EVNPECC4 and other parties’ common efforts in commissioning and energizing Vinh Quang 110kV substation and connecting transmission lines in Kien Giang province

12/07/2023 16:07:37

At precisely 8 p.m. on July 3, 2023, the Vinh Quang 110kV substation and connecting transmission lines in Kien Giang province were successfully energized and put into operation.

To enhance power supply capacity in order to meet the electricity demand in the Rach Gia city area and neighboring districts of Kien Giang province, in 2022, the Southern Power Corporation (EVNSPC) invested in this project. The Southern Power Project Management Board (SPMB) was assigned to manage and oversee the project. The consortium between Y.K Construction & Trading Co., Ltd. and Systech High Voltage Engineering Development Joint Stock Company carried out the construction.

In addition to the efforts of SPMB, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) - Southern Affiliate, together with specialized departments of EVNSPC, the Southern Regional Load Dispatch Center, Kien Giang Power Company, the SCADA Operations Center, the Southern Electrical Testing Company, etc., cooperated with the investor, contractors, and authorities at all levels to ensure the project completion according to the assigned schedule.

Overview of Vinh Quang 110/22kV substation

The groundbreaking ceremony occurred on September 6, 2022, in Vinh Quang ward, Rach Gia city, Kien Giang province. The project is designed with two transformers of 40MVA capacity each. This phase focused on installing one 40MVA transformer, with a 32-meter connecting transmission line. The total investment for the project exceeded 66 billion VND, financed through commercial loans and EVNSPC's funds.

Thanks to the dedicated efforts of the leadership, engineers, and staffs of all involved units, as well as EVNSPC's close supervision of the project, all the connection works were completed on July 3, 2023.

To modernize the operation management, the Vinh Quang 110kV substation and the connecting transmission lines are equipped with SCADA, HMI, and surveillance camera systems,… to enable data acquisition, monitoring, and remote control of devices in the substation, in line with the central management and automation goals of the power sector.

The firefighting force is preparing for the energization of the transformer

Throughout the project implementation, the related parties closely coordinated with the Compensation Board, the People's Committee of Vinh Quang ward - Rach Gia city, and Kien Giang Power Company; together with the persistent guidance from EVNSPC to accelerate the progress, promptly resolve any obstacles, and ensure the timely energization of the project.

Vinh Quang 110kV Substation and connecting transmission lines, Kien Giang province

Investor: Southern Power Corporation (EVNSPC)

Project Management: Southern Power Project Management Board

Location: Vinh Quang ward, Rach Gia city, Kien Giang province

Engineering: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) – Southern Branch

Construction Scopes:

+Vinh Quang 110kV Substation:

  • Voltage Level: 110/22 kV
  • Substation Capacity: 2x40 MVA, Phase 01: installing 1 transformer - 40 MVA
  • 110kV Side: H-configuration single busbar with 5 circuit breakers.
  • 22kV Side: A single busbar configuration with sectionalized circuit breakers, corresponding to two 110kV transformers. In this phase, it is fully equipped for 1 sectionalized busbar.

+110kV connecting transmission lines:

  • Voltage Level: 110kV
  • Number of circuits: 2
  • Length: 32 meters
  • Conductor: 2xACKP 240/39mm2 aluminum conductor steel-reinforced cable
  • Connection point: Connected to 110kV Rạch Gia - Hon Dat  transmission line

icon.com.vn

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827329

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice