NEWS & EVENTS

EVN inaugurates key energy infrastructure project, creating launchpad for Con Dao toward high-quality ecological special zone

20/12/2025 14:21:12

The power supply project from the national power grid to Con Dao District (formerly part of Ba Ria–Vung Tau Province), now the Con Dao Special Zone under Ho Chi Minh City, was officially inaugurated by Vietnam Electricity (EVN) on the morning of December 19, 2025. The project is assessed as a critical foundation for energy infrastructure, creating a prerequisite for developing Con Dao in a modern, green, and sustainable direction.

This is also among the large-scale power projects of significant importance, celebrating the 14th National Congress of the Communist Party of Vietnam.

Attending the inauguration ceremony were Comrade Nguyen Phuoc Loc – Deputy Secretary of the Ho Chi Minh City Party Committee and Chairman of the Vietnam Fatherland Front Committee of Ho Chi Minh City; Comrade Ho Thi Cam Dao – Deputy Secretary of the Can Tho City Party Committee and Chairman of the Vietnam Fatherland Front Committee of Can Tho City; and Comrade Nguyen Thi Yen – former Standing Deputy Secretary of the Ba Ria – Vung Tau Provincial Party Committee, former Head of the National Assembly Delegation of Ba Ria – Vung Tau Province, and a member of the 15th National Assembly. Also in attendance were representatives of the Ministries of National Defense, Public Security, Industry and Trade, Finance, Construction, Agriculture, and Environment.

Representing EVN were Comrade Cao Quang Quynh – Member of the Board of Directors of Vietnam Electricity (EVN); Comrade Nguyen Tai Anh – EVN Vice President; Comrade Uong Quang Huy – Vice Chairman of the Vietnam Electricity Trade Union; and Comrade Vo Quang Lam – former EVN Vice President. Also attending were representatives of EVN’s functional departments, Power Project Management Board No. 3 (EVNPMB3), Ho Chi Minh City Power Corporation (EVNHCMC), Southern Power Corporation (EVNSPC), representatives of design consultants, supervision consultants, construction contractors, contractors and units participating in supporting the construction of the transmission line, along with a large number of residents of the Con Dao Special Zone.

Delegates attending ceremony

The power supply project from the national power grid to Con Dao Special Zone has been implemented by EVN since December 2024. Once completed, the transmission line will ensure power supply for the Con Dao Special Zone, with a total capacity of approximately 29MW by 2026, 55MW by 2030, and 90MW by 2035. The work meets socio-economic development needs, ensures national defense and security, and improves people’s living standards; replaces on-site diesel-based power generation sources, reduces electricity production costs, limits greenhouse gas emissions, and contributes to the implementation of Vietnam’s commitments to emission reduction and sustainable development.

The Power Project Management Board 3 under the Vietnam Electricity (EVN) successfully energised the 110 kV Con Dao transformer station to supply electricity from the national grid to Con Dao Special Zone on September 2, 2025. This project aimed to celebrate the 80th anniversary of the August Revolution (August 19, 1945 - August 19, 2025) and National Day (September 2, 1945 - September 2, 2025).

The successful implementation of the project has demonstrated the capability to deploy large-scale energy projects using modern technology in complex and harsh offshore construction conditions. At the same time, it marks an important turning point in realizing the national energy infrastructure development strategy, demonstrating the determination of the Government, the Power sector, and participating units in caring for and developing infrastructure in maritime and island areas, as well as border and island regions of the Fatherland.

Delegates performing ribbon-cutting ceremony to inaugurate power supply project from National Power Grid to Con Dao Special Zone.

Highest level of complexity

With extensive experience, strong determination, and great efforts by EVN, Power Project Management Board No. 3, consulting units, and participating contractors, the project was completed nearly 3.5 months ahead of schedule.

Nguyen Tai Anh – EVN Vice President speaking at ceremony

The project was completed and energized on 4 September 2025, fully replacing the island’s traditional diesel-based power generation with electricity supplied from the national power grid. This is an event of exceptionally great significance and a historic milestone in socio-economic development, ensuring security, national defense, and sovereignty over the country’s seas and islands.

Toward building high-quality ecological special zone

National power grid crossing open sea to supply power to people of Con Dao Special Zone

Comrade Nguyen Van Manh – Vice Chairman of Con Dao Special Zone speaking at ceremony

Comrade Pham Quang Nhat – Director of Ho Chi Minh City Department of Industry and Trade speaking at ceremony

According to Pham Quang Nhat, Director of the Ho Chi Minh City Department of Industry and Trade, the inauguration of the power supply project from the National Power Grid to Con Dao is not only of special importance to Con Dao Special Zone, but also to the overall development of Ho Chi Minh City in the new phase. This is a key energy infrastructure and a prerequisite for the City to orient the spatial development of Con Dao toward a modern, green, and sustainable direction, thereby forming new development models based on high-quality tourism, commercial services, the digital economy, and the green economy.

On the occasion of the inauguration ceremony of the Power Supply Project from the National Power Grid to the Con Dao Special Zone, Vietnam Electricity, and representatives of the contractors donated a total of VND 500 million to support social welfare activities in the Con Dao Special Zone.

Member of Board of Directors of EVN Cao Quang Quynh (left) presenting symbolic donation of VND 200 million to support Con Dao Special Zone
General Director of PC1 Group Joint Stock Company Vu Anh Duong (left), representing contractor, presenting symbolic donation of VND 300 million to support Con Dao Special Zone

Power supply project from the National Power Grid to Con Dao Special Zone:

* Project owner: Vietnam Electricity (EVN). 

* Project scale: 110kV power transmission line with a total length of 103.7km, including a 77.7km subsea cable route.

* Total investment: VND 4,923 billion.

* Key project milestones:

  • Construction commencement: December 2024
  • Completion of cable laying along the entire route: 12 August  2025
  • Completion of expansion of Vinh Chau 220kV Substation (Can Tho City): 5 August  2025
  • Trial energization of the entire transmission line: 6:42 PM, 22 August 2025
  • Official energization: 7:09 PM on 2 September 2025

In this national key project, the Joint Venture of PC1 Group Joint Stock Company and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in implementing Package HH01-DZCD: Design, equipment supply and construction of submarine cable section (EPC).

Building on the success of power supply projects from the national power system to Ly Son island district and Cu Lao Cham island, EVNPECC4’s young team of design engineers continued to demonstrate pioneering spirit and master modern technology to make a strong mark in the National Grid Power Supply Project to Con Dao Special Economic Zone - A project with the longest 110 kV submarine cable line in Southeast Asia, implemented for the first time in Vietnam. The project not only ensures safe, continuous and stable power supply but also meets socio-economic development needs, ensures national defense and security, and improves the lives of people on remote islands.

Representatives of EVNPECC4 attending the inauguration ceremony of the project:

Video Con Dao Special Zone set to “take off” with access to the national power grid:

EVN.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096767

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4