State Steering Committee had a meeting on land clearance work and implementation status of the 500kV Lao Cai - Vinh Yen transmission line project

01/08/2025 11:13:50

On July 31st, at the headquarters of the Ministry of Industry and Trade, Deputy Minister Nguyen Hoang Long - Standing Member of the State Steering Committee for nationally important programs and key energy sector projects chaired an online meeting on land clearance work and implementation status of the 500kV Lao Cai - Vinh Yen transmission line project.

Attending the meeting were representatives of the leadership of Lao Cai and Phu Tho provinces; representatives of the Government Office and relevant ministries and sectors; leaders of units under the Ministry of Industry and Trade.

From Vietnam Electricity (EVN), there were Mr. Pham Hong Phuong – Vice President of EVN, Mr. Do Quang Khai - Deputy Director of Power Project Management Board 1 (EVNPMB1).

Deputy Minister of Industry and Trade Nguyen Hoang Long (standing) chaired the meeting. Photo: Ng.Tuan

Reporting on the implementation of compensation and land clearance work for the project, EVN’s Vice President Pham Hong Phuong said that the project has completed the land handover of for 468/468 tower foundation locations. Regarding the transmission corridor, the work of surveying, marking, handing over markers and counting has been completed; the work of approving compensation, support and resettlement plans (provisional and official) has achieved over 99%.

Regarding construction progress, to date the entire project has completed concrete foundation construction at all locations; completed erection of 259/468 tower locations (achieving 55.34%); currently installing and erecting 152/468 tower locations (32.48%); not yet erected towers at 57/468 locations (12.18%); completed stringing and pulling conductors for 10/242 anchor spans.

EVN and EVNPMB1 have been actively implementing the tasks assigned by the Government, as well as the directive conclusions of the Deputy Minister of Industry and Trade. The project owner resolutely directs contractors to concentrate all resources with the highest determination and efforts, overcoming all weather conditions and difficult terrain to complete tower erection before August 10th, 2025; conductor stringing and pulling before August 15th, 2025; acceptance testing and energizing the project before August 19th, 2025 according to the schedule assigned by the Prime Minister in Official Dispatch No. 81/CD-TTg dated June 3rd, 2025.

Continuing to coordinate with localities to complete documentation and procedures related to compensation and land clearance work, payment to people and mobilizing people's support to create conditions to accelerate the project's progress.

EVN’s Vice President Pham Hong Phuong (standing) reported on the implementation progress of the 500kV Lao Cai - Vinh Yen transmission line project. Photo: Ng.Tuan

To accelerate the completion of compensation and land clearance work, especially land clearance for the transmission corridor section and ensure the schedule for conductor stringing to complete construction and energization according to the Prime Minister's direction, EVN’s Vice President Pham Hong Phuong proposed that the People's Committees of Lao Cai and Phu Tho provinces direct the decisive handling of households obstructing construction and have plans to protect construction. Communes in the project area should urge people to clear trees and relocate; complete handling of remaining compensation and land clearance issues, approve and pay compensation, as well as accelerate approval and payment of resettlement compensation to households, recover all land, convert land use purposes, handle illegal construction…

The Departments of Industry and Trade of Lao Cai and Phu Tho province support mobilizing owners of hydroelectric plants affected by power outages on 220/110kV transmission lines and medium voltage lines to coordinate and agree on power outage schedules according to the project owner's proposal. Request Military Region 2 to continue maintaining forces and means to support construction at difficult locations and when cutting down and relocating assets in the transmission corridor. The Ministry of Public Security continues to direct provincial police to coordinate in propaganda, ensure security and order, mobilize people to support the project and not obstruct construction.

After hearing reports from EVN and opinions from localities, Deputy Minister of Industry and Trade Nguyen Hoang Long - on behalf of the State Steering Committee for nationally important projects and key energy sector projects - acknowledged and thanked the determination, responsibility and great contributions of localities, EVN and related parties.

The Deputy Minister emphasized that the 500kV Lao Cai - Vinh Yen transmission line project is an extremely important project, included in the list of projects celebrating the 80th anniversary of the August Revolution (August 19th, 1945 - August 19th, 2025), closely directed by the Prime Minister. The Deputy Minister highly appreciated that both Lao Cai and Phu Tho provinces committed to completing their tasks, have specific approaches and mobilize the entire political system, especially at the commune level - which has now been decentralized with sufficient authority to directly implement many tasks.

The Deputy Minister requested EVN to continue close coordination with localities. The Deputy Minister also highly appreciated EVN's report for clearly stating the remaining items and specific proposals, while requesting localities to urgently consider and resolve to ensure energization of the project on schedule by August 19th, 2025.

In addition, the Deputy Minister requested the Ministry of National Defense and Ministry of Public Security to continue directing forces in the area to coordinate with local authorities, both supporting construction and ensuring project safety, especially at key locations.

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251711

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4