Successfully energizing Lao Cai - Vinh Yen 500kV transmission line project

01/10/2025 16:19:39

At 23:12 on 30 September 2025, Vietnam Electricity, Power Project Management Board 1, in coordination with relevant units at the construction site, successfully energized the Lao Cai - Vinh Yen 500kV transmission line project, completing 8 months ahead of schedule compared to the original plan, according to the project investment policy decision approved by the Prime Minister. Previously, on September 29 and 30, 2025, the Lao Cai 500kV substation phase 2 and the 500kV feeders at the Vinh Yen 500kV substation were also successfully energized.

The Lao Cai – Vinh Yen 500kV transmission line project is a national key project, consisting of a 500kV double-circuit transmission line with a total length of 229.5km and 468 pole foundation sites. The project runs through two provinces, Lao Cai and Phu Tho (previously four provinces: Lao Cai, Yen Bai, Phu Tho, and Vinh Phuc), commencing at the Lao Cai 500kV substation and terminating at the Vinh Yen 500kV substation. The Project’s total investment, exceeding VND 7,410 billion, is financed with 80% from a loan provided by the Joint Stock Commercial Bank for Foreign Trade of Vietnam (Vietcombank) and 20% from EVN’s counterpart capital. In addition, the Lao Cai 500kV Substation Phase 2 project, with a total investment of over VND 1,564 billion, has also been completed, including the construction and energization of the 500kV switchyard and 500kV transformer, in synchronization with the Lao Cai – Vinh Yen 500kV transmission line project.

After being put into operation, the Lao Cai – Vinh Yen 500kV transmission line will have the capacity to transmit approximately 3,000MW from hydropower plants in the Northwest region and neighboring provinces to the national grid, while enhancing the country’s electricity import capacity. At the same time, it enhances inter-regional connectivity within the power system, improves the safe and stable operation of the national grid, reduces transmission losses, and increases the efficiency of EVN’s power production and business activities.

After successfully energizing the Lao Cai - Vinh Yen 500kV Transmission Line and the Lao Cai 500kV Substation along with the connecting 220kV transmission lines, Vietnam Electricity and Power Project Management Board 1 in coordination with relevant units at the construction site will continue completing the work and related administrative procedures, aiming to put the work into operation in early October 2025, practically celebrating the 71st anniversary of the Capital’s Liberation Day (October 10, 1954 - October 10, 2025), as well as to welcome the 1st Congress of the Government’s Party Committee for the 2025 - 2030 tenure and the 14th National Congress of the Party.

Lao Cai - Vinh Yen 500kV Transmission Line Project:

  • Investor: Vietnam Electricity;
  • Representative of the project owner responsible for project management and operation: Power Project Management Board 1;
  • Survey and engineering consultants: Joint venture of Power Engineering Consulting JSC 1 (EVNPECC1) and Power Engineering Consulting JSC 4 (EVNPECC4);
  • Total investment: More than VND 7,410 billion;
  • Project area: Lao Cai, Phu Tho;
  • Construction start date: 16 March 2025;
  • Energization date: 30 September 2025.

Lao Cai 500kV Substation Project Phase 2:

  • Investor: Vietnam Electricity;
  • Representative of the project owner responsible for project management and operation: Power Project Management Board 1;
  • Total investment: More than VND 1,564 billion;
  • Construction location: Lao Cai;
  • Construction start date: 21 April 2022;
  • Energization date: 30 September 2025.

EVN.COM.VN

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827136

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice