NEWS & EVENTS

EVN leaders inspect construction site of Bac Ai Pumped Storage Hydropower Plant Project

27/03/2026 17:14:04

On the morning of 26 March 2026, in Bac Ai Tay commune, Khanh Hoa Province, the EVN delegation, led by EVN Vice President Pham Hong Phuong, inspected the construction progress at the Bac Ai Pumped Storage Hydropower Plant Project site.

According to the report of the Power Project Management Board 3 (EVNPMB3), in the first quarter of 2026, many critical path items of the Bac Ai Pumped Storage Hydropower Plant Project achieved positive results, contributing to the consolidation of overall progress. In the photo: representatives of EVNPMB3 and contractors reporting to EVN Vice President  Pham Hong Phuong (top row, second from right) on results of construction situation in first quarter.
Following that, the delegation inspected the construction progress at the project tunnels. In the photo: Inspection team checking excavation and reinforcement works of underground power plant.
Construction of underground powerhouse component was initiated on 22 January 2026
The construction and operation access and ventilation tunnels have achieved over 55% cumulative progress. Meanwhile, the downstream valve tower has completed open excavation works and is undergoing shotcrete reinforcement of slopes, reaching 24.3% of the first-quarter plan.
As of March 8, 2026, the contractor has completed the installation of the crushing plant equipment and is now carrying out material testing before commencing large-scale crushing and screening of aggregates for project supply. Accordingly, the excavated soil and rock will be transported to two crushing and screening plants to create crushed stone aggregate for road embankment construction, roadbeds in tunnels, and as material for spraying concrete to reinforce the slopes and tunnel arches. In the photo: Aggregate crushing and screening station No. 1.
Bac Ai pumped-storage hydropower work is not only an important energy project, but also brings many long-term economic, social, and environmental benefits.

EVN.COM.VN

Bac Ai Pumped Storage Hydropower Plant Project, Khanh Hoa Province:

  • Investor: Vietnam Electricity;
  • Investor’s representative for project management and operation: Power Project Management Board 3;
  • Project engineering consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Construction location: Bac Ai Tay commune, Khanh Hoa province;
  • Total capacity: 1,200MW;
  • Total investment: Over 21,101 billion VND;
  • Construction commencement: February 2025;
  • Planned schedule: Unit No. 01 to generate electricity in December 2029, Unit No. 02 in April 2030, Unit No. 03 in August 2030, Unit No. 04 in December 2030.

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096602

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice