The 500kV Viet Tri Substation is being upgraded to a capacity of 900MVA to enhance power supply reliability for Phu Tho province and the surrounding areas

25/10/2022 16:04:11

At 5:30 am on October 25th, the Central Power Projects Management Board (CPMB), in coordination with relevant units, successfully energized the Phase 2 installation of Transformer No. 2 at the 500kV Viet Tri Substation.

Construction units conducted pre-energization testing and calibration before installing the second transformer at the 500kV Viet Tri Substation

Previously, the Phase 1 energization of the project took place in April 2021. After the completion, the capacity of the Viet Tri 500kV Substation has been increased to 2x450MVA.

The project is invested by the National Power Transmission Corporation (EVNNPT), managed by CPMB, engineered by Power Engineering Consulting Joint Stock Company 1, supervised by Power Engineering Consulting Joint Stock Company 4 (EVNPECC4), and operated by Power Transmission Company 1.

Being a special-grade and Group B project, it has a total investment of over 196 billion VND. The project is constructed within the existing 500kV Viet Tri Substation premises, located in Bao Thanh and Gia Thanh communes, Phu Ninh district, Phu Tho province.

The project involves the installation of a new 500/220/35kV transformer - 3x150 MVA (AT2 transformer) as a backup unit, increasing the substation's capacity to 2x450 MVA. It also includes the installation of an online oil monitoring system for the newly installed AT2 transformer, as well as for the existing AT1 transformer and 500kV surge arresters, including computer systems and accompanying software. Additionally, it equips the substation with 500kV circuit breakers, isolators, current transformers, and voltage transformers to connect the AT2 transformer from a delta configuration to a star configuration

Furthermore, the project also provides equipment for the 220kV busbar section relating to the AT2 transformer, installs lightning arrester valves and a 35kV voltage transformer for the AT2 transformer's balance coil, and supplies control, protection and measurement equipment for the newly installed devices. It also involves the declaration, update, and supplementary configuration of computer control systems for the newly installed devices.

Once completed, the project will ensure a stable and reliable long-term electricity supply for the socio-economic development of Phu Tho province and the surrounding areas. It will enhance the reliability and transmission capability of the power grid, reduce power losses in the transmission grid, and increase the operational efficiency of EVN's power generation and business.

Source: icon.com.vn

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096950

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice