At 5:30 am on October 25th, the Central Power Projects Management Board (CPMB), in coordination with relevant units, successfully energized the Phase 2 installation of Transformer No. 2 at the 500kV Viet Tri Substation.

Construction units conducted pre-energization testing and calibration before installing the second transformer at the 500kV Viet Tri Substation

Previously, the Phase 1 energization of the project took place in April 2021. After the completion, the capacity of the Viet Tri 500kV Substation has been increased to 2x450MVA.

The project is invested by the National Power Transmission Corporation (EVNNPT), managed by CPMB, engineered by Power Engineering Consulting Joint Stock Company 1, supervised by Power Engineering Consulting Joint Stock Company 4 (EVNPECC4), and operated by Power Transmission Company 1.

Being a special-grade and Group B project, it has a total investment of over 196 billion VND. The project is constructed within the existing 500kV Viet Tri Substation premises, located in Bao Thanh and Gia Thanh communes, Phu Ninh district, Phu Tho province.

The project involves the installation of a new 500/220/35kV transformer - 3x150 MVA (AT2 transformer) as a backup unit, increasing the substation's capacity to 2x450 MVA. It also includes the installation of an online oil monitoring system for the newly installed AT2 transformer, as well as for the existing AT1 transformer and 500kV surge arresters, including computer systems and accompanying software. Additionally, it equips the substation with 500kV circuit breakers, isolators, current transformers, and voltage transformers to connect the AT2 transformer from a delta configuration to a star configuration

Furthermore, the project also provides equipment for the 220kV busbar section relating to the AT2 transformer, installs lightning arrester valves and a 35kV voltage transformer for the AT2 transformer's balance coil, and supplies control, protection and measurement equipment for the newly installed devices. It also involves the declaration, update, and supplementary configuration of computer control systems for the newly installed devices.

Once completed, the project will ensure a stable and reliable long-term electricity supply for the socio-economic development of Phu Tho province and the surrounding areas. It will enhance the reliability and transmission capability of the power grid, reduce power losses in the transmission grid, and increase the operational efficiency of EVN's power generation and business.

Source: icon.com.vn

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827217

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice