At 01h12 on 26 April 2023, Power Project Management Board No.2 in coordination with relevant units successfully energize the Bo Y 220kV switching station (Ngoc Hoi district, Kon Tum province) and connection 220kV power lines.

The project is invested in and built to import electricity from Nam Kong 1, 2, and 3 hydropower plants (Laos) to Vietnam.

The project is invested by Vietnam Electricity. Power Project Management Board No.2 is assigned to manage and operate the project.

Power Project Management Board No.2 and units performing the energizing work of project of Bo Y 220kV switching station and connection 220kV power lines

The work was started in April 2022 with a new construction scale of Bo Y 220kV switching station, including ten 220kV bays, in this phase, six bays will be installed; construction of a 6.03km-long 2-circuit 220kV line connecting from the Bo Y 220kV switching station to the 220kV power line connecting the Nam Kong 2, 3 220kV substations (Laos); construction of a 4-circuit 220kV line with 0.8km length connecting from the Bo Y 220kV switching station to the Xekaman 1 (Laos) - Pleiku 2 220kV transmission line.

Bo Y 220kV switching station

During the implementation, the project encountered many difficulties. However, under the close direction of Vietnam Electricity and the high determination of the Power Project Management Board No.2 & the contractors, the project was successfully energized at 01h12'' on 26th April 2023.

When the Nam Kong 2 and 3 hydropower plant projects in Laos complete the procedures according to regulations, the Bo Y switching station will receive electricity from these plants (expected before 15 May 2023) to be integrated into Vietnam’s power system.

The project of Bo Y 220kV switching station and connection 220kV power lines contribute to the implementation of bilateral commitments on cooperation relations between the Governments of Vietnam and Laos in the field of energy development; at the same time strengthen the capacity of Vietnam’s power system, especially in the hot season.

The project of Bo Y 220kV switching station and connection 220kV power lines:

- The investor: Vietnam Electricity;

- Project Management: Power Project Management Board No.2;

- Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) is a consulting contractor for survey, engineering for different phases, feasibility study report, technical design, bidding documents preparation, detailed design; construction supervision;

- Construction contractor consortium: LILAMA Corporation, Power Construction Installation Limited Company No 4 and Toji Group Joint Stock Company;

- Total investment: 181 billion VND, was started in April 2022;

- Project location: Ngoc Hoi district, Kon Tum province.

Some pictures of EVNPECC4 participating in the project acceptance process:

EVNPECC4 joined the meeting with the Grassroots Acceptance Council

EVNPECC4 joined the meeting with the investor-level acceptance committee

Successfully energizing the project
EVNPECC4 participated in the project acceptance test to successfully complete the energizing
EVNPECC4 participated in the meeting to check the acceptance of Electricity Regulatory Authority - Ministry of Industry and Trade
Connecting the project of Bo Y 220kV switching station and connection 220kV power lines
Status of successfully energizing the project at night

EVN.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097071

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice