Prime Minister praises EVN and EVNNPT for promoting Heroic tradition in implementing 500kV circuit 3 transmission line Project

04/04/2024 09:14:40

Chairing the conference on the implementation status of 500 kV circuit 3 transmission line projects from Quang Trach to Pho Noi on the afternoon of April 1, in Hanoi, Prime Minister Pham Minh Chinh praised the Vietnam Electricity (EVN), directly the National Power Transmission Corporation (EVNNPT), has promoted the Heroic tradition and strongly deployed solutions to promote the project’s implementation.

The conference is held in an offline combined online format. Deputy Prime Minister Tran Hong Ha attended the conference at the video point in Khanh Hoa province.

Attending the conference were Minister of Industry and Trade Nguyen Hong Dien; Minister and Chairman of the Government Office Tran Van Son; leaders of ministries, branches, and agencies at the Central level; leaders of Hung Yen, Hai Duong, Thai Binh, Nam Dinh, Ninh Binh, Thanh Hoa, Nghe An, Ha Tinh, and Quang Binh provinces.

On EVN's side were the Chairman of EVN’s Board of Directors Dang Hoang An, EVN President and CEO Nguyen Anh Tuan, and the leader of the National Power Transmission Corporation.

The project has achieved many encouraging results

Recently, with the drastic direction and action of the Government, the 500kV transmission line project from Quang Trach to Pho Noi has achieved many encouraging results. Specifically, the project has currently completed signing contracts for 225/226 bidding packages; and completed site clearance of 100% of pole foundation positions (1177/1177) and 45.92% (231/503) of span.

Prime Minister chairs the conference - Photo: VGP/Nhat Bac

Currently, the project has been simultaneously implementing construction on 100% of the foundation positions of the entire route; completed foundation casting in 430/1177 positions; completed erection of 43/1177 pole positions; and 59/1177 pole positions are being erected.

To strive to complete the projects under the Prime Minister's direction, EVN/EVNNPT recommends that the People's Committees of the provinces continue to support the right-of-way clearance, handing over the remaining spans to the investor to carry out wire pulling (expected to start on April 10, 2024); at the same time, direct the People's Committees of districts/site clearance councils to urgently inventory, count, and determine the number of houses/households that must be relocated and resettled, and carry out resettlement procedures for the households, ensuring the right-of-way safety to energize the project by June 2024...

Prime Minister thanks, acknowledges, and appreciates ministries, branches, localities, EVN, and EVNNPT - Photo: VGP/Nhat Bac

Put into operation no later than June 30, 2024

Deputy Prime Minister Tran Hong Ha gives speech - Photo: VGP/Minh Khoi

Chairman of EVN's Board of Directors Dang Hoang An speaks at conference - Photo: VGP/Nhat Bac

Assessing the important projects, the implementation progress basically meets the requirements, but the workload is still very large. To complete the project as planned, Prime Minister Pham Minh Chinh required ministries, sectors, localities, and units to focus on coordinating and synchronously deploying the remaining tasks, continuing to coordinate and review related issues; promptly handle authorized problems; striving to overcome difficulties and challenges, ensure timely progress, quality, and labor safety, especially labor safety in locations with difficult and complex terrain and unfavorable weather.

Conference held online at Government headquarters with 9 provinces where the project passed through - Photo: VGP/Nhat Bac

EVN, directly EVNNPT, continues to urge construction contractors to concentrate human resources and construction machinery to soon complete the pole foundations construction and organize the pole erection and wire pulling following the committed schedule; materials and equipment supply contractors urgently complete the manufacture and transport it to the construction site for synchronous erection.

The Prime Minister required relevant units to strive to complete the policy framework to compensate people affected by the project before April 10, 2024; Complete the casting of foundation positions before April 30; Complete the pole erection before May 30; Basically complete project items on June 20, 2024, to energize and put into operation no later than June 30, 2024.

The 500kV circuit-3 transmission line project from Quang Trach to Pho Noi

- Project investor: National Power Transmission Corporation (under EVN)

- Total investment: approximately 22,000 billion VND

- Scale: Includes 2 circuits of 500kV transmission line, approximately 519km length. Starting point is the 500kV Quang Trach Switchyard (Quang Binh), ending point is the 500kV Pho Noi substation (Hung Yen)

- Engineering consultants: Power Engineering Consulting Joint Stock Companies 1, 2, 4 and Institute of Energy

- The Northern Power Projects Management Board (NPMB) on behalf of EVNNPT manages and operates 2 sections: Nam Dinh I Thermal Power Plant – Thanh Hoa and Nam Dinh I Thermal Power Plant – Pho Noi.

- The Central Power Projects Management Board (CPMB) on behalf of EVNNPT manages and operates 2 sections: Quang Trach – Quynh Luu and Quynh Luu – Thanh Hoa.

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251880

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4