NEWS & EVENTS

Taking advantage of favorable weather, accelerating construction progress of 500kV Lao Cai - Vinh Yen transmission line

28/03/2025 16:17:26

On March 27th, EVN’s Vice President Mr.Pham Hong Phuong inspected the construction of packages 1, 3, and 4 of the 500kV Lao Cai - Vinh Yen transmission line project in Lao Cai and Yen Bai provinces. EVN’s leaders specifically required contractors to take advantage of the "golden time" with current favorable weather conditions to accelerate project progress.

EVN’s Vice President Mr.Pham Hong Phuong and the delegation inspected the site at positions VT2, VT14, VT33 of package 1 of Song Da Construction & Service - PC1 - Dong Anh Consortium.

At the site, Deputy General Director of Song Da Construction and Service JSC – Mr.Nguyen Cao Ngoc said that package 1, which his unit is responsible for constructing, has 36 tower foundation positions in Lao Cai province. As of March 27th, the unit is building access roads to 18 positions; implementing site leveling and foundation pit excavation at 14 positions, and reinforcing steel base foundations at 3 positions. 

Mr. Hoang Quoc Dong (Power Project Management Board 1 - EVNPMB1) - Chief Construction Supervisor for package 1 in Lao Cai province reported that currently, contractors have concentrated manpower, machinery, and materials at the construction site and implemented negotiations for temporary roads and yards with local residents to proceed with construction. Given the urgency of this project, EVNPMB1 has required contractor’s leaders to be present on-site, maximize human resources, financial resources, as well as materials to ensure continuous construction, especially during favorable weather in April.

The units participating in the project are urgently implementing work, with determination to complete all foundation pits in May 2025, complete tower erection in July 2025, and complete wire stringing in August 2025.

Position 14 of package 1 is being implemented with foundation base reinforcement to proceed with concrete pouring. Photo: Ng.Tuan

Inspecting construction at package 4 of the project, Mr. Nguyen Van Dung, Deputy General Director of Song Da 11 Company - the implementing contractor, said that package 4 has 51 positions (from positions 149 to 200) located in Yen Bai province. The unit has developed a plan to accelerate construction progress before the northern mountainous provinces enter the rainy season. To date, the unit is implementing construction at a total of 28 positions, having completed leveling at 22 positions, and is excavating foundations and pouring concrete at 10 positions. Song Da 11 aims to complete the foundation part in approximately 40-45 days. The unit will coordinate closely between foundation construction and material supply to ensure synchronization.

Consultants and contractors reported to EVN’s Vice President Mr.Pham Hong Phuong (second from left) on detailed design at position 166 in Yen Bai, part of package 4 of Song Da 11 JSC. Photo: Ng.Tuan

Through on-site inspection, EVN’s Vice President Mr.Pham Hong Phuong acknowledged that contractors have implemented the project decisively and synchronously. However, some packages have not met the investor's expectations regarding implementation progress.

Currently, packages 1 and 4 are being implemented relatively well, while package 3 is mainly focusing on negotiation, compensation, and site clearance, without sufficient manpower and equipment on site.

Position 168 in Yen Bai of package 4 by Song Da 11 Company has completed foundation pits. Photo: Ng.Tuan

EVN’s Vice President Mr.Pham Hong Phuong requested contractors to increase manpower from now until March 31st to ensure synchronized implementation at all positions to meet the urgent schedule of the project. In particular, they must take advantage of favorable weather to accelerate construction progress. Currently, it is the "golden time" for project construction in the northern mountainous region.

The EVN’s Vice President also directed the supervision consultant to promptly accept phase transitions, closely monitor construction conditions and developments at the site for timely supervision. Power Project Management Board 1 should continue to strictly manage the project, increase construction supervision manpower, and implement simultaneous solutions to ensure progress and quality.

Find more information about the 500kV Lao Cai - Vinh Yen transmission line project here.

500kV Lao Cai - Vinh Yen Transmission Line Project:

  • Investor: Vietnam Electricity;
  • Investor's representative for project management: Power Project Management Board 1;
  • Survey and engineering consultants: Consortium of Power Engineering Consulting Joint Stock Company 1 (EVNPECC1) and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Total investment: Over 7,410 billion VND;
  • Project route through: Lao Cai, Yen Bai, Phu Tho, and Vinh Phuc provinces;
  • Construction implementation: March 2025;
  • Expected completion: Before September 2nd 2025.

EVN.COM.VN

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251906

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4