NEWS & EVENTS

The 500kV Quang Trach - Doc Soi transmission line project is ready for technical commissioning

02/06/2022 00:00:00

The Technical Acceptance Council of the National Power Transmission Corporation (EVNNPT) conducted the technical commissioning of the 500kV Quang Trach - Doc Soi transmission line project and the 500kV Quang Trach Substation on May 30, 2022, in Quang Binh province. Mr. Bui Van Kien, Deputy General Director of EVNNPT and Chairman of the Acceptance Council affirmed that the project is ready for technical commissioning.

The meeting was attended by Mr. Khuong The Anh, Deputy Head of Construction Management Department (Vietnam Electricity), specialized departments of EVNNPT, Central Power Project Management Board, construction contractors, engineering consultants, supervision consultants, testing and calibration, construction testing, equipment and material suppliers, and operation management unit.

During the meeting, Deputy General Director of EVNNPT, Mr. Bui Van Kien, acknowledged the efforts of The Central Power Projects Management Board (EVNCPMB) - the project management and operation unit, as well as the participating units involved in the construction of the project, in overcoming challenges such as the COVID-19 pandemic and floods in recent years to bring the project to completion.

Mr. Bui Van Kien, Deputy General Director of EVNNPT stated: "The 500kV Quang Trach - Doc Soi transmission line project and the 500kV Quang Trach Substation have completed construction work according to approved design documents and have undergone acceptance tests in compliance with the current regulations and decrees of the state regarding the quality management of construction projects, ensuring the conditions for putting the projects into operation. The project meets the requirements and is ready for electrical commissioning and technical acceptance."

Mr. Bui Van Kien, Deputy General Director of EVNNPT, requested EVNCPMB to coordinate with relevant units to ensure the safety of the electrical commissioning. After the acceptance tests, some minor issues do not affect the electrical commissioning. EVNCPMB will lead in coordinating with the relevant units to address these issues before handing over the project.

Mr. Bui Van Kien - Deputy General Director of EVNNPT, Chairman of the Acceptance Council made a statement at the meeting

The 500kV Quang Trach - Doc Soi transmission line project is constructed over the provinces of Quang Binh, Quang Tri, Thua Thien Hue, Quang Nam, Quang Ngai, and Da Nang city.

CPMB reported that as of May 30, 2022, the foundation, grounding, and steel columns were constructed according to the approved design and closely monitored during construction to ensure quality and technical requirements. The conductor wires, lightning protection, fiber optic cables, and accessories were also installed according to the approved design and manufacturer's instructions, with strict supervision during construction to ensure quality compliance with the approved design.

The transmission line corridor ensures a safe distance according to Decree 14/2014/NĐ-CP dated February 26, 2014, and Decree 51/2020/NĐ-CP dated April 21, 2020, which amend and supplement some provisions of Decree 14/2014/NĐ-CP of the Government on the safety protection of high-voltage power grids.

The optical repeater stations were constructed according to the approved design and closely monitored during construction to ensure quality and technical requirements.

The project involves the construction of a double-circuit 500kV transmission line with a length of 500.14 km from the Quang Trach 500kV substation to the Doc Soi 500kV substation. It includes the construction of three optical repeater stations along the transmission line to amplify and transmit information signals and the construction of three operation management buildings for the transmission team.

CPMB has organized the construction of the 500kV Quang Trach - Doc Soi transmission line project and the 500kV Quang Trach Substation following the approved design documents, gathering complete documentation of the completed project and conducting the acceptance testing of the project components in compliance with legal regulations.

The members of the Acceptance Council for the 500kV Quang Trach - Doc Soi Transmission Line and the 500kV Quang Trach Distribution Substation Project

The 500kV Quang Trach - Doc Soi transmission line and the 500kV Quang Trach distribution substation project

  • Investor: National Power Transmission Corporation (EVNNPT)
  • Representative of the investor: Central Power Projects Management Board
  • Engineering consulting firm: Consortium of Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) - Institute of Energy - Power Engineering Consulting Joint Stock Company 1
  • Supervision consulting firm: Power Transmission Company 2
  • Commencement date: December 18, 2018
  • Expected completion date: May 31, 2022

Source: npt.com.vn

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251493

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4