EVN leaders inspect construction site of Bac Ai Pumped Storage Hydropower Plant Project

27/03/2026 17:14:04

On the morning of 26 March 2026, in Bac Ai Tay commune, Khanh Hoa Province, the EVN delegation, led by EVN Vice President Pham Hong Phuong, inspected the construction progress at the Bac Ai Pumped Storage Hydropower Plant Project site.

According to the report of the Power Project Management Board 3 (EVNPMB3), in the first quarter of 2026, many critical path items of the Bac Ai Pumped Storage Hydropower Plant Project achieved positive results, contributing to the consolidation of overall progress. In the photo: representatives of EVNPMB3 and contractors reporting to EVN Vice President  Pham Hong Phuong (top row, second from right) on results of construction situation in first quarter.
Following that, the delegation inspected the construction progress at the project tunnels. In the photo: Inspection team checking excavation and reinforcement works of underground power plant.
Construction of underground powerhouse component was initiated on 22 January 2026
The construction and operation access and ventilation tunnels have achieved over 55% cumulative progress. Meanwhile, the downstream valve tower has completed open excavation works and is undergoing shotcrete reinforcement of slopes, reaching 24.3% of the first-quarter plan.
As of March 8, 2026, the contractor has completed the installation of the crushing plant equipment and is now carrying out material testing before commencing large-scale crushing and screening of aggregates for project supply. Accordingly, the excavated soil and rock will be transported to two crushing and screening plants to create crushed stone aggregate for road embankment construction, roadbeds in tunnels, and as material for spraying concrete to reinforce the slopes and tunnel arches. In the photo: Aggregate crushing and screening station No. 1.
Bac Ai pumped-storage hydropower work is not only an important energy project, but also brings many long-term economic, social, and environmental benefits.

EVN.COM.VN

Bac Ai Pumped Storage Hydropower Plant Project, Khanh Hoa Province:

  • Investor: Vietnam Electricity;
  • Investor’s representative for project management and operation: Power Project Management Board 3;
  • Project engineering consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Construction location: Bac Ai Tay commune, Khanh Hoa province;
  • Total capacity: 1,200MW;
  • Total investment: Over 21,101 billion VND;
  • Construction commencement: February 2025;
  • Planned schedule: Unit No. 01 to generate electricity in December 2029, Unit No. 02 in April 2030, Unit No. 03 in August 2030, Unit No. 04 in December 2030.

Related article

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

EVN and its units actively respond to Earth Hour 2026 campaign

EVN and its units actively respond to Earth Hour 2026 campaign

In response to the Earth Hour 2026 Campaign launched by the Ministry of Industry and Trade, Vietnam Electricity (EVN) has proactively and effectively coordinated the unified implementation of a wide range of communication, advocacy, and execution activities nationwide, contributing to the strong dissemination of the message of efficient energy use and environmental protection.

Upgrading 500kV Pho Noi Substation to 1,800 MVA which strengthening power supply for Northern Vietnam

Upgrading 500kV Pho Noi Substation to 1,800 MVA which strengthening power supply for Northern Vietnam

At 2:00 AM on March 25th 2026, the National Power Transmission Corporation (EVNNPT), the Power Transmission Project Management Board (NPTPMB), in coordination with the National Electricity System and Market Operation Company Limited (NSMO) and relevant units, successfully energized the project of upgrading 500kV Pho Noi Substation’s capacity.

EVNPECC4 Labour Union Held Gathering to Celebrate the 116th Anniversary of International Women’s Day (March 8th)

EVNPECC4 Labour Union Held Gathering to Celebrate the 116th Anniversary of International Women’s Day (March 8th)

On the occasion of the 116th anniversary of International Women’s Day (March 8th 1910 – March 8th 2026) and the 1986th anniversary of the Hai Ba Trung Uprising, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) organized a women’s gathering at the Company’s Head Office, 11 Hoang Hoa Tham Street, Nha Trang, on the morning of March 6th 2026.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2756455

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice