Signboard mounting for project Van Phong 500kV substation and connection line to welcome the 8th Congress of Vietnam Trade Union

28/04/2023 22:12:22

On April 7, 2023, in Khanh Hoa, the Vietnam General Confederation of Labor in collaboration with the Vietnam Electricity (EVN), the National Power Transmission Corporation (EVNNPT) organized a ceremony for mounting the project signboard at Vietnam General Confederation of Labor level for the project "Van Phong 500kV substation and connection line". This project aims to welcome the 8th Congress of Vietnam Trade Union for the term of 2023 - 2028.

Mr. Duong Quang Thanh - Chairman of EVN's Board of Directors speaking at ceremony

Overcoming difficulties

The scale of Van Phong 500kV substation and connection line project is composed of installing 2 new 900MVA transformers; 6 500kV feeders; 13 220kV feeders; building a 26.1 km long 220kV transmission line from Van Phong 500kV substation to Van Phong 220kV substation and connected to one circuit of Van Phong - Tuy Hoa 220kV transmission line.

The project started construction in September 2021. According to the schedule agreed with the project owner of Van Phong 1 BOT Thermal Power Plant, this project must be completed before December 26, 2022. The construction duration of this project is very short compared to other projects of similar size and nature. After 14 months of rush implementation on the construction site, the project was completed, energized and put into operation on November 28, 2022, ahead of schedule.

The project's energizing ensures a safe and uninterrupted power supply to Khanh Hoa province and neighboring provinces; meets the electricity demand for the key economic region of the South Central Coast; absorbs the capacity of Van Phong 1 BOT thermal power plant and renewable energy stations in Ninh Thuan, Khanh Hoa and Phu Yen provinces; contributing to ensuring the N-1 criterion, strengthening the stability of the power system, improving the reliability and safety of power supply for the national power system.

Mr. Nguyen Dinh Khang - Chairman of Vietnam General Confederation of Labor speaking at ceremony

Mr. Nguyen Dinh Khang - Chairman of Vietnam General Confederation of Labor awarding Decision on signboard mounting to welcome the 8th Trade Union Congress

Exciting emulation movement

Delegates performing ceremony of signboard mounting

At the ceremony, many collectives and individuals who had achieved excellent achievements in the emulation movement to complete the project on schedule were awarded Certificates of Merit from the Vietnam General Confederation of Labor, the Commission for Management of State Capital at Enterprises, Khanh Hoa Provincial People's Committee, EVN, Vietnam Electricity Trade Union.
Mr. Duong Quang Thanh - Chairman of EVN'S Board of Directors and Mr. Tran Dinh Nhan - President & CEO of EVN awarded Certificates of Merit to many collectives which have achieved excellent accomplishments in the emulation movement to complete the project schedule. Representative of EVNPECC4, Mr. Nguyen Xuan Phuong - Deputy General Director (the second from the left) was honoured to receive the Certificate of Merit.

Van Phong 500kV substation and connection line:

- EVN assigns EVNNPT as the project owner;

- The Central Power Project Management Board on behalf of the project owner manages the project implementation;

- Project location: Ninh Hoa town, Khanh Hoa province;

- Total investment cost: About VND 1,098 billion;

- Design consulting unit: Power Engineering Consulting Joint Stock Company No.2;

- Supervision consulting unit: Consortium of Power Engineering Consulting Joint Stock Company No.4 (EVNPECC4) and EVN International Joint Stock Company;

- Construction contractors: Alphanam E&C Joint Stock Company and Hai Phong Electrical Installation & Construction Investment Joint Stock Company;

- Contractor for transformer installation and calibration experiment: Power Transmission Engineering Service Company;

- Operation unit: Power Transmission Company No.3.

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251917

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4