NEWS & EVENTS

Preparation for the groundbreaking ceremony of Bac Ai Pumped Storage Hydropower Plant in late February 2025

18/02/2025 16:57:39

The Bac Ai Pumped Storage Hydropower Plant project, located in Ninh Thuan province, has been approved by the Prime Minister under the National Power Development Plan for the period 2021–2030, with a vision to 2050. This is Vietnam’s first pumped storage hydropower project, with Vietnam Electricity (EVN) as the investor. The Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) was assigned by EVN to research and develop the project since 2006. The project is scheduled to commence construction in February 2025, with the first generating unit to be commissioned in December 2029 and full project completion expected by May 2031.

EVNPECC4 – The engineering consultant for the first Pumped Storage Hydropower Project in Vietnam

The Bac Ai Pumped Storage Hydropower Plant has a total capacity of 1,200 MW, consisting of four pump/turbine-generator/motor units, each with a capacity of 300 MW. The total investment for the project is approximately VND 21,100 billion, with funding sourced from loans and EVN’s allocated capital. The first generating unit is expected to commence operation in December 2029, and the entire project is set for completion in May 2031.

Accordingly, EVNPECC4 has undertaken key consultancy roles, including site surveys, investment report, feasibility study, environmental impact assessment, technical design, bidding document preparation, and detailed design for the project.

General Drawing of 3D Diagram - Bac Ai Pumped Storage Hydropower Plant
The outlet works of the Bac Ai Pumped Storage Hydropower Plant project were completed in March 2021

This project holds significant importance for the national power system, particularly as numerous renewable energy plants (solar and wind) with low stability are being integrated into the grid. The primary function of the project is to generate electricity to cover the peak of the system’s load diagram, helping to balance fluctuations in the load curve by utilizing pump power during off-peak hours and generating electricity during peak demand periods.

In October 2023, representatives from EVNPECC4 presented the design plan for the Bac Ai Pumped Storage Hydropower Plant to a consortium of co-financiers at Song Cai Reservoir – the lower reservoir of the project.

Signing of the Construction Contract for Bac Ai Pumped Storage Hydropower Plant Project (Phase 2)

On February 13th 2025, EVN, in collaboration with Power Project Management Board 3 and a contractor consortium (including Lung Lo Construction Corporation, Song Da Corporation, LILAMA 10 Joint Stock Company, SCI E&C Joint Stock Company, Construction 47 Joint Stock Company, Truong Son Construction Corporation, and Vietnam Construction and Import-Export Corporation), held a signing ceremony for contract package 02XL-BA: “Construction and Installation of Works for the Bac Ai Pumped Storage Hydropower Plant – Phase 2, Stage 1” in Ninh Thuan province.

EVN and Contractor Consortium signed construction contract for Bac Ai Pumped Storage Hydropower Plant – Phase 2, Stage 1 (Photo: EVN)

Speaking at the signing ceremony, EVN’s leadership emphasized that this is Vietnam’s first pumped storage hydropower project and a key project in EVN’s 2025 implementation plan. Throughout the investment preparation and project execution phases, EVN has received close attention and guidance from the Government, the Ministry of Industry and Trade, the Commission for Management of State Capital at Enterprises, as well as strong support and coordination from Ninh Thuan Provincial People’s Committee and relevant departments. These collaborative efforts have ensured the formulation of an optimal construction strategy, the selection of suitable contractors, and compliance with safety, progress, and quality requirements.

EVN has assigned Power Project Management Board 3 and the contractor consortium under contract package 02XL-BA to manage and execute the project, ensuring adherence to quality and environmental standards. Resources and equipment will be concentrated to expedite progress and strive for project completion as scheduled.

Bac Ai Pumped Storage Hydropower Plant Project, Ninh Thuan Province:

  • Investor: Vietnam Electricity (EVN);
  • Project Management and Administration: Power Project Management Board 3;
  • Location: Bac Ai District, Ninh Thuan Province;
  • Engineering Consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Total Investment: 21,101 billion VND;
  • Construction Commencement: February 2025;
  • Commissioning Schedule: Unit 1: December 2029, Unit 2: April 2030, Unit 3: August 2030, Unit 4: December 2030;
  • Expected Full Project Completion: May 2031.

According to EVN.COM.VN

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827333

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice