NEWS & EVENTS

Upgrading 500kV Pho Noi Substation to 1,800 MVA which strengthening power supply for Northern Vietnam

25/03/2026 16:35:18

At 2:00 AM on March 25th 2026, the National Power Transmission Corporation (EVNNPT), the Power Transmission Project Management Board (NPTPMB), in coordination with the National Electricity System and Market Operation Company Limited (NSMO) and relevant units, successfully energized the project of upgrading 500kV Pho Noi Substation’s capacity.

Project stakeholders witnessed the energization milestone

This is a special-grade energy project (Group B), with EVNNPT as the investor, NPTPMB acting on behalf of the investor for project management and administration, and Power Transmission Company No. 1 responsible for operation. The project was implemented within the existing 500kV Pho Noi Substation (without land expansion), located in Dai Dong Commune, Hung Yen Province.

The 500kV Pho Noi Substation plays a critically important role in supplying electricity to Hung Yen Province, the southeastern area of Hanoi, and neighboring provinces. Prior to the upgrade, the substation frequently operated at over 90% load, at times reaching up to 97%. To ensure reliable power supply during the 2026 peak dry season, the project was classified as an urgent project and approved by the Prime Minister under Decision No. 2634/QĐ-TTg dated December 2nd 2025.

Fire Prevention and Rescue Police forces (Hung Yen Provincial Police), in coordination with relevant units, were on standby to ensure fire and explosion safety during energization

The project scope includes the installation of one new 500kV–900MVA transformer (AT5), isolating the existing 500kV–600MVA transformer (AT1) for standby operation, thereby increasing the total capacity of the 500kV Pho Noi Substation from 1,500MVA to 1,800MVA; Installation of equipment for the 500kV main bay of transformer AT5; installation of equipment for the 220kV main bay of transformer AT5; installation of tubular busbars and the 35kV auxiliary system for transformer AT5; and completion of technical solutions in accordance with the substation’s capacity scale.

The project commenced on November 20th 2025. After intensive efforts with round-the-clock operations (three shifts, four crews), the project was completed by the afternoon of March 23rd 2026. The investor’s acceptance council approved energization shortly thereafter. The project was energized on March 25th 2026, ahead of the schedule assigned by EVNNPT under Decision No. 315/QĐ-EVNNPT dated February 12th 2026 (originally planned for Q2/2026), demonstrating the strong project management capability of NPTPMB and the dedication of all participating units on site.

The 500kV–900MVA transformer (AT5) at 500kV Pho Noi Substation was successfully energized

Completing the project ahead of the dry season helps reduce the load on existing 500kV transformers at the substation, thereby ensuring N-1 reliability criteria, enhancing system stability, and improving the safety and reliability of power supply for Hung Yen Province, southeastern Hanoi, and neighboring areas. This contributes significantly to regional socio-economic development.

NPT.COM.VN

500kV Pho Noi Substation Capacity Upgrade Project:

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management: Power Transmission Project Management Board (NPTPMB);
  • Operator: Power Transmission Company No. 1;
  • Engineering and supervision consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Project Scope: Special-grade energy project (Group B); installation of one 500kV–900MVA transformer (AT5); isolation of 500kV–600MVA transformer (AT1) for standby; capacity upgrade from 1,500MVA to 1,800MVA; Installation of equipment for the 500kV main bay of transformer AT5; installation of equipment for the 220kV main bay of transformer AT5; installation of tubular busbars and the 35kV auxiliary system for transformer AT5; and completion of technical solutions in accordance with the substation’s capacity scale;
  • The completion of the project prior to the dry season helps reduce the load on the existing 500kV transformers at the 500kV Pho Noi Substation, thereby contributing to ensuring the N-1 reliability criterion, enhancing power system stability, and improving the reliability and safety of electricity supply for Hung Yen Province, the southeastern area of Hanoi, and neighboring provinces, thus supporting socio-economic development in the region.

Images of EVNPECC4 providing engineering and supervision consulting services for the 500kV Pho Noi  Substation Capacity Upgrade Project:

Related article

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

Gia Lai Approved Investment Policy for the Se San 3 Hydropower Plant Expansion

The Gia Lai Provincial People’s Committee has recently approved the investment policy and concurrently approved Vietnam Electricity (EVN) as the investor for the Se San 3 Hydropower Plant Expansion Project. The project will be implemented in Ia Ly Commune, Gia Lai Province, and Ya Ly Commune, Quang Ngai Province.

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

Gia Lai approves investment policy for Sesan 4 Hydropower Plant Expansion Project

The Gia Lai Provincial People’s Committee issued Decision No. 3625/QD-UBND dated August 23, 2026, approving the investment policy and simultaneously approving Vietnam Electricity (EVN) as the investor of the Sesan 4 Hydropower Plant Expansion Project. The project has a design capacity of 120MW and a total investment of nearly VND 3 trillion.

Announcement of National Day Holiday on September 2nd 2026

Announcement of National Day Holiday on September 2nd 2026

Dear valued Shareholders, Partners and Customers, please be informed that our offices will be closed during the National Day holiday 2026

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

Power Engineering Consulting Joint Stock Company 4 successfully organized the 2026 Extraordinary General Meeting of Shareholders

On August 24th 2026, at its Headquarters at 11 Hoang Hoa Tham Street, Nha Trang Ward, Khanh Hoa Province, Power Engineering Consulting Joint Stock Company 4 (PECC4), stock code TV4, successfully organized its 2026 Extraordinary General Meeting of Shareholders in accordance with the prescribed procedures, formalities, and applicable laws. The Meeting was attended and directed by representatives of Vietnam Electricity (EVN), including Ms. Pham Thi Thuy Ha - EVN’s Board Member; Mr. Tran Vinh Thai - Deputy Head of Corporate Planning Department; and Ms. Pham Huong Giang - Officer of Corporate Planning Department, together with 46 PECC4 shareholders, representing 14,850,719 shares, equivalent to 75.07% of the Company’s total voting shares.

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

EVNPECC4 participated in Football Tournament to commemorate the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026)

On the afternoon of August 18th 2026, at My Anh Football Field in Nha Trang Ward, Power Engineering Consulting Joint Stock Company 4 (EVNPECC4) participated in a football tournament commemorating the 81st Anniversary of the Traditional Day of the People’s Public Security Forces of Vietnam (19/8/1945 - 19/8/2026). The tournament was organized by the Cybersecurity and High-Tech Crime Prevention Division of Khanh Hoa Provincial Police.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3096609

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice