NEWS & EVENTS

Successfully energizing Lao Cai - Vinh Yen 500kV transmission line project

01/10/2025 16:19:39

At 23:12 on 30 September 2025, Vietnam Electricity, Power Project Management Board 1, in coordination with relevant units at the construction site, successfully energized the Lao Cai - Vinh Yen 500kV transmission line project, completing 8 months ahead of schedule compared to the original plan, according to the project investment policy decision approved by the Prime Minister. Previously, on September 29 and 30, 2025, the Lao Cai 500kV substation phase 2 and the 500kV feeders at the Vinh Yen 500kV substation were also successfully energized.

The Lao Cai – Vinh Yen 500kV transmission line project is a national key project, consisting of a 500kV double-circuit transmission line with a total length of 229.5km and 468 pole foundation sites. The project runs through two provinces, Lao Cai and Phu Tho (previously four provinces: Lao Cai, Yen Bai, Phu Tho, and Vinh Phuc), commencing at the Lao Cai 500kV substation and terminating at the Vinh Yen 500kV substation. The Project’s total investment, exceeding VND 7,410 billion, is financed with 80% from a loan provided by the Joint Stock Commercial Bank for Foreign Trade of Vietnam (Vietcombank) and 20% from EVN’s counterpart capital. In addition, the Lao Cai 500kV Substation Phase 2 project, with a total investment of over VND 1,564 billion, has also been completed, including the construction and energization of the 500kV switchyard and 500kV transformer, in synchronization with the Lao Cai – Vinh Yen 500kV transmission line project.

After being put into operation, the Lao Cai – Vinh Yen 500kV transmission line will have the capacity to transmit approximately 3,000MW from hydropower plants in the Northwest region and neighboring provinces to the national grid, while enhancing the country’s electricity import capacity. At the same time, it enhances inter-regional connectivity within the power system, improves the safe and stable operation of the national grid, reduces transmission losses, and increases the efficiency of EVN’s power production and business activities.

After successfully energizing the Lao Cai - Vinh Yen 500kV Transmission Line and the Lao Cai 500kV Substation along with the connecting 220kV transmission lines, Vietnam Electricity and Power Project Management Board 1 in coordination with relevant units at the construction site will continue completing the work and related administrative procedures, aiming to put the work into operation in early October 2025, practically celebrating the 71st anniversary of the Capital’s Liberation Day (October 10, 1954 - October 10, 2025), as well as to welcome the 1st Congress of the Government’s Party Committee for the 2025 - 2030 tenure and the 14th National Congress of the Party.

Lao Cai - Vinh Yen 500kV Transmission Line Project:

  • Investor: Vietnam Electricity;
  • Representative of the project owner responsible for project management and operation: Power Project Management Board 1;
  • Survey and engineering consultants: Joint venture of Power Engineering Consulting JSC 1 (EVNPECC1) and Power Engineering Consulting JSC 4 (EVNPECC4);
  • Total investment: More than VND 7,410 billion;
  • Project area: Lao Cai, Phu Tho;
  • Construction start date: 16 March 2025;
  • Energization date: 30 September 2025.

Lao Cai 500kV Substation Project Phase 2:

  • Investor: Vietnam Electricity;
  • Representative of the project owner responsible for project management and operation: Power Project Management Board 1;
  • Total investment: More than VND 1,564 billion;
  • Construction location: Lao Cai;
  • Construction start date: 21 April 2022;
  • Energization date: 30 September 2025.

EVN.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096769

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice