NEWS & EVENTS

Successful energization of the first 500kV - 900MVA transformer manufactured in Vietnam on the national power grid

19/12/2025 15:57:17

The national-level science and technology product - the 500kV-3x300MVA transformer designed and manufactured by Dong Anh Electrical Equipment Corporation (EEMC) was successfully energized at 11:23 PM on December 14th 2025, at 500kV Hoa Binh Substation (Hoa Binh Ward, Phu Tho Province). This is also the 500kV Hoa Binh Substation Capacity Upgrade Project invested by the National Power Transmission Corporation.

The 500kV-3x300MVA transformer is a product of a national-level science and technology project assigned by the Ministry of Science and Technology to EEMC. After being evaluated as an excellent product by the State-level Acceptance Council and approved for operation by Vietnam Electricity (EVN), EEMC deployed transportation and installation at the AT2 position of 500kV Hoa Binh Substation. Under the direction of EVNNPT and coordination of related units, the transformer unit completed installation, testing, and calibration on December 8th 2025.

AT2 Transformer at 500kV Hoa Binh Substation before the energization moment

The 500kV Hoa Binh Substation Capacity Upgrade Project is a special-grade, Group B energy project, with investment scale: replacing 2 existing 500/220/35kV-450MVA transformers with 2 new 500/220/35kV-900MVA transformers, increasing the total station capacity from 900MVA to 1,800MVA. Phase 1 replaces AT2 transformer from 450MVA to 900MVA; Phase 2 will replace AT1 transformer from 450MVA to 900MVA, expected to be completed in the coming phase.

Related units witnessing the successful energization moment of AT2 transformer

In the context of the 450MVA transformers at 500kV Hoa Binh  Substation operating at overload at many times, the station's capacity upgrade will contribute to ensuring operational safety as well as enhancing power transmission capacity from large and small hydropower sources in the Northwest region, ensuring stable power supply for Phu Tho province, Hanoi Capital and northern provinces, especially in the context of increasing load demand. This is an urgent project playing an important role in ensuring national energy security.

According to the Power Transmission Project Management Board (under EVNNPT), the project construction process faced many challenges due to construction in cramped conditions; equipment at 500kV Hoa Binh Substation being energized; hydropower plants in the area being mobilized at maximum capacity to optimize costs, making power outage registration difficult. Under the close direction of EVNNPT and support from dispatch levels, Power Transmission Company 1, and Hoa Binh Power Transmission Team, AT2 transformer of 500kV Hoa Binh Substation was successfully upgraded in capacity.

Previously, on the afternoon of December 14th 2025, the investor-level Acceptance Council chaired by EVNNPT Deputy General Director – Mr. Nguyen Ngoc Tan met and agreed to energize the project

For Dong Anh Electrical Equipment Corporation, this is an important step marking the first time a domestic enterprise has mastered the design and successful manufacture of a 500kV transformer with the largest capacity on Vietnam's transmission grid. At the same time, it helps EEMC train a team of design engineers, technology engineers, managers and skilled technical workers to master the technological equipment line for manufacturing 500kV transformers. This success is also a premise for EEMC to continue striving to research and develop new products, contributing to localizing major electrical equipment on Vietnam's power grid.

EVN.COM.VN

500kV Hoa Binh Substation Capacity Upgrade Project

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project management and operation representative: Power Transmission Project Management Board;
  • Operating unit: Power Transmission Company 1;
  • Engineering consultant and Supervision consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Special-grade, Group B energy project, with investment scale: replacing 2 existing 500/220/35kV-450MVA transformers with 2 new 500/220/35kV-900MVA transformers, increasing the total station capacity from 900MVA to 1,800MVA, completing the 220kV distribution system diagram suitable for the capacity upgrade scale. Phase 1 replaces AT2 transformer from 450MVA to 900MVA; Phase 2 will replace AT1 transformer from 450MVA to 900MVA, expected to be completed in the coming phase.
  • Chief Supervisor and Design Manager of the Project from EVNPECC4

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251358

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4