The energization of the 220kV Yen Hung Substation and Interconnection: Enhancing power supply for Quang Ninh Province during the hot season

13/06/2022 00:00:00

At 7:00 AM on June 13th, The Northern Power Projects Management Board (EVNNPMB), in collaboration with relevant units, energized the 220kV Yen Hung Substation and Interconnection project.

This is a Grade I energy project, Group B, with a total investment of over 482 billion VND. The National Power Transmission Corporation (EVNNPT) is the investor, EVNNPMB manages the project, Power Engineering Consulting Joint Stock Company 1 is engineering consultant, and Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) is appraisal and construction estimation consultant, and Power Transmission Company 1 is the operator.

The AT1 Transformer at the 220kV Yen Hung Substation

The 220kV Yen Hung Substation is located in Minh Thanh Ward, Quang Yen Town, Quang Ninh Province. The interconnection line of the 220kV Yen Hung Substation passes through the following areas: Bac Son and Nam Khe wards in Uong Bi City and Minh Thanh and Dong Mai wards in Quang Yen Town, Quang Ninh Province.

The newly constructed 220/110/22kV substation includes the installation of a 250MVA (AT1) 220/110/22kV transformer. The 220kV section is equipped with devices for 2 transmission line circuits (to connect to the 220kV Yen Hung Substation on the existing Uong Bi Thermal Power Plant - Trang Bach 220kV transmission line) and 1 transformer bay operating according to a delta configuration (designed according to a missing quadrilateral diagram).

The 110kV section is equipped with devices for 11 bays (8 transmission line bays, 1 communication bay, 1 ring circuit bay, and 1 total 110kV transformer bay for the 220kV substation).

The 22kV section has outdoor devices arranged according to the power supply block diagram for self-use. The control, protection, measurement, communication, and SCADA systems are equipped in compliance with EVN and EVNNPT regulations, as well as current regulations.

The 220kV interconnection line is constructed as a forward interconnection on the existing Uong Bi Thermal Power Plant - Trang Bach 220kV transmission line, with a cross-sectional area of 2xACSR 330/43 and a length of approximately 20km.

The completion of the project meets the electricity supply demand for Quang Ninh Province during this year's hot season. Additionally, it strengthens the connectivity between regions in the power system, enhances the safe and stable operation of the national power system, improves power supply stability, reduces power losses and energy losses in the system, and enhances the production and business efficiency of EVNNPT.

Source: petrotimes.vn

Related article

APPRECIATION LETTER 50 YEARS OF COMPANIONSHIP - TRUST BUILDING

APPRECIATION LETTER 50 YEARS OF COMPANIONSHIP - TRUST BUILDING

Dear Valued Clients, Partners and Shareholders On the occasion of the 50th Anniversary of Power Engineering Consulting Joint Stock Company 4 (PECC4), We would like to extend our heartfelt gratitude for your trust, partnership, and invaluable support throughout our journey of growth and development.

French Embassy and AFD visited 500kV Binh Duong 1 substation, recognizing successful cooperation with EVNNPT

French Embassy and AFD visited 500kV Binh Duong 1 substation, recognizing successful cooperation with EVNNPT

Recently, a delegation from the French Embassy in Vietnam and the French Development Agency (AFD) held a working session with the National Power Transmission Corporation (EVNNPT) and visited the 500kV Binh Duong 1 Substation.

Training on the BIM Software Ecosystem for EVNPECC4's Professional Consulting Engineers

Training on the BIM Software Ecosystem for EVNPECC4's Professional Consulting Engineers

Continuing its efforts to provide training and enhance the skills required to use software supporting surveying and engineering consulting activities, on 19th June 2026, Power Engineering Consulting Joint Stock Company No. 4 (EVNPECC4) signed a training contract with the Research and Development of Software in Construction (RDSIC) under the Hanoi University of Civil Engineering to organize Building Information Modeling (BIM) training courses for EVNPECC4's professional consulting engineers.

PRESS RELEASE

PRESS RELEASE

To: Valued Customers, Partners, Shareholders, Investors, and Employees of Power Engineering Consulting Joint Stock Company 4 (PECC4)

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2927488

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice