NEWS & EVENTS

Upgrading 500kV Pho Noi Substation to 1,800 MVA which strengthening power supply for Northern Vietnam

25/03/2026 16:35:18

At 2:00 AM on March 25th 2026, the National Power Transmission Corporation (EVNNPT), the Power Transmission Project Management Board (NPTPMB), in coordination with the National Electricity System and Market Operation Company Limited (NSMO) and relevant units, successfully energized the project of upgrading 500kV Pho Noi Substation’s capacity.

Project stakeholders witnessed the energization milestone

This is a special-grade energy project (Group B), with EVNNPT as the investor, NPTPMB acting on behalf of the investor for project management and administration, and Power Transmission Company No. 1 responsible for operation. The project was implemented within the existing 500kV Pho Noi Substation (without land expansion), located in Dai Dong Commune, Hung Yen Province.

The 500kV Pho Noi Substation plays a critically important role in supplying electricity to Hung Yen Province, the southeastern area of Hanoi, and neighboring provinces. Prior to the upgrade, the substation frequently operated at over 90% load, at times reaching up to 97%. To ensure reliable power supply during the 2026 peak dry season, the project was classified as an urgent project and approved by the Prime Minister under Decision No. 2634/QĐ-TTg dated December 2nd 2025.

Fire Prevention and Rescue Police forces (Hung Yen Provincial Police), in coordination with relevant units, were on standby to ensure fire and explosion safety during energization

The project scope includes the installation of one new 500kV–900MVA transformer (AT5), isolating the existing 500kV–600MVA transformer (AT1) for standby operation, thereby increasing the total capacity of the 500kV Pho Noi Substation from 1,500MVA to 1,800MVA; Installation of equipment for the 500kV main bay of transformer AT5; installation of equipment for the 220kV main bay of transformer AT5; installation of tubular busbars and the 35kV auxiliary system for transformer AT5; and completion of technical solutions in accordance with the substation’s capacity scale.

The project commenced on November 20th 2025. After intensive efforts with round-the-clock operations (three shifts, four crews), the project was completed by the afternoon of March 23rd 2026. The investor’s acceptance council approved energization shortly thereafter. The project was energized on March 25th 2026, ahead of the schedule assigned by EVNNPT under Decision No. 315/QĐ-EVNNPT dated February 12th 2026 (originally planned for Q2/2026), demonstrating the strong project management capability of NPTPMB and the dedication of all participating units on site.

The 500kV–900MVA transformer (AT5) at 500kV Pho Noi Substation was successfully energized

Completing the project ahead of the dry season helps reduce the load on existing 500kV transformers at the substation, thereby ensuring N-1 reliability criteria, enhancing system stability, and improving the safety and reliability of power supply for Hung Yen Province, southeastern Hanoi, and neighboring areas. This contributes significantly to regional socio-economic development.

NPT.COM.VN

500kV Pho Noi Substation Capacity Upgrade Project:

  • Investor: National Power Transmission Corporation (EVNNPT); 
  • Project Management: Power Transmission Project Management Board (NPTPMB);
  • Operator: Power Transmission Company No. 1;
  • Engineering and supervision consultant: Power Engineering Consulting Joint Stock Company 4 (EVNPECC4);
  • Project Scope: Special-grade energy project (Group B); installation of one 500kV–900MVA transformer (AT5); isolation of 500kV–600MVA transformer (AT1) for standby; capacity upgrade from 1,500MVA to 1,800MVA; Installation of equipment for the 500kV main bay of transformer AT5; installation of equipment for the 220kV main bay of transformer AT5; installation of tubular busbars and the 35kV auxiliary system for transformer AT5; and completion of technical solutions in accordance with the substation’s capacity scale;
  • The completion of the project prior to the dry season helps reduce the load on the existing 500kV transformers at the 500kV Pho Noi Substation, thereby contributing to ensuring the N-1 reliability criterion, enhancing power system stability, and improving the reliability and safety of electricity supply for Hung Yen Province, the southeastern area of Hanoi, and neighboring provinces, thus supporting socio-economic development in the region.

Images of EVNPECC4 providing engineering and supervision consulting services for the 500kV Pho Noi  Substation Capacity Upgrade Project:

Related article

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

Energization of 900MVA Transformer Raises 500kV Di Linh Substation Capacity to 1,350 MVA

The commissioning of the 500kV – 900MVA AT1 transformer has increased the capacity of 500kV Di Linh Substation from 900MVA to 1,350 MVA, initially enhancing its capability to evacuate power generated by power sources in the region.

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

PECC4 Shines in Pink: A Warm and Inspiring Celebration of Vietnamese Women's Day 20/10

In celebration of the 96th anniversary of the Vietnam Women's Union (20/10/1930 – 20/10/2026) and the 16th anniversary of Vietnamese Women's Day (20/10/2010 – 20/10/2026), with the approval of the Company's Executive Board, the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4) organized a gathering for female employees at the Company's headquarters (11 Hoang Hoa Tham Street, Nha Trang), followed by a social gathering at I-Resort Nha Trang. The event took place in a warm and joyful atmosphere, bringing meaningful moments and memorable experiences to PECC4's female employees.

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

PECC4 participates in a consortium for the engineering and survey consulting contract for the 500kV Krong Buk - Tay Ninh 1 tranmission line project

500kV Krong Buk - Tay Ninh 1 tranmission line project is invested by the National Power Transmission Corporation (EVNNPT) and managed by the Southern Power Projects Management Board (SPMB). The consortium comprising Power Engineering Consulting Joint Stock Company 4 (PECC4), Power Engineering Consulting Joint Stock Company 3 (PECC3), and Power Engineering Consulting Joint Stock Company 2 (PECC2) has signed Contract No.259//HĐTV-SPMB-PECC3-PECC2-PECC4 on 18/9/2026 with the Southern Power Projects Management Board (SPMB) for Package No. 5: Provision of construction survey consulting services; preparation of the technical design and construction cost estimate; detailed design; and bidding documents for the 500kV Krong Buk – Tay Ninh 1 Transmission Line Project.

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Mid-Autumn Festival 2026: Sharing Love, Bringing Joy to the Children of PECC4 Employees

Caring for employees’ spiritual well-being and nurturing the younger generation, particularly the children of PECC4 employees, have always received great attention from the Executive Board and the Labor Union of Power Engineering Consulting Joint Stock Company 4 (PECC4). This annual tradition has been preserved and continuously promoted over the years, becoming a meaningful part of PECC4’s corporate culture and reflecting the Company’s strong humanitarian values.

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

PECC4 successfully organized the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3

On September 25th 2026, in Nam Nha Trang Ward, the 2026 Sports Festival of Khanh Hoa Province’s Enterprise Emulation Cluster No. 3 was successfully held. As the Head of the Cluster in 2026, Power Engineering Consulting Joint Stock Company 4 (PECC4) was honored to host the event.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 3251355

Copyright © 2026 Power Engineering Consulting Joint Stock Company 4