Successful energization of 220kV Vinh Hao substation and connecting transmission line

06/02/2024 12:12:36

At 02:05 a.m. on January 31st 2024, Power Project Management Board 2 (EVNPMB2), in coordination with related units, organized the energization to put the 220kV Vinh Hao Substation and 220kV connecting transmission line project into operation (in Vinh Hai village, Vinh Hao commune, Tuy Phong district, Binh Thuan province).

This is a Grade I, Group B energy project invested by Vietnam Electricity (EVN), with EVNPMB2 representing EVN to manage and direct the project implementation. The engineering and construction consultants are the consortium of Telematic Joint Stock Company, Computer - Communication - Control 3C Incorporation, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) - Toshiba Transmission & Distribution Systems (Vietnam) Ltd. - Alphanam E&C Joint Stock Company. Power Transmission Company No.3 is the operating unit.

Power Project Management Board 2 and units carried out the energization of 220kV Vinh Hao Substation and 220kV Connecting Transmission Line Project

The project aims to strengthen transmission network capacity, relieve renewable energy generation capacity in Binh Thuan and neighboring provinces, ensure reliable operation of the 110kV Phan Ri - Ninh Phuoc transmission line. At the same time, it contributes to meeting the N-1 criterion, enhancing reliability and safety of electricity supply to the regional grid.

220/110/22kV-250MVA Transformer at the 220kV Vinh Hao substation

The project includes 2 components: The substation part - implemented the new 220/110kV substation construction with a total capacity of 500 MVA (this phase installed 01 220/110kV transformer - 250 MVA); The 220kV area has a scale of 06 bays, this phase carried out equipment installation for 04 220kV bays, reserving positions for 02 bays; for 110 kV switchyard,   equipment was installed for 01 incoming feeder located in the existing reserve land at 110kV Vinh Hai Switching Substation; Control, protection, measurement, metering, information and communication systems and SCADA: were equipped in accordance with EVN and EVNNPT regulations; complying with current standards and regulations. The 220kV connecting transmission line part - built a new section connecting 02 and 04 circuits which is transitionally connected to the 220kV Vinh Tan - Phan Ri transmission line, about 1.3 km length.

Some additional images of the project:

220kV Vinh Hao substation and 220kV connecting transmission line

Project investor: Vietnam Electricity (EVN)

Project management: Power Project Management Board 2 (EVNPMB2)

Project scale: new 220/110kV substation construction with total capacity of 500 MVA (this phase installed 01 220/110kV transformer - 250 MVA) and about 1.3km 220kV connecting transmission line which is transitionally connected to the 220kV Vinh Tan – Phan Ri transmission line (274/Vinh Tan – 274 Phan Ri)

Engineering Procurement Construction (EPC): The consortium of Telematic Joint Stock Company, Computer - Communication - Control 3C Incorporation, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) - Toshiba Transmission & Distribution Systems (Vietnam) Ltd. - Alphanam E&C Joint Stock Company.

Substation Engineering Centre

Related article

APPRECIATION LETTER 50 YEARS OF COMPANIONSHIP - TRUST BUILDING

APPRECIATION LETTER 50 YEARS OF COMPANIONSHIP - TRUST BUILDING

Dear Valued Clients, Partners and Shareholders On the occasion of the 50th Anniversary of Power Engineering Consulting Joint Stock Company 4 (PECC4), We would like to extend our heartfelt gratitude for your trust, partnership, and invaluable support throughout our journey of growth and development.

French Embassy and AFD visited 500kV Binh Duong 1 substation, recognizing successful cooperation with EVNNPT

French Embassy and AFD visited 500kV Binh Duong 1 substation, recognizing successful cooperation with EVNNPT

Recently, a delegation from the French Embassy in Vietnam and the French Development Agency (AFD) held a working session with the National Power Transmission Corporation (EVNNPT) and visited the 500kV Binh Duong 1 Substation.

Training on the BIM Software Ecosystem for EVNPECC4's Professional Consulting Engineers

Training on the BIM Software Ecosystem for EVNPECC4's Professional Consulting Engineers

Continuing its efforts to provide training and enhance the skills required to use software supporting surveying and engineering consulting activities, on 19th June 2026, Power Engineering Consulting Joint Stock Company No. 4 (EVNPECC4) signed a training contract with the Research and Development of Software in Construction (RDSIC) under the Hanoi University of Civil Engineering to organize Building Information Modeling (BIM) training courses for EVNPECC4's professional consulting engineers.

PRESS RELEASE

PRESS RELEASE

To: Valued Customers, Partners, Shareholders, Investors, and Employees of Power Engineering Consulting Joint Stock Company 4 (PECC4)

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2927828

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice