NEWS & EVENTS

EVN’s leaders inspected the construction site of 500kV Lao Cai - Vinh Yen transmission line in Vinh Phuc, Phu Tho

25/03/2025 10:11:26

On March 24th, EVN’s Vice President Mr.Pham Hong Phuong directly inspected the construction progress of packages 8, 9, and 10 of the 500kV Lao Cai - Vinh Yen transmission line project in Vinh Phuc and Phu Tho provinces.

EVN’s leaders inspected construction at position 364 of the 500kV Lao Cai - Vinh Yen transmission line project

In the first week following the groundbreaking command issued by the Prime Minister (on March 16th), the construction of the 500kV Lao Cai – Vinh Yen transmission line has been urgently and actively implemented by EVN and contractors.

Through on-site inspection, EVN’s leaders noted that some contractors have adopted the spirit of "overcoming heat, conquering rain," "3 shifts, 4 teams," and valuable lessons learned from the 500kV circuit-3 transmission line project to implement this project with the highest determination.

On March 24th, EVN’s leaders inspected the construction of packages 8, 9, and 10 of the project

EVN’s leaders required contractors to continue mobilizing additional human resources and arranging more machinery and equipment; they must deploy simultaneously at all foundation positions. Specifically, for package 8, Viet A contractor must mobilize sufficient excavators to simultaneously work at 24 foundation positions in March. For package 9, PCC1 Ninh Binh contractor must urgently supplement manpower for steel construction at positions where excavation is completed; coordinate with partners to immediately pour concrete at foundations that meet conditions. For package 10, Song Da 5 contractor must mobilize 22 teams to work at 22 positions by the end of March.

The EVN’s Vice President also directed the supervision consultant to promptly accept phase transitions, closely monitor construction conditions and developments at the site for timely supervision. Power Project Management Board 1 should continue to strictly manage the project, implementing simultaneous solutions to ensure progress and quality.

Find more information about the 500kV Lao Cai - Vinh Yen transmission line project here.

500kV Lao Cai - Vinh Yen Transmission Line Project:

  • Investor: Vietnam Electricity;
  • Investor's representative for project management: Power Project Management Board 1;
  • Survey and engineering consultants: Consortium of Power Engineering Consulting Joint Stock Company 1 (EVNPECC1) and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Total investment: Over 7,410 billion VND;
  • Project route through: Lao Cai, Yen Bai, Phu Tho, and Vinh Phuc provinces;
  • Construction implementation: March 2025;
  • Expected completion: Before September 2nd 2025.

EVN.COM.VN

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827327

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice