NEWS & EVENTS

EVNPECC4 makes important mark in the success of the National grid power supply project to Con Dao

04/09/2025 18:24:31

On September 4th 2025, Vietnam Electricity (EVN)/ Power Project Management Board 3 successfully energized the 110 kV Con Dao Substation, serving the power supply from the national grid to Con Dao Special Economic Zone. Previously, on September 2nd 2025, EVN/ Power Project Management Board 3 also successfully organized the energization of the National Grid Power Supply Project to Con Dao Special Economic Zone. In this national key project, the Joint Venture of PC1 Group Joint Stock Company and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in implementing Package HH01-DZCD: Design, equipment supply and construction of submarine cable section (EPC).

This achievement demonstrates the advancement of domestic enterprises, proving their capability to replace foreign contractors, thereby helping to save foreign currency for the country. This is also the first time Vietnamese contractors have synchronous and modern monitoring equipment to carry out trenching and laying of 110 kV offshore submarine cables, which previously was only done with 22/35 kV voltage levels in near-shore marine areas. This is a complex project due to very high requirements such as construction of buried submarine cables in marine areas with depths up to 52m, underground cable works crossing through the forest conservation area of Con Dao National Park with strict environmental protection requirements during construction and operation. In addition, the project completion time had to be shortened according to the Prime Minister's requirements. 

The Joint Venture of PC1 Group Joint Stock Company and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in implementing Package HH01-DZCD: Design, equipment supply and construction of submarine cable section (EPC)

Building on the success of power supply projects from the national power system to Ly Son island district and Cu Lao Cham island, EVNPECC4’s young team of design engineers continued to demonstrate pioneering spirit and master modern technology to make a strong mark in the National Grid Power Supply Project to Con Dao Special Economic Zone - A project with the longest 110 kV submarine cable line in Southeast Asia, implemented for the first time in Vietnam. The project not only ensures safe, continuous and stable power supply but also meets socio-economic development needs, ensures national defense and security, and improves the lives of people on remote islands.

EVNPECC4‘s representative, Mr. Vuong Anh Dung - Deputy General Director (3rd from right) taking photos with leaders of Power Project Management Board 3, PC1 Group Joint Stock Company at the Launching Ceremony of the emulation movement to complete the Project on March 8th, 2025

The project helps replace on-site diesel power generation sources, reduce electricity production costs, limit greenhouse gas emissions, contribute to Vietnam's emission reduction commitments and sustainable development, affirming the capacity to deploy large-scale energy projects with modern technology under complex and harsh marine construction conditions.

The National Grid Power Supply Project to Con Dao was approved for investment policy by the Prime Minister in Decision 708/QD-TTg dated June 16th 2023, and assigned to EVN for implementation. With a total length of 103.7 km, the project includes a 17.5 km overhead line through Soc Trang province; a 77.7 km submarine cable connecting from mainland to the island; an 8.5 km underground cable on the island; expansion of circuit bays at 220 kV Vinh Chau substation (Soc Trang province) and construction of a 110/22 kV substation at Con Dao.

EVNPECC4's leaders joined the working delegation in the acceptance of the submarine cable landfall project to the island

The project holds particularly important significance for the socio-economic development of Con Dao Special Economic Zone, Ho Chi Minh City. This is a project celebrating the 80th anniversary of the successful August Revolution and National Day of the Socialist Republic of Vietnam (September 2nd, 1945 - September 2nd, 2025). The project's completion is an important turning point in realizing the national energy infrastructure development strategy, demonstrating the determination of the Government, the power sector and participating units in caring for and developing infrastructure for sea and island areas, border and maritime island regions of the Fatherland.

Some construction images of the National Grid Power Supply Project to Con Dao (source: EVN, Tien Phong Newspaper):

National Grid Power Supply Project to Con Dao:

        Investor: Vietnam Electricity (EVN).
        Project scale: 110kV voltage level project, total length 103.7km, including:

  • Overhead line: 17.5km through Vinh Chau Town, Soc Trang province.
  • Submarine cable: 77.7km connecting from VT32 (last pole at sea) to Con Dao.
  • Underground cable on island: 8.5km from landing point to 110KV substation at An Hoi Power Plant, Con Dao.
  • Substations: Expansion of 110kV circuit bay at 220kV Vinh Chau Substation (Soc Trang) and construction of 110/22kV GIS Substation at Con Dao.
  • Total investment: 4,923 billion VND
  • Construction deployment: December 2024
  • Completion of cable laying entire route: August 12th, 2025.
  • Completion of 220kV Vinh Chau substation expansion (Can Tho City): August 5th, 2025
  • Test energization of entire route: 6:42 PM on August 22nd, 2025.
  • Energization: 7:09 PM on September 2nd, 2025.

P4-VP

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251505

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4