The 220kV Chu Se Substation and Interconnection have been energized

01/08/2022 00:00:00

At 9:50 AM on August 1st, in Gia Lai province, Central Power Project Management Board (EVNCPMB), coordinating with relevant units, organized the acceptance and energization of the 220kV Chu Se Substation and Interconnection project.

The 220kV Chu Se Substation and Interconnection Line

This is a Grade I industrial electricity project, Group B, invested by the National Power Transmission Corporation (EVNNPT), managed by EVNCPMB, engineered by Power Engineering Consulting Joint Stock Company 4 (EVNPECC4), and operated by Power Transmission Company 3. The project has been implemented since the end of 2019 in Ia Pal commune, Chu Se district, Gia Lai province.

The project involves the construction of a new 220/110/22kV substation with a planned capacity of 2x125MVA. In this phase, one 125MVA transformer has been installed. The 220kV branch line consists of two circuits, approximately 0.39km in length, connecting to the existing 220kV Pleiku 2 - Krong Buk transmission line.

Within the project scope, the installation of lightning protection wires combined with optical cables on the existing 220kV Pleiku 2 - Krong Buk transmission line has been carried out, along with additional lightning protection wires at certain pole sections to share the single-phase short-circuit current.

The completion of the project holds significant importance in ensuring electricity supply to Gia Lai province and surrounding areas, collecting renewable energy sources in the region for transmission to the national grid, reducing power losses in the regional power grid, and improving the voltage of the 110kV power grid in the area.

Source: evn.com.vn

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827211

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice