NEWS & EVENTS

EVNPECC4 - The first engineering consulting firm in Vietnam to perform Technical design and Detailed design for a nearly 80 km long 110kV submarine cable route

13/03/2025 08:15:42

On March 8th 2025, in Vinh Chau Town, Soc Trang Province, Vietnam Electricity (EVN), in collaboration with the EVN’s Labor Union, held a launching ceremony to promote the completion of construction progress targets for the National Power Grid Connection Project to Con Dao District, Ba Ria - Vung Tau Province. As part of the EPC package for the project, in partnership with PC1 Group Joint Stock Company, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) is honored to be the first engineering consulting firm in Vietnam to perform the technical design and detailed design for this crucial nearly 80 km long 110kV submarine cable route.

In alignment with the Party and State's policies on electricity supply for islands, the Prime Minister and the Ministry of Industry and Trade assigned EVN as the investor for the National Power Grid Connection Project to Con Dao District, with Power Project Management Board 3 (EVNPMB3) responsible for project management.

According to the plan, the project is expected to be completed and energized in 2025, with a total investment of VND 4,923 billion. The project consists of a 110kV transmission line with a total length of 103.7 km, including: 17.5 km of overhead transmission lines across Soc Trang Province, 77.7 km of submarine cable, 8.5 km of underground cable on Con Dao, Expansion of the 220kV Vinh Chau Substation (Soc Trang) and construction of the 110/22kV GIS Substation on Con Dao.

The EPC package is the primary package of the project, covering the engineering, equipment procurement, and construction of the 110kV submarine cable route, approximately 77.7 km long, extending from the offshore transition point in Soc Trang to the Con Dao landing point. This is the longest 110kV submarine cable route in Southeast Asia, implemented for the first time in Vietnam. The PC1 Group - EVNPECC4 Consortium was honored to be selected as the EPC contractor by EVN through domestic competitive bidding, meeting the required technical capacity and experience for the package. 

The emulation launching ceremony for completing the construction progress targets of the National Power Grid Connection Project to Con Dao on March 8th (Photo: EVN)
EPC Consortium representative - PC1 Group - EVNPECC4 Consortium delivered a speech at the ceremony

Con Dao holds critical strategic importance in national defense, security, and maritime sovereignty, while also being a highly valuable historical, cultural, and tourism destination. However, the island district currently relies on a diesel power system with limited capacity (11.8MW), which is insufficient to meet future economic and social development needs. After completion, the transmission line is expected to supply electricity to Con Dao with a total capacity of approximately 29MW by 2026, 55MW by 2030, and 90MW by 2035.

Mr. Vuong Anh Dung – Deputy General Director of EVNPECC4 shared: “EVNPECC4 has reached a significant milestone by becoming the first engineering consulting firm in Vietnam to design a nearly 80 km long 110kV submarine cable route for the National Power Grid Connection Project to Con Dao District, Ba Ria - Vung Tau Province. We hope that by September 2025, the entire island district will be illuminated, maritime security will be strengthened, and the living conditions of the island’s residents will be improved, befitting Con Dao’s status as a renowned cultural and spiritual landmark.” 

EVNPECC4’s representative - Mr. Vuong Anh Dung - Deputy General Director (3rd from the right), took a commemorative photo with EVNPMB3’s leaders and PC1 Group’s representatives at the ceremony

Video of the Emulation Launching Ceremony for completing the Construction Progress Targets of the National Power Grid Connection Project to Con Dao on March 8th 2025:

National Power Grid Connection Project to Con Dao District, Ba Ria - Vung Tau Province:

Investor: Vietnam Electricity (EVN);

Investor's Representative for Project Management and Operation: Power Project Management Board 3 (EVNPMB3);

The project has a 110kV voltage level, with a total length of 103.7 km, including:

   •   Overhead transmission line: 17.5 km across Soc Trang Province.

   •   Submarine cable: 77.7 km, connecting the mainland to the island.

   •   Underground cable on the island: 8.5 km in Con Dao District.

   •   Substations: Expansion of the 220kV Vinh Chau Substation (Soc Trang) and construction of the 110/22kV GIS Substation in Con Dao.

Total investment: VND 4,923 billion;

Construction commencement: March 2025; 

Expected completion and energization: Within 2025

EVNPECC4 synthesis

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097049

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice