Striving to complete the cluster of 220kV transmission line projects serving electricity import from Laos within November

28/10/2025 10:46:42

The National Power Transmission Corporation (EVNNPT) is accelerating two key 220 kV transmission line projects - Tuong Duong–Do Luong and Do Luong–Nam Cam - to strengthen power supply in Nghe An province and enable electricity imports from Laos, with completion targeted for November.

The National Power Transmission Corporation (EVNNPT) is accelerating two key 220 kV transmission line projects - Tuong Duong–Do Luong and Do Luong–Nam Cam - to strengthen power supply in Nghe An province and enable electricity imports from Laos, with completion targeted for November.

The Tuong Duong – Do Luong line spans over 80 km with two 220 kV circuits linking the Tuong Duong and Do Luong substations. In Nghe An province, all 192 tower foundations have been handed over, with 44 of 58 corridor segments cleared. Construction has completed 182 out of 192 towers and nearly 33 km of wiring.

The 37 km Do Luong – Nam Cam line, also with two circuits, has cleared 105 of 106 foundations and 38 of 51 segments. So far, 87 foundations, 83 towers and over 13 km of wiring have been completed, with work ongoing at several sites.

According to the Central Vietnam Power Projects Management Board (CPMB), the projects are broadly on schedule. But adverse weather, particularly storms between September and early October, has caused delays, especially in mountainous or flood-prone zones where access roads were damaged or sites submerged. Some localities have also yet to hand over all required land and corridor.

CPMB continues coordinating with land compensation committees and local authorities to meet with affected households, explain project policies, and encourage timely land handover.
 

220kV Do Luong – Nam Cam Transmission Line Project


At a review meeting on October 6, EVNNPT Deputy General Director Truong Huu Thanh commended the large volume of completed work, but stressed that overall progress still falls short of expectations.

The projects aims to transmit electricity from Lao wind farms, the Nam Mo hydropower cluster, and small and medium plants in western Nghe An to the national grid, enhancing supply reliability, strengthening regional grid connectivity, and supporting Nghe An’s industrial growth and socio-economic development.

Thanh urged CPMB and local authorities in Nghe An to promptly resolve land clearance issues and accelerate construction.

He requested contractors to add manpower, carry out foundation excavation, tower erection, and wiring simultaneously, and continue coordinating with CPMB to facilitate the handover of foundation locations for construction; while maintaining close coordination to ensure project completion by early November 2025 as directed by EVN./.

EVN.COM.VN

220kV Tuong Duong – Do Luong Transmission Line Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management Unit: Central Power Projects Management Board (CPMB);
  • Scope of Work of Power Engineering Consulting Joint Stock Company 4 (EVNPECC4): Engineering services for surveys serving the preparation of the Feasibility Study Report (FS), preparation of the FS and specialized reports; engineering services for surveys serving the preparation of the Technical Design – Total Cost Estimate, preparation of the Technical Design – Total Cost Estimate, Detail Design, and Bidding Documents; environmental monitoring during the construction phase; surveying and preparation of land parcel records for compensation and site clearance; and preparation of the Investment Policy Approval Dossier;
  • The project has a total length of over 80 km, comprising two 220kV circuits, starting from the 220kV Tuong Duong Substation and ending at the 220kV Do Luong Substation.

220kV Do Luong – Nam Cam Transmission Line Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management Unit: Central Power Projects Management Board (CPMB);
  • Operation and Maintenance Unit: Transmission Company No.1;
  • Supervision Consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • The project consists of two 220kV transmission line circuits from the 220kV Do Luong Substation to the 220kV Nam Cam Substation, with a total length of approximately 37 km. It also includes the expansion of feeder bays at the 220kV Do Luong Substation and the integration of the communication system for the 220kV Do Luong – Nam Cam transmission line.

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096776

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice