Prime Minister praises EVN and EVNNPT for promoting Heroic tradition in implementing 500kV circuit 3 transmission line Project

04/04/2024 09:14:40

Chairing the conference on the implementation status of 500 kV circuit 3 transmission line projects from Quang Trach to Pho Noi on the afternoon of April 1, in Hanoi, Prime Minister Pham Minh Chinh praised the Vietnam Electricity (EVN), directly the National Power Transmission Corporation (EVNNPT), has promoted the Heroic tradition and strongly deployed solutions to promote the project’s implementation.

The conference is held in an offline combined online format. Deputy Prime Minister Tran Hong Ha attended the conference at the video point in Khanh Hoa province.

Attending the conference were Minister of Industry and Trade Nguyen Hong Dien; Minister and Chairman of the Government Office Tran Van Son; leaders of ministries, branches, and agencies at the Central level; leaders of Hung Yen, Hai Duong, Thai Binh, Nam Dinh, Ninh Binh, Thanh Hoa, Nghe An, Ha Tinh, and Quang Binh provinces.

On EVN's side were the Chairman of EVN’s Board of Directors Dang Hoang An, EVN President and CEO Nguyen Anh Tuan, and the leader of the National Power Transmission Corporation.

The project has achieved many encouraging results

Recently, with the drastic direction and action of the Government, the 500kV transmission line project from Quang Trach to Pho Noi has achieved many encouraging results. Specifically, the project has currently completed signing contracts for 225/226 bidding packages; and completed site clearance of 100% of pole foundation positions (1177/1177) and 45.92% (231/503) of span.

Prime Minister chairs the conference - Photo: VGP/Nhat Bac

Currently, the project has been simultaneously implementing construction on 100% of the foundation positions of the entire route; completed foundation casting in 430/1177 positions; completed erection of 43/1177 pole positions; and 59/1177 pole positions are being erected.

To strive to complete the projects under the Prime Minister's direction, EVN/EVNNPT recommends that the People's Committees of the provinces continue to support the right-of-way clearance, handing over the remaining spans to the investor to carry out wire pulling (expected to start on April 10, 2024); at the same time, direct the People's Committees of districts/site clearance councils to urgently inventory, count, and determine the number of houses/households that must be relocated and resettled, and carry out resettlement procedures for the households, ensuring the right-of-way safety to energize the project by June 2024...

Prime Minister thanks, acknowledges, and appreciates ministries, branches, localities, EVN, and EVNNPT - Photo: VGP/Nhat Bac

Put into operation no later than June 30, 2024

Deputy Prime Minister Tran Hong Ha gives speech - Photo: VGP/Minh Khoi

Chairman of EVN's Board of Directors Dang Hoang An speaks at conference - Photo: VGP/Nhat Bac

Assessing the important projects, the implementation progress basically meets the requirements, but the workload is still very large. To complete the project as planned, Prime Minister Pham Minh Chinh required ministries, sectors, localities, and units to focus on coordinating and synchronously deploying the remaining tasks, continuing to coordinate and review related issues; promptly handle authorized problems; striving to overcome difficulties and challenges, ensure timely progress, quality, and labor safety, especially labor safety in locations with difficult and complex terrain and unfavorable weather.

Conference held online at Government headquarters with 9 provinces where the project passed through - Photo: VGP/Nhat Bac

EVN, directly EVNNPT, continues to urge construction contractors to concentrate human resources and construction machinery to soon complete the pole foundations construction and organize the pole erection and wire pulling following the committed schedule; materials and equipment supply contractors urgently complete the manufacture and transport it to the construction site for synchronous erection.

The Prime Minister required relevant units to strive to complete the policy framework to compensate people affected by the project before April 10, 2024; Complete the casting of foundation positions before April 30; Complete the pole erection before May 30; Basically complete project items on June 20, 2024, to energize and put into operation no later than June 30, 2024.

The 500kV circuit-3 transmission line project from Quang Trach to Pho Noi

- Project investor: National Power Transmission Corporation (under EVN)

- Total investment: approximately 22,000 billion VND

- Scale: Includes 2 circuits of 500kV transmission line, approximately 519km length. Starting point is the 500kV Quang Trach Switchyard (Quang Binh), ending point is the 500kV Pho Noi substation (Hung Yen)

- Engineering consultants: Power Engineering Consulting Joint Stock Companies 1, 2, 4 and Institute of Energy

- The Northern Power Projects Management Board (NPMB) on behalf of EVNNPT manages and operates 2 sections: Nam Dinh I Thermal Power Plant – Thanh Hoa and Nam Dinh I Thermal Power Plant – Pho Noi.

- The Central Power Projects Management Board (CPMB) on behalf of EVNNPT manages and operates 2 sections: Quang Trach – Quynh Luu and Quynh Luu – Thanh Hoa.

EVN.COM.VN

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827398

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice