NEWS & EVENTS

Taking advantage of favorable weather, accelerating construction progress of 500kV Lao Cai - Vinh Yen transmission line

28/03/2025 16:17:26

On March 27th, EVN’s Vice President Mr.Pham Hong Phuong inspected the construction of packages 1, 3, and 4 of the 500kV Lao Cai - Vinh Yen transmission line project in Lao Cai and Yen Bai provinces. EVN’s leaders specifically required contractors to take advantage of the "golden time" with current favorable weather conditions to accelerate project progress.

EVN’s Vice President Mr.Pham Hong Phuong and the delegation inspected the site at positions VT2, VT14, VT33 of package 1 of Song Da Construction & Service - PC1 - Dong Anh Consortium.

At the site, Deputy General Director of Song Da Construction and Service JSC – Mr.Nguyen Cao Ngoc said that package 1, which his unit is responsible for constructing, has 36 tower foundation positions in Lao Cai province. As of March 27th, the unit is building access roads to 18 positions; implementing site leveling and foundation pit excavation at 14 positions, and reinforcing steel base foundations at 3 positions. 

Mr. Hoang Quoc Dong (Power Project Management Board 1 - EVNPMB1) - Chief Construction Supervisor for package 1 in Lao Cai province reported that currently, contractors have concentrated manpower, machinery, and materials at the construction site and implemented negotiations for temporary roads and yards with local residents to proceed with construction. Given the urgency of this project, EVNPMB1 has required contractor’s leaders to be present on-site, maximize human resources, financial resources, as well as materials to ensure continuous construction, especially during favorable weather in April.

The units participating in the project are urgently implementing work, with determination to complete all foundation pits in May 2025, complete tower erection in July 2025, and complete wire stringing in August 2025.

Position 14 of package 1 is being implemented with foundation base reinforcement to proceed with concrete pouring. Photo: Ng.Tuan

Inspecting construction at package 4 of the project, Mr. Nguyen Van Dung, Deputy General Director of Song Da 11 Company - the implementing contractor, said that package 4 has 51 positions (from positions 149 to 200) located in Yen Bai province. The unit has developed a plan to accelerate construction progress before the northern mountainous provinces enter the rainy season. To date, the unit is implementing construction at a total of 28 positions, having completed leveling at 22 positions, and is excavating foundations and pouring concrete at 10 positions. Song Da 11 aims to complete the foundation part in approximately 40-45 days. The unit will coordinate closely between foundation construction and material supply to ensure synchronization.

Consultants and contractors reported to EVN’s Vice President Mr.Pham Hong Phuong (second from left) on detailed design at position 166 in Yen Bai, part of package 4 of Song Da 11 JSC. Photo: Ng.Tuan

Through on-site inspection, EVN’s Vice President Mr.Pham Hong Phuong acknowledged that contractors have implemented the project decisively and synchronously. However, some packages have not met the investor's expectations regarding implementation progress.

Currently, packages 1 and 4 are being implemented relatively well, while package 3 is mainly focusing on negotiation, compensation, and site clearance, without sufficient manpower and equipment on site.

Position 168 in Yen Bai of package 4 by Song Da 11 Company has completed foundation pits. Photo: Ng.Tuan

EVN’s Vice President Mr.Pham Hong Phuong requested contractors to increase manpower from now until March 31st to ensure synchronized implementation at all positions to meet the urgent schedule of the project. In particular, they must take advantage of favorable weather to accelerate construction progress. Currently, it is the "golden time" for project construction in the northern mountainous region.

The EVN’s Vice President also directed the supervision consultant to promptly accept phase transitions, closely monitor construction conditions and developments at the site for timely supervision. Power Project Management Board 1 should continue to strictly manage the project, increase construction supervision manpower, and implement simultaneous solutions to ensure progress and quality.

Find more information about the 500kV Lao Cai - Vinh Yen transmission line project here.

500kV Lao Cai - Vinh Yen Transmission Line Project:

  • Investor: Vietnam Electricity;
  • Investor's representative for project management: Power Project Management Board 1;
  • Survey and engineering consultants: Consortium of Power Engineering Consulting Joint Stock Company 1 (EVNPECC1) and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Total investment: Over 7,410 billion VND;
  • Project route through: Lao Cai, Yen Bai, Phu Tho, and Vinh Phuc provinces;
  • Construction implementation: March 2025;
  • Expected completion: Before September 2nd 2025.

EVN.COM.VN

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3097055

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice