Inauguration of Seraphin Waste-to-Energy Plant with capacity of 2,250 tons/day and night

19/09/2025 14:14:19

On the morning of September 18th, 2025, at the Xuan Son Solid Waste Treatment Complex in Tung Thien Ward, the Hanoi People's Committee and AMACCAO Group organized the inauguration ceremony of the Seraphin Waste-to-Energy Plant with a capacity of 2,250 tons/day and night.

Attending the inauguration ceremony were Mr. Tran Sy Thanh - Central Party Committee Member, Deputy Secretary of the Municipal Party Committee, Chairman of Hanoi People's Committee; Mr. Nguyen Trong Dong Standing Committee Member of the Municipal Party Committee, Vice Chairman of Hanoi People's Committee and Mr. Pham Qui Tien - Vice Chairman of the Municipal People's Council.

Hanoi city leaders toured the plant's operation center. Photo: Hoang Son

Currently, approximately 7,600 tons of domestic waste are generated daily in Hanoi, creating significant pressure on infrastructure, environment, and people's lives. For many years, landfill methods have remained predominant, which are both outdated and harbor numerous risks of soil, water, and air pollution. In this context, bringing the Seraphin Waste-to-Energy Plant into commercial operation is considered a breakthrough solution.

The plant has a processing capacity of 2,250 tons of waste/day and night - equivalent to approximately one-third of the entire city's domestic waste volume and generates 37 MW of electricity per hour, sufficient to supply tens of thousands of households. Throughout the entire waste incineration process, the plant utilizes Martin technology (Germany), helping reduce landfill rates by 97-98%, while ensuring emission indicators, exhaust gases, and fine dust meet stringent EU2010 standards.

Notably, by-products from the waste processing such as bottom ash are utilized to produce precast concrete and non-fired bricks, contributing to circular economy development.

Hanoi city leaders and AMACCAO Group representatives cut the ribbon to inaugurate the Seraphin Waste-to-Energy Plant. Photo: Hoang Son

With a total investment of approximately 5,000 billion VND over an area of 6.28 hectares, Seraphin is the first modern waste-to-energy plant owned and invested by a Vietnamese private enterprise as the main investor, general contractor for engineering, construction, and supervision consulting, thereby affirming domestic enterprises' capabilities in mastering high technology.

The Seraphin project was granted investment policy approval by the Hanoi People's Committee in late 2021, with construction commencing in March 2022. After more than three years of continuous construction, on May 1st 2025, the plant began receiving and processing waste, and by July 1st 2025, it had commenced commercial electricity generation. This timeline is evaluated as "record-breaking," as similar waste-to-energy projects worldwide typically take 5-8 years to complete.

Vice Chairman of Hanoi People's Committee Mr. Nguyen Trong Dong spoke at the inauguration ceremony. Photo: Hoang Son

Speaking at the inauguration ceremony, Vice Chairman of Hanoi People's Committee Mr. Nguyen Trong Dong commended the active role of municipal departments, committees, and sectors, particularly the departments of Construction, Finance, Agriculture and Environment for their timely advice, obstacle resolution, and facilitation enabling the project to proceed on schedule with quality and efficiency.

"Putting the Seraphin Waste-to-Energy Plant into operation is only the beginning step. The city sets the goal of completely ending domestic waste landfilling in the coming period, replacing it with advanced treatment technologies such as waste-to-energy incineration, recycling, and reuse," Vice Chairman of the People's Committee Mr. Nguyen Trong Dong emphasized.

Overview of the Seraphin Waste-to-Energy Plant. Photo: Hoang Son

To achieve this goal, comrade Nguyen Trong Dong stated that Hanoi city will continue to replicate the model of modern waste-to-energy plants, construct centralized waste treatment complexes, while simultaneously promoting waste separation at source - a key solution linked to raising community awareness. The city also commits to creating the most favorable conditions for enterprises investing in the waste treatment sector, aimed at building a clean, friendly, and modern Hanoi.

HANOIMOI.VN

Seraphin Waste-to-Energy Plant Project

Location: Xuan Son Solid Waste Treatment Complex, Tung Thien Ward, Hanoi City.

Rated waste receiving capacity: 2,250 tons day/night.

Power generation capacity: 37MW per hour, sufficient to supply tens of thousands of households. Throughout the entire waste incineration process, the plant utilizes Martin technology (Germany), helping reduce landfill rates by 97-98%, while ensuring emission indicators, exhaust gases, and fine dust meet stringent EU2010 standards.

Scope of work of Power Engineering Consulting Joint Stock Company 4 (EVNPECC4): implementing the consulting package for preparing the adjusted Feasibility Study (FS) Report, adjusted Environmental Impact Assessment Report, Technical Design and Detailed Design.

Representative of EVNPECC4, Mr. Nguyen Manh Cuong - Director of Northern Affiliate (far right) attending the inauguration ceremony of Seraphin Waste-to-Energy Plant on September 18th, 2025

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827143

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice