/EVNPMB1 recommended that Phu Tho Provincial People's Committee not approve other construction projects within the project's power grid corridor. For power tower locations requiring adjustments or fine-tuning, EVN requested the Provincial Committee assign agencies to flexibly shorten local agreement time for sections requiring adjustment right at the site. They requested the Provincial Military Command's opinion on unexploded ordnance in the project construction area before December 15th 2024. Additionally, they proposed establishing dedicated compensation, site clearance, and resettlement teams for the project, and arranging resettlement land for households under the 500kV transmission line corridor (estimated 102 households). EVN/EVNPMB1 also made recommendations regarding forest land use conversion, replacement forestation, and temporary forest use plans.

Overall perspective of the 500kV Lao Cai - Vinh Yen transmission line project

At the working session, representatives from departments, agencies, and districts provided specific comments on issues related to preparing for the 500kV Lao Cai - Vinh Yen transmission line implementation in the province.

Despite the large workload and many difficulties, Phu Tho province identified this as a key project requiring determined implementation. Phu Tho Provincial People's Committee Vice Chairman – Mr. Nguyen Thanh Hai stated that the province committed to close cooperation with EVN to implement the project, with " no excuses ".

The Provincial People's Committee leadership required departments, agencies, and localities to coordinate with the investor to calculate and propose scientific and effective working methods with decisive engagement. They also required establishing a project implementation steering working group with representatives from departments, agencies, localities, and organizations; focusing on site clearance and public communication. A specific schedule needs to be developed to implement and monitor work along the entire transmission line in each district. Additionally, the province requested EVN to assign permanent local representatives to promptly coordinate and resolve project-related issues in Phu Tho province.

500kV Lao Cai - Vinh Yen Transmission Line Project:

  • Investor: EVN
  • Investor's Representative: Power Project Management Board 1
  • Survey and Engineering Consultant: Consortium of Power Engineering Consulting Joint Stock Company 1 (EVNPECC1) and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4)
  • Passing through provinces: Lao Cai, Yen Bai, Phu Tho, Vinh Phuc
  • Scope: New construction of 500kV double-circuit transmission line approximately 228.92 km long; expansion of two 500kV bays at 500kV Vinh Yen Substation to 500kV Lao Cai Substation.
  • Investment capital: over 7,000 billion VND
  • Expected groundbreaking: April 30th 2025.

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3252043

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4