EVN leaders worked with contractors, urged progress of the 500kV circuit-3 transmission line project

23/02/2024 14:19:08

On the morning of February 21 in Hanoi, Mr. Dang Hoang An, Chairman of the Board of Vietnam Electricity (EVN), chaired a meeting with contractors participating in the 500kV circuit-3 transmission line project from Quang Trach to Pho Noi to review construction progress and urge contractors to mobilize human resources and equipment to speed up the project's progress. The meeting was held in a combination of in-person and online formats.

Also attending the meeting were Mr. Nguyen Anh Tuan – EVN’s President and CEO, Mr. Nguyen Duc Cuong – EVN’s Member of the Board, Mr. Pham Hong Phuong – EVN’s Vice President, leaders of EVN's professional departments, leaders of the National Power Transmission Corporation, contractors for construction, engineering consulting, and equipment supply for the project, etc.…

The 500kV circuit-3 transmission line project from Quang Trach to Pho Noi includes 4 sub-projects: Quang Trach - Quynh Luu, Quynh Luu - Thanh Hoa, Thanh Hoa - Nam Dinh I Thermal Power Plant, and Nam Dinh I Thermal Power Plant - Pho Noi, with a total length of about 519km, passing through 9 provinces (including 4 towns and 39 districts). With the strong direction of the Prime Minister, the decisive involvement of local authorities, up to now, along the entire line, 1,118 out of 1,180 (achieving 95%) tower foundation positions and 179 out of 502 (achieving 36%) anchor spans have been handed over.

Currently, contractors have completed casting foundations at 87 positions, are constructing temporary roads and simultaneously installing foundations at 752 positions, have completed installing 1 steel tower, and are installing 6 towers.

Mr. Dang Hoang An – EVN’s Chairman of the Board chaired the meeting

In implementing the Prime Minister's instructions, EVN has regularly directed and supervised the project implementation by the project investor (National Power Transmission Corporation) and contractors. Every week, EVN leaders organize meetings with the project owner to review and urge progress. Even during the recent Lunar New Year holiday, over the first 3 days of Tet, EVN's leaders inspected the production of materials, equipment for the project, and the construction situation of contractors at the construction sites. 

In parallel, EVN leaders also worked with the authorities of the 9 provinces through which the project passes to resolve difficulties and obstacles related to the project. For issues beyond their authority, EVN has also promptly reported to relevant ministries, agencies, the Government, and the Prime Minister for resolution.

At the meeting, the contractors reported on the implementation of their packages and committed to making maximum efforts and concentrating resources to complete the required work items according to the progress required by the project investor. 

Speaking at the meeting, Mr. Dang Hoang An – EVN’s Chairman of the Board emphasized that this is an urgent and important energy project to strengthen the 500kV transmission grid capacity between the North and Central regions, contributing to ensuring power supply for the Northern region. The project has received the attention and strong direction from the Government and the Prime Minister, as well as the involvement of the entire political system. 

The meeting was attended by many contractors participating in the project

As directed by the Prime Minister, the entire line must be energized by June 2024. The EVN’s Chairman of the Board requested that contractors prioritize and allocate all resources for the project, strengthen labor force and equipment, and urgently deploy at positions that have been handed over. Engineering consulting units need to further promote their roles and accelerate the progress of work items. For contractors supplying materials and equipment such as steel towers, conductors, insulators accessories, and fiber optic cables… they need to speed up production progress, ensuring quality and schedule as committed. EVN leaders demanded that contractors unite their efforts and determination to complete the project according to the Prime Minister's instructions, together with the project investor.

The EVN’s Chairman of the Board also requested that EVN leaders, the leaders of the National Power Transmission Corporation, and the leaders of EVN's professional departments continue to closely monitor the progress of contractors, promptly resolve emerging difficulties and obstacles, and take immediate measures to address contractors at risk of delays. 

The construction progress of sub-projects under the 500kV circuit-3 transmission line project from Quang Trach to Pho Noi as of February 20, 2024:

* Nam Dinh I TPP - Thanh Hoa: completed casting foundations at 78/180 positions, constructing temporary roads, simultaneously digging and casting foundations or driving piles at 98/180 foundation positions.

* Nam Dinh I TPP- Pho Noi: completed casting foundations at 7/334 positions, deploying temporary road construction, simultaneously digging and casting foundations at 234/334 positions.

* Quynh Luu - Thanh Hoa: completed casting foundations at 1/203 positions, deploying temporary road construction, simultaneously digging and casting foundations at 135/203 positions.

* Quang Trach - Quynh Luu: completed casting foundations at 1/463 positions, deploying temporary road construction, simultaneously digging and casting foundations at 285/463 positions.

The 500kV circuit-3 transmission line project from Quang Trach to Pho Noi

- Project investor: National Power Transmission Corporation (under EVN)

- Total investment: approximately 22,000 billion VND

- Scale: Includes 2 circuits of 500kV transmission line, approximately 519km length. Starting point is the 500kV Quang Trach Switchyard (Quang Binh), ending point is the 500kV Pho Noi substation (Hung Yen)

- Engineering consultants: Power Engineering Consulting Joint Stock Companies 1, 2, 4 and Institute of Energy

- The Northern Power Projects Management Board (NPMB) on behalf of EVNNPT manages and operates 2 sections: Nam Dinh I Thermal Power Plant – Thanh Hoa and Nam Dinh I Thermal Power Plant – Pho Noi.

- The Central Power Projects Management Board (CPMB) on behalf of EVNNPT manages and operates 2 sections: Quang Trach – Quynh Luu and Quynh Luu – Thanh Hoa.

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251647

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4