NEWS & EVENTS

Striving to complete the cluster of 220kV transmission line projects serving electricity import from Laos within November

28/10/2025 10:46:42

The National Power Transmission Corporation (EVNNPT) is accelerating two key 220 kV transmission line projects - Tuong Duong–Do Luong and Do Luong–Nam Cam - to strengthen power supply in Nghe An province and enable electricity imports from Laos, with completion targeted for November.

The National Power Transmission Corporation (EVNNPT) is accelerating two key 220 kV transmission line projects - Tuong Duong–Do Luong and Do Luong–Nam Cam - to strengthen power supply in Nghe An province and enable electricity imports from Laos, with completion targeted for November.

The Tuong Duong – Do Luong line spans over 80 km with two 220 kV circuits linking the Tuong Duong and Do Luong substations. In Nghe An province, all 192 tower foundations have been handed over, with 44 of 58 corridor segments cleared. Construction has completed 182 out of 192 towers and nearly 33 km of wiring.

The 37 km Do Luong – Nam Cam line, also with two circuits, has cleared 105 of 106 foundations and 38 of 51 segments. So far, 87 foundations, 83 towers and over 13 km of wiring have been completed, with work ongoing at several sites.

According to the Central Vietnam Power Projects Management Board (CPMB), the projects are broadly on schedule. But adverse weather, particularly storms between September and early October, has caused delays, especially in mountainous or flood-prone zones where access roads were damaged or sites submerged. Some localities have also yet to hand over all required land and corridor.

CPMB continues coordinating with land compensation committees and local authorities to meet with affected households, explain project policies, and encourage timely land handover.
 

220kV Do Luong – Nam Cam Transmission Line Project


At a review meeting on October 6, EVNNPT Deputy General Director Truong Huu Thanh commended the large volume of completed work, but stressed that overall progress still falls short of expectations.

The projects aims to transmit electricity from Lao wind farms, the Nam Mo hydropower cluster, and small and medium plants in western Nghe An to the national grid, enhancing supply reliability, strengthening regional grid connectivity, and supporting Nghe An’s industrial growth and socio-economic development.

Thanh urged CPMB and local authorities in Nghe An to promptly resolve land clearance issues and accelerate construction.

He requested contractors to add manpower, carry out foundation excavation, tower erection, and wiring simultaneously, and continue coordinating with CPMB to facilitate the handover of foundation locations for construction; while maintaining close coordination to ensure project completion by early November 2025 as directed by EVN./.

EVN.COM.VN

220kV Tuong Duong – Do Luong Transmission Line Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management Unit: Central Power Projects Management Board (CPMB);
  • Scope of Work of Power Engineering Consulting Joint Stock Company 4 (EVNPECC4): Engineering services for surveys serving the preparation of the Feasibility Study Report (FS), preparation of the FS and specialized reports; engineering services for surveys serving the preparation of the Technical Design – Total Cost Estimate, preparation of the Technical Design – Total Cost Estimate, Detail Design, and Bidding Documents; environmental monitoring during the construction phase; surveying and preparation of land parcel records for compensation and site clearance; and preparation of the Investment Policy Approval Dossier;
  • The project has a total length of over 80 km, comprising two 220kV circuits, starting from the 220kV Tuong Duong Substation and ending at the 220kV Do Luong Substation.

220kV Do Luong – Nam Cam Transmission Line Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management Unit: Central Power Projects Management Board (CPMB);
  • Operation and Maintenance Unit: Transmission Company No.1;
  • Supervision Consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • The project consists of two 220kV transmission line circuits from the 220kV Do Luong Substation to the 220kV Nam Cam Substation, with a total length of approximately 37 km. It also includes the expansion of feeder bays at the 220kV Do Luong Substation and the integration of the communication system for the 220kV Do Luong – Nam Cam transmission line.

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251345

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4