NEWS & EVENTS

EVN leaders inspect construction site of Bac Ai Pumped Storage Hydropower Plant Project

27/03/2026 17:14:04

On the morning of 26 March 2026, in Bac Ai Tay commune, Khanh Hoa Province, the EVN delegation, led by EVN Vice President Pham Hong Phuong, inspected the construction progress at the Bac Ai Pumped Storage Hydropower Plant Project site.

According to the report of the Power Project Management Board 3 (EVNPMB3), in the first quarter of 2026, many critical path items of the Bac Ai Pumped Storage Hydropower Plant Project achieved positive results, contributing to the consolidation of overall progress. In the photo: representatives of EVNPMB3 and contractors reporting to EVN Vice President  Pham Hong Phuong (top row, second from right) on results of construction situation in first quarter.
Following that, the delegation inspected the construction progress at the project tunnels. In the photo: Inspection team checking excavation and reinforcement works of underground power plant.
Construction of underground powerhouse component was initiated on 22 January 2026
The construction and operation access and ventilation tunnels have achieved over 55% cumulative progress. Meanwhile, the downstream valve tower has completed open excavation works and is undergoing shotcrete reinforcement of slopes, reaching 24.3% of the first-quarter plan.
As of March 8, 2026, the contractor has completed the installation of the crushing plant equipment and is now carrying out material testing before commencing large-scale crushing and screening of aggregates for project supply. Accordingly, the excavated soil and rock will be transported to two crushing and screening plants to create crushed stone aggregate for road embankment construction, roadbeds in tunnels, and as material for spraying concrete to reinforce the slopes and tunnel arches. In the photo: Aggregate crushing and screening station No. 1.
Bac Ai pumped-storage hydropower work is not only an important energy project, but also brings many long-term economic, social, and environmental benefits.

EVN.COM.VN

Bac Ai Pumped Storage Hydropower Plant Project, Khanh Hoa Province:

  • Investor: Vietnam Electricity;
  • Investor’s representative for project management and operation: Power Project Management Board 3;
  • Project engineering consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Construction location: Bac Ai Tay commune, Khanh Hoa province;
  • Total capacity: 1,200MW;
  • Total investment: Over 21,101 billion VND;
  • Construction commencement: February 2025;
  • Planned schedule: Unit No. 01 to generate electricity in December 2029, Unit No. 02 in April 2030, Unit No. 03 in August 2030, Unit No. 04 in December 2030.

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251334

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4