NEWS & EVENTS

EVNPECC4 - The first engineering consulting firm in Vietnam to perform Technical design and Detailed design for a nearly 80 km long 110kV submarine cable route

13/03/2025 08:15:42

On March 8th 2025, in Vinh Chau Town, Soc Trang Province, Vietnam Electricity (EVN), in collaboration with the EVN’s Labor Union, held a launching ceremony to promote the completion of construction progress targets for the National Power Grid Connection Project to Con Dao District, Ba Ria - Vung Tau Province. As part of the EPC package for the project, in partnership with PC1 Group Joint Stock Company, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) is honored to be the first engineering consulting firm in Vietnam to perform the technical design and detailed design for this crucial nearly 80 km long 110kV submarine cable route.

In alignment with the Party and State's policies on electricity supply for islands, the Prime Minister and the Ministry of Industry and Trade assigned EVN as the investor for the National Power Grid Connection Project to Con Dao District, with Power Project Management Board 3 (EVNPMB3) responsible for project management.

According to the plan, the project is expected to be completed and energized in 2025, with a total investment of VND 4,923 billion. The project consists of a 110kV transmission line with a total length of 103.7 km, including: 17.5 km of overhead transmission lines across Soc Trang Province, 77.7 km of submarine cable, 8.5 km of underground cable on Con Dao, Expansion of the 220kV Vinh Chau Substation (Soc Trang) and construction of the 110/22kV GIS Substation on Con Dao.

The EPC package is the primary package of the project, covering the engineering, equipment procurement, and construction of the 110kV submarine cable route, approximately 77.7 km long, extending from the offshore transition point in Soc Trang to the Con Dao landing point. This is the longest 110kV submarine cable route in Southeast Asia, implemented for the first time in Vietnam. The PC1 Group - EVNPECC4 Consortium was honored to be selected as the EPC contractor by EVN through domestic competitive bidding, meeting the required technical capacity and experience for the package. 

The emulation launching ceremony for completing the construction progress targets of the National Power Grid Connection Project to Con Dao on March 8th (Photo: EVN)
EPC Consortium representative - PC1 Group - EVNPECC4 Consortium delivered a speech at the ceremony

Con Dao holds critical strategic importance in national defense, security, and maritime sovereignty, while also being a highly valuable historical, cultural, and tourism destination. However, the island district currently relies on a diesel power system with limited capacity (11.8MW), which is insufficient to meet future economic and social development needs. After completion, the transmission line is expected to supply electricity to Con Dao with a total capacity of approximately 29MW by 2026, 55MW by 2030, and 90MW by 2035.

Mr. Vuong Anh Dung – Deputy General Director of EVNPECC4 shared: “EVNPECC4 has reached a significant milestone by becoming the first engineering consulting firm in Vietnam to design a nearly 80 km long 110kV submarine cable route for the National Power Grid Connection Project to Con Dao District, Ba Ria - Vung Tau Province. We hope that by September 2025, the entire island district will be illuminated, maritime security will be strengthened, and the living conditions of the island’s residents will be improved, befitting Con Dao’s status as a renowned cultural and spiritual landmark.” 

EVNPECC4’s representative - Mr. Vuong Anh Dung - Deputy General Director (3rd from the right), took a commemorative photo with EVNPMB3’s leaders and PC1 Group’s representatives at the ceremony

Video of the Emulation Launching Ceremony for completing the Construction Progress Targets of the National Power Grid Connection Project to Con Dao on March 8th 2025:

National Power Grid Connection Project to Con Dao District, Ba Ria - Vung Tau Province:

Investor: Vietnam Electricity (EVN);

Investor's Representative for Project Management and Operation: Power Project Management Board 3 (EVNPMB3);

The project has a 110kV voltage level, with a total length of 103.7 km, including:

   •   Overhead transmission line: 17.5 km across Soc Trang Province.

   •   Submarine cable: 77.7 km, connecting the mainland to the island.

   •   Underground cable on the island: 8.5 km in Con Dao District.

   •   Substations: Expansion of the 220kV Vinh Chau Substation (Soc Trang) and construction of the 110/22kV GIS Substation in Con Dao.

Total investment: VND 4,923 billion;

Construction commencement: March 2025; 

Expected completion and energization: Within 2025

EVNPECC4 synthesis

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251909

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4