NEWS & EVENTS

EVNPECC4 - The first engineering consulting firm in Vietnam to perform Technical design and Detailed design for a nearly 80 km long 110kV submarine cable route

13/03/2025 08:15:42

On March 8th 2025, in Vinh Chau Town, Soc Trang Province, Vietnam Electricity (EVN), in collaboration with the EVN’s Labor Union, held a launching ceremony to promote the completion of construction progress targets for the National Power Grid Connection Project to Con Dao District, Ba Ria - Vung Tau Province. As part of the EPC package for the project, in partnership with PC1 Group Joint Stock Company, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) is honored to be the first engineering consulting firm in Vietnam to perform the technical design and detailed design for this crucial nearly 80 km long 110kV submarine cable route.

In alignment with the Party and State's policies on electricity supply for islands, the Prime Minister and the Ministry of Industry and Trade assigned EVN as the investor for the National Power Grid Connection Project to Con Dao District, with Power Project Management Board 3 (EVNPMB3) responsible for project management.

According to the plan, the project is expected to be completed and energized in 2025, with a total investment of VND 4,923 billion. The project consists of a 110kV transmission line with a total length of 103.7 km, including: 17.5 km of overhead transmission lines across Soc Trang Province, 77.7 km of submarine cable, 8.5 km of underground cable on Con Dao, Expansion of the 220kV Vinh Chau Substation (Soc Trang) and construction of the 110/22kV GIS Substation on Con Dao.

The EPC package is the primary package of the project, covering the engineering, equipment procurement, and construction of the 110kV submarine cable route, approximately 77.7 km long, extending from the offshore transition point in Soc Trang to the Con Dao landing point. This is the longest 110kV submarine cable route in Southeast Asia, implemented for the first time in Vietnam. The PC1 Group - EVNPECC4 Consortium was honored to be selected as the EPC contractor by EVN through domestic competitive bidding, meeting the required technical capacity and experience for the package. 

The emulation launching ceremony for completing the construction progress targets of the National Power Grid Connection Project to Con Dao on March 8th (Photo: EVN)
EPC Consortium representative - PC1 Group - EVNPECC4 Consortium delivered a speech at the ceremony

Con Dao holds critical strategic importance in national defense, security, and maritime sovereignty, while also being a highly valuable historical, cultural, and tourism destination. However, the island district currently relies on a diesel power system with limited capacity (11.8MW), which is insufficient to meet future economic and social development needs. After completion, the transmission line is expected to supply electricity to Con Dao with a total capacity of approximately 29MW by 2026, 55MW by 2030, and 90MW by 2035.

Mr. Vuong Anh Dung – Deputy General Director of EVNPECC4 shared:EVNPECC4 has reached a significant milestone by becoming the first engineering consulting firm in Vietnam to design a nearly 80 km long 110kV submarine cable route for the National Power Grid Connection Project to Con Dao District, Ba Ria - Vung Tau Province. We hope that by September 2025, the entire island district will be illuminated, maritime security will be strengthened, and the living conditions of the island’s residents will be improved, befitting Con Dao’s status as a renowned cultural and spiritual landmark.” 

EVNPECC4’s representative - Mr. Vuong Anh Dung - Deputy General Director (3rd from the right), took a commemorative photo with EVNPMB3’s leaders and PC1 Group’s representatives at the ceremony

Video of the Emulation Launching Ceremony for completing the Construction Progress Targets of the National Power Grid Connection Project to Con Dao on March 8th 2025:

National Power Grid Connection Project to Con Dao District, Ba Ria - Vung Tau Province:

Investor: Vietnam Electricity (EVN);

Investor's Representative for Project Management and Operation: Power Project Management Board 3 (EVNPMB3);

The project has a 110kV voltage level, with a total length of 103.7 km, including:

   •   Overhead transmission line: 17.5 km across Soc Trang Province.

   •   Submarine cable: 77.7 km, connecting the mainland to the island.

   •   Underground cable on the island: 8.5 km in Con Dao District.

   •   Substations: Expansion of the 220kV Vinh Chau Substation (Soc Trang) and construction of the 110/22kV GIS Substation in Con Dao.

Total investment: VND 4,923 billion;

Construction commencement: March 2025; 

Expected completion and energization: Within 2025

EVNPECC4 synthesis

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827327

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice