Successful energization of national grid power supply project to Con Dao

04/09/2025 16:02:41

At 04:05 on September 4, 2025, Vietnam Electricity (EVN)/Power Project Management Board No. 3 successfully energized the Con Dao 110kV Substation, serving the power supply from the national grid to Con Dao Special Zone.

Earlier, at 19:09 on September 2, 2025, EVN/Power Project Management Board No. 3 also successfully energized the national grid power supply project to Con Dao. This project was inaugurated in celebration of the 80th anniversary of the August Revolution and the National Day of the Socialist Republic of Vietnam (September 2, 1945 - September 2, 2025).

The successful energization of the project ensures the safe, continuous, and stable power supply for Con Dao Special Zone, meeting socio-economic development needs, safeguarding national defense and security, and improving local living standards. It replaces local diesel power generation, reduces power production costs, limits greenhouse gas emissions, and contributes to Vietnam’s commitments to reducing emissions and promoting sustainable development. The project affirms EVN’s capability in implementing large-scale, modern energy projects under complex and harsh marine construction conditions.

The national grid power supply project to Con Dao is a significant milestone in realizing the national energy infrastructure development strategy. It demonstrates the determination of the Government, the power sector, and all participating units to care for and develop infrastructure in islands and border areas of the country.

Some photos of the construction and laying of submarine power cables supplying electricity from the national grid to Con Dao:

General information about the project:

  • Investor: Vietnam Electricity (EVN).

    Scale: 110kV voltage level, total length of 103.7km, including:

  • Overhead transmission line: 17.5km across Vinh Chau Town, Soc Trang Province.
  • Submarine cable: 77.7km from VT32 (last offshore tower) to Con Dao.
  • Underground cable on the island: 8.5km from the landing point to the 110kV substation at An Hoi Power Plant, Con Dao.
  • Substations: Expansion of the 110kV bay at the Vinh Chau 220kV Substation (Soc Trang) and construction of the 110/22kV GIS Substation at Con Dao.
  • Total investment: VND 4,923 billion.
  • Commencement: December 2024.
  • Completion of submarine cable laying: August 12, 2025.
  • Completion of expansion at Vinh Chau 220kV Substation (Can Tho City): August 5, 2025.
  • Entire route commissioning: 18:42, August 22, 2025.
  • Official energization: 19:09, September 2, 2025.

EVN.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096888

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice