The 220kV Van Phong substation project is invested by the National Power Transmission Corporation (EVNNPT), with CPMB managing the project on behalf of EVNNPT. Power Transmission Company 3 is responsible for operation and management, EVNPECC4 handles the design, Electricity Joint Stock Company provides supervision consulting, Power Transmission Technical Service Company conducts testing and calibration, and Alphanam E&C is responsible for construction.

The AT1 220kV Van Phong transformer

The project includes:

  • Construction of a new 220kV substation: Van Phong 220kV substation, an outdoor type with a capacity of a 220kV transformer - 250MVA, four 220kV outgoing feeder bays, one 220kV busbar bay, one 220kV interlocking bay, six 110kV outgoing feeder bays, one 110kV busbar bay, one 110kV interlocking bay, one 110kV loop breaker bay, and one 22kV feeder bay.
  • Construction of new transmission lines: two 220kV double-circuit transmission lines, approximately 265m in length, connecting the existing 220kV Tuy Hoa - Nha Trang transmission line, and construction of a single-circuit 22kV transmission line, 889.5m in length, to provide power for the substation's usage.

The commissioning of the 220kV Van Phong substation will enhance reliability and ensure power supply for the growing loads in Ninh Hoa town and a part of the Van Phong economic zone, meeting the socio-economic development needs of Khanh Hoa province. Additionally, it will facilitate the connection of renewable energy sources in the area to the national power grid.

congthuong.vn

Related article

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Announcement of Liberation Day (30th April) and International Labor Day (1st May) holidays 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Liberation Day (30th April) and International Labor Day (1st May) holidays as following

Announcement of Hung Kings’ Commemoration Day 2026

Announcement of Hung Kings’ Commemoration Day 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the Hung Kings' Commemoration Day holiday as following:

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

EVNNPT Labor Union Supports Construction Site, Accelerates Completion of the 500kV Hoa Binh Substation Capacity Upgrade Project on Schedule

On April 9th 2026, in Phu Tho, the Labor Union of the National Power Transmission Corporation (EVNNPT) visited and encouraged employees of the Power Transmission Project Management Board (NPTPMB), along with contractors working on the 500kV Hoa Binh Substation Capacity Upgrade Project—one of EVNNPT’s key and urgent power transmission projects.

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

Investment of VND 3,000 billion to develop a waste-to-energy plant in Khanh Son

On the morning of March 19th, the Vietnam Bank for Agriculture and Rural Development (Agribank), in coordination with Vietnam Environment Joint Stock Company (a member of the Amaccao Group), held a signing ceremony for a credit agreement and an insurance contract to implement the Khanh Son waste-to-energy plant project (Hoa Khanh Ward, Da Nang City).

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2827229

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice