NEWS & EVENTS

Successful energization of the first 500kV - 900MVA transformer manufactured in Vietnam on the national power grid

19/12/2025 15:57:17

The national-level science and technology product - the 500kV-3x300MVA transformer designed and manufactured by Dong Anh Electrical Equipment Corporation (EEMC) was successfully energized at 11:23 PM on December 14th 2025, at 500kV Hoa Binh Substation (Hoa Binh Ward, Phu Tho Province). This is also the 500kV Hoa Binh Substation Capacity Upgrade Project invested by the National Power Transmission Corporation.

The 500kV-3x300MVA transformer is a product of a national-level science and technology project assigned by the Ministry of Science and Technology to EEMC. After being evaluated as an excellent product by the State-level Acceptance Council and approved for operation by Vietnam Electricity (EVN), EEMC deployed transportation and installation at the AT2 position of 500kV Hoa Binh Substation. Under the direction of EVNNPT and coordination of related units, the transformer unit completed installation, testing, and calibration on December 8th 2025.

AT2 Transformer at 500kV Hoa Binh Substation before the energization moment

The 500kV Hoa Binh Substation Capacity Upgrade Project is a special-grade, Group B energy project, with investment scale: replacing 2 existing 500/220/35kV-450MVA transformers with 2 new 500/220/35kV-900MVA transformers, increasing the total station capacity from 900MVA to 1,800MVA. Phase 1 replaces AT2 transformer from 450MVA to 900MVA; Phase 2 will replace AT1 transformer from 450MVA to 900MVA, expected to be completed in the coming phase.

Related units witnessing the successful energization moment of AT2 transformer

In the context of the 450MVA transformers at 500kV Hoa Binh  Substation operating at overload at many times, the station's capacity upgrade will contribute to ensuring operational safety as well as enhancing power transmission capacity from large and small hydropower sources in the Northwest region, ensuring stable power supply for Phu Tho province, Hanoi Capital and northern provinces, especially in the context of increasing load demand. This is an urgent project playing an important role in ensuring national energy security.

According to the Power Transmission Project Management Board (under EVNNPT), the project construction process faced many challenges due to construction in cramped conditions; equipment at 500kV Hoa Binh Substation being energized; hydropower plants in the area being mobilized at maximum capacity to optimize costs, making power outage registration difficult. Under the close direction of EVNNPT and support from dispatch levels, Power Transmission Company 1, and Hoa Binh Power Transmission Team, AT2 transformer of 500kV Hoa Binh Substation was successfully upgraded in capacity.

Previously, on the afternoon of December 14th 2025, the investor-level Acceptance Council chaired by EVNNPT Deputy General Director – Mr. Nguyen Ngoc Tan met and agreed to energize the project

For Dong Anh Electrical Equipment Corporation, this is an important step marking the first time a domestic enterprise has mastered the design and successful manufacture of a 500kV transformer with the largest capacity on Vietnam's transmission grid. At the same time, it helps EEMC train a team of design engineers, technology engineers, managers and skilled technical workers to master the technological equipment line for manufacturing 500kV transformers. This success is also a premise for EEMC to continue striving to research and develop new products, contributing to localizing major electrical equipment on Vietnam's power grid.

EVN.COM.VN

500kV Hoa Binh Substation Capacity Upgrade Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project management and operation representative: Power Transmission Project Management Board;
  • Operating unit: Power Transmission Company 1;
  • Engineering consultant and Supervision consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Special-grade, Group B energy project, with investment scale: replacing 2 existing 500/220/35kV-450MVA transformers with 2 new 500/220/35kV-900MVA transformers, increasing the total station capacity from 900MVA to 1,800MVA, completing the 220kV distribution system diagram suitable for the capacity upgrade scale. Phase 1 replaces AT2 transformer from 450MVA to 900MVA; Phase 2 will replace AT1 transformer from 450MVA to 900MVA, expected to be completed in the coming phase.
  • Chief Supervisor and Design Manager of the Project from EVNPECC4

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827124

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice