NEWS & EVENTS

EVN’s leaders inspected the construction site of 500kV Lao Cai - Vinh Yen transmission line in Vinh Phuc, Phu Tho

25/03/2025 10:11:26

On March 24th, EVN’s Vice President Mr.Pham Hong Phuong directly inspected the construction progress of packages 8, 9, and 10 of the 500kV Lao Cai - Vinh Yen transmission line project in Vinh Phuc and Phu Tho provinces.

EVN’s leaders inspected construction at position 364 of the 500kV Lao Cai - Vinh Yen transmission line project

In the first week following the groundbreaking command issued by the Prime Minister (on March 16th), the construction of the 500kV Lao Cai – Vinh Yen transmission line has been urgently and actively implemented by EVN and contractors.

Through on-site inspection, EVN’s leaders noted that some contractors have adopted the spirit of "overcoming heat, conquering rain," "3 shifts, 4 teams," and valuable lessons learned from the 500kV circuit-3 transmission line project to implement this project with the highest determination.

On March 24th, EVN’s leaders inspected the construction of packages 8, 9, and 10 of the project

EVN’s leaders required contractors to continue mobilizing additional human resources and arranging more machinery and equipment; they must deploy simultaneously at all foundation positions. Specifically, for package 8, Viet A contractor must mobilize sufficient excavators to simultaneously work at 24 foundation positions in March. For package 9, PCC1 Ninh Binh contractor must urgently supplement manpower for steel construction at positions where excavation is completed; coordinate with partners to immediately pour concrete at foundations that meet conditions. For package 10, Song Da 5 contractor must mobilize 22 teams to work at 22 positions by the end of March.

The EVN’s Vice President also directed the supervision consultant to promptly accept phase transitions, closely monitor construction conditions and developments at the site for timely supervision. Power Project Management Board 1 should continue to strictly manage the project, implementing simultaneous solutions to ensure progress and quality.

Find more information about the 500kV Lao Cai - Vinh Yen transmission line project here.

500kV Lao Cai - Vinh Yen Transmission Line Project:

  • Investor: Vietnam Electricity;
  • Investor's representative for project management: Power Project Management Board 1;
  • Survey and engineering consultants: Consortium of Power Engineering Consulting Joint Stock Company 1 (EVNPECC1) and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Total investment: Over 7,410 billion VND;
  • Project route through: Lao Cai, Yen Bai, Phu Tho, and Vinh Phuc provinces;
  • Construction implementation: March 2025;
  • Expected completion: Before September 2nd 2025.

EVN.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097049

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice