NEWS & EVENTS

Successfully energizing Lao Cai - Vinh Yen 500kV transmission line project

01/10/2025 16:19:39

At 23:12 on 30 September 2025, Vietnam Electricity, Power Project Management Board 1, in coordination with relevant units at the construction site, successfully energized the Lao Cai - Vinh Yen 500kV transmission line project, completing 8 months ahead of schedule compared to the original plan, according to the project investment policy decision approved by the Prime Minister. Previously, on September 29 and 30, 2025, the Lao Cai 500kV substation phase 2 and the 500kV feeders at the Vinh Yen 500kV substation were also successfully energized.

The Lao Cai – Vinh Yen 500kV transmission line project is a national key project, consisting of a 500kV double-circuit transmission line with a total length of 229.5km and 468 pole foundation sites. The project runs through two provinces, Lao Cai and Phu Tho (previously four provinces: Lao Cai, Yen Bai, Phu Tho, and Vinh Phuc), commencing at the Lao Cai 500kV substation and terminating at the Vinh Yen 500kV substation. The Project’s total investment, exceeding VND 7,410 billion, is financed with 80% from a loan provided by the Joint Stock Commercial Bank for Foreign Trade of Vietnam (Vietcombank) and 20% from EVN’s counterpart capital. In addition, the Lao Cai 500kV Substation Phase 2 project, with a total investment of over VND 1,564 billion, has also been completed, including the construction and energization of the 500kV switchyard and 500kV transformer, in synchronization with the Lao Cai – Vinh Yen 500kV transmission line project.

After being put into operation, the Lao Cai – Vinh Yen 500kV transmission line will have the capacity to transmit approximately 3,000MW from hydropower plants in the Northwest region and neighboring provinces to the national grid, while enhancing the country’s electricity import capacity. At the same time, it enhances inter-regional connectivity within the power system, improves the safe and stable operation of the national grid, reduces transmission losses, and increases the efficiency of EVN’s power production and business activities.

After successfully energizing the Lao Cai - Vinh Yen 500kV Transmission Line and the Lao Cai 500kV Substation along with the connecting 220kV transmission lines, Vietnam Electricity and Power Project Management Board 1 in coordination with relevant units at the construction site will continue completing the work and related administrative procedures, aiming to put the work into operation in early October 2025, practically celebrating the 71st anniversary of the Capital’s Liberation Day (October 10, 1954 - October 10, 2025), as well as to welcome the 1st Congress of the Government’s Party Committee for the 2025 - 2030 tenure and the 14th National Congress of the Party.

Lao Cai - Vinh Yen 500kV Transmission Line Project:

  • Investor: Vietnam Electricity;
  • Representative of the project owner responsible for project management and operation: Power Project Management Board 1;
  • Survey and engineering consultants: Joint venture of Power Engineering Consulting JSC 1 (EVNPECC1) and Power Engineering Consulting JSC 4 (EVNPECC4);
  • Total investment: More than VND 7,410 billion;
  • Project area: Lao Cai, Phu Tho;
  • Construction start date: 16 March 2025;
  • Energization date: 30 September 2025.

Lao Cai 500kV Substation Project Phase 2:

  • Investor: Vietnam Electricity;
  • Representative of the project owner responsible for project management and operation: Power Project Management Board 1;
  • Total investment: More than VND 1,564 billion;
  • Construction location: Lao Cai;
  • Construction start date: 21 April 2022;
  • Energization date: 30 September 2025.

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251493

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4