Successful energization of 110kV Thanh An Substation, 110kV An Lap Substation and Connection Line, 110kV Vinh Loi Substation (Binh Duong Province)

28/02/2025 18:08:57

On February 24th, 25th and 27th 2025, in Binh Duong province, the Southern Power Corporation (EVNSPC) successfully energized three substations engineered by Power Engineering Consulting Joint Stock Company 4 (EVNPECC4): 110kV Thanh An Substation, 110kV An Lap Substation and connection line, 110kV Vinh Loi Substation.

Successful energization of 110kV An Lap Substation and connection line, Binh Duong province

On February 24th, EVNSPC successfully energized the 110kV An Lap Substation and connection line in Binh Duong province. The substation is located at An Lap Industrial Zone, An Lap Commune, Dau Tieng District, Binh Duong Province.

110kV An Lap Substation and connection line (Photo: EVNSPC)

The project includes two transformers with a total capacity of 2x40MVA. In this phase, one transformer (1x40MVA) has been installed, with a reserved space for a second transformer in the future. The length of the connecting line to the 110kV Thanh An – Ben Cat substation is 150m. The substation occupies an area of 2,891m2, with a total investment of approximately VND 57.636 billion, funded by commercial credit sources. The Southern Power Project Management Board was assigned by EVNSPC to manage and operate the project.

Inspection before energizing the facility (Photo: EVNSPC)

Once operational, the substation will supply electricity to the An Lap Industrial Cluster, Dau Tieng District, and surrounding areas, including Bau Bang District and Ben Cat Town in Binh Duong Province. It will also connect and transfer power for the 110kV Dau Tieng, An Tay, and Thanh An substations in case of incidents while shortening power supply radius, improving voltage quality, and minimizing energy loss in the local distribution network. Furthermore, the project ensures grid reliability meeting N-1 criterion, contributing to the socio-economic development of Ben Cat Town and Binh Duong Province.

The project was successfully energized at 19:06 on February 24th 2025 (Photo: EVNSPC)

The timely completion of the project was achieved thanks to the strong leadership of the Binh Duong Provincial People's Committee, the support from the Dau Tieng District People's Committee and Tan Phuoc Ward People's Committee, as well as close coordination among the Southern Power Project Management Board, Binh Duong Power Company, EVNPECC4, Viet Power Construction Service Trading Company Limited, Southern Electrical Testing Company and the South Regional Load Dispatch Centre.

Commissioning of 110kV Thanh An Substation, Binh Duong Province

On February 25th EVNSPC successfully energized the 110kV Thanh An Substation in Binh Duong Province. The substation is located on DT744 Road, Thanh An Industrial Cluster, Co Trach Hamlet, Thanh An Commune, Dau Tieng District, Binh Duong Province.

The project commenced on December 25th 2023, and consists of two transformers with a total capacity of 2x40MVA. In this phase, one transformer (1x40MVA) has been installed, with a reserved space for a second transformer in the future. The substation covers an area of 2,714m2, with a total investment of nearly VND 70 billion, funded by commercial credit sources and EVNSPC’s equity capital. The Southern Power Project Management Board was assigned by EVNSPC to manage and operate the project.

Performing energization operations (Photo: EVNSPC)

Once energized and put into operation, the project will supply electricity to Thanh An Industrial Cluster, the demand loads in Dau Tieng District, and surrounding areas in Bau Bang District and Ben Cat Town. It will also connect and transfer power for the 110kV Dau Tieng and An Tay substations in case of incidents, reduce supply radius, improve voltage quality, and minimize energy loss in the local distribution network. Additionally, it will ensure grid reliability according to N-1 criterion, fostering socio-economic growth in Thuan An City and Binh Duong Province.

Southern Power Projects Management Board’s leaders directed the energization (Photo: EVNSPC)

The successful energization was due to decisive direction from the Provincial People's Committee, active support from Dau Tieng District People's Committee, Thanh An Commune People's Committee, Dau Tieng Rubber Corporation and EVNSPC departments, along with close coordination between the Southern Power Projects Management Board and related units including Binh Duong Power Company, EVNPECC4, Construction And Installation Electric Joint Stock Company, Southern Electrical Testing Company and the South Regional Load Dispatch Centre. 

EVNPECC4’s representatives with other units at the 110kV Thanh An Substation energization meeting (Photo: EVNSPC)

The energization sequence was completed successfully at 20:20 on February 25th 2025. EVNSPC and its affiliated units continue to urge contractors to finalize the entire project to supply electricity to customers in Binh Duong Province as soon as possible.

Technical acceptance testing for 110kV Vinh Loi Substation, Binh Duong Province

At 21:45 on February 27th EVNSPC successfully conducted the technical commissioning of the "110kV VSIP2 – MR2 Substation and Connection Line" project in Binh Duong Province, also known as the 110kV Vinh Loi Substation.

110kV Vinh Loi Substation (Photo: EVNSPC)

The substation is located at the corner of Bach Dang (D5) Street and Road No. 31 in the expanded VSIP2 Industrial Park, Vinh Tan Commune, Tan Uyen Town, Binh Duong Province.

The project consists of two transformers with a total capacity of 2x63MVA, a connection line with a total length of 7.524km, and an area of 3,186m2 for the substation. The total investment is approximately 152 billion VND, funded by EVNSPC’s basic depreciation and commercial loans. The Southern Power Project Management Board was assigned by EVNSPC to manage and operate the project.

110kV Vinh Loi Substation technical acceptance testing on the evening of February 27th (Photo: EVNSPC)

The objective of the 110kV Vinh Loi Substation is to meet the power demand of the expanding VSIP Industrial Park, Thu Dau Mot City, and Binh Duong Service Urban Area. The project also reduces the 22kV medium-voltage power supply radius, minimizes energy loss, and enhances grid reliability. Additionally, the substation improves operational flexibility by allowing load transfers among the 110/22kV substations within the area, supporting power capacity sharing with the 110kV VSIP2MR1 and 110kV Cong Xanh substations.

EVNSPC.VN

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827331

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice