Quynh Luu - Thanh Hoa 500kV Circuit-3 transmission line operational
The National Power Transmission Corporation (EVNNPT) and the Central Vietnam Power Project Management Board (CPMB) in collaboration with relevant units sent electricity to the Quynh Luu - Thanh Hoa 500kV Circuit-3 transmission line on August 19 morning.
Representatives of EVNNPT and related units at the ceremony to send electricity to the Quynh Luu - Thanh Hoa 500kV Circuit-3 transmission line. (Photo: VGP)
The National Power Transmission Corporation (EVNNPT) and the Central Vietnam Power Project Management Board (CPMB) in collaboration with relevant units sent electricity to the Quynh Luu - Thanh Hoa 500kV Circuit-3 transmission line on August 19 morning.
As part of the 500kV Circuit-3 power transmission line project, which runs from Quang Trach in the central province of Quang Binh to Pho Noi in the northern province of Hung Yen, the line is invested by the EVNNPT, managed by the CPMB, and operated by Power Transmission Company 1 (PTC1).
The 92-km line passes through the central provinces of Nghe An and Thanh Hoa. Its construction began on January 18.
It is expected to reduce the load and avoid overloading of existing 500kV lines and help improve transmission capacity, thus contributing to strengthening capacity from power sources in the north-central region to the load centre in the northern region.
Previously, on the morning of August 19th 2024, under the chairmanship of EVNNPT Deputy General Director, Chairman of the Investor-level Acceptance Council - Mr. Truong Huu Thanh chaired the meeting and all Council members agreed to energize the project (Photo: EVNNPT)
The completion and commissioning of the project meets the Prime Minister's directives, serving as a significant motivation for completing the entire 500kV Circuit-3 power transmission line project in the coming days./.
|
The 500kV circuit-3 Quynh Luu - Thanh Hoa transmission line project:
- Project investor: National Power Transmission Corporation (under EVN);
- Investor representative: Central Power Project Management Board;
- Engineering entities: Consortium of Power Engineering Consulting Joint Stock Company 1 and Power Engineering Consulting Joint Stock Company 2;
- Site supervision entities: Consortium of EVN International Joint Stock Company and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
- Project appraisal entity: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
- Operator: Power Transmission Company 1;
- This is a special energy project, group A;
- Scale: 92km, double-circuit, 200 tower positions;
- Commencement date: 18th January 2024;
- Energization date: 19th August 2024.
|
View more information about the 500kV circuit-3 transmission line project from Quang Trach to Pho Noi here.