NEWS & EVENTS

Vinh Tan 4 Extension Thermal Power Plant successfully grid-connected for the first time

08/07/2019 00:00:00

The Vinh Tan 4 Extension Thermal Power Plant (VT4E) is undertaken by a consortium of Power Engineering Consulting Joint Stock Company 3 and Power Engineering Consulting Joint Stock Company 4 for contract management, design appraisal, and construction supervision. The project has been substantially completed, ensuring quality and surpassing the schedule.

On April 22, 2019, the VT4E successfully conducted its first grid connection, surpassing the schedule by 71 days (the planned date as per the contract was July 1, 2019). This milestone marks a significant step towards commissioning the project for commercial operation before October 31, 2019.

Vinh Tan 4 Extension Thermal Power Plant has successfully achieved its first grid connection

VT4E, with an installed capacity of 600 MW, is located in Vinh Tan commune, Tuy Phong district, Binh Thuan province. Vietnam Electricity is the Investor, and the Power Generation Corporation 3/Project Management Board of Vinh Tan Thermal Power Plant is responsible for project management.

The project utilizes existing infrastructure and some shared systems with the Vinh Tan 4 Thermal Power Plant project. It is one of the critical projects of the government, aligned with the Power Development Plan VII, aiming to meet the urgent electricity demand of the southern provinces.

According to the design, the annual electricity output of VT4 will contribute approximately 3.6 billion kWh to the power system. It will operate with the existing Vinh Tan 4 Thermal Power Plant (2 x 600 MW) to ensure a stable power supply for the socio-economic development of Binh Thuan province and the southern provinces.

Main information about the Vinh Tan 4 Extension Thermal Power Plant Project:

  1. Investor: Vietnam Electricity.
  2. Project management consulting unit: Power Generation Corporation 3/Project Management Board of Vinh Tan Thermal Power Plant.
  3. EPC contractor: DMPP Consortium, consisting of Doosan Heavy Industries & Construction (DHI - South Korea), Mitsubishi Corporation (MC - Japan), Power Engineering Consulting Joint Stock Company 2 (EVNPECC2 - Vietnam), and Pacific Corporation (PACIFIC - Vietnam).
  4. Contract management and construction supervision consulting: Consortium of Power Engineering Consulting Joint Stock Company 3 (EVNPECC3), Power Engineering Consulting Joint Stock Company 4 (EVNPECC4), and foreign subcontractors.
  5. Design capacity: 1 x 600 MW (utilizing supercritical boiler technology).
  6. Total investment: 23,926 billion VND.
  7. Commencement date: April 23, 2016.

The EVNPECC4’s scope of work in the contract management and construction supervision consulting package includes:

Main work items:

  • Auxiliary equipment system of the turbine.
  • Auxiliary equipment system of the boiler: burners, crushers, feedwater pumps, flue gas systems, air dryers.
  • Distributed control and monitoring system (DCS).
  • Entire Balance of Plant (BOP) system of the power plant: coal supply and treatment system, water supply and wastewater treatment system, circulating water pipe, auxiliary cooling water system, compressed air system, fire detection and firefighting system, smoke treatment systems: electrostatic precipitator (ESP), seawater flue gas desulfurization (FGD), 210m flue gas stack, bottom ash and fly ash handling system, HVAC system for the entire plant, mineral water, domestic and service water tanks, clean and dirty oil tanks.
  • Electrical system inside the power plant: 11kV electrical equipment, DC backup and UPS system, cable system, CCTV surveillance system, continuous environmental monitoring system (CEMS) and data transmission to the Department of Natural Resources and Environment (DNRE).
  • Construction part: main power house, ESP-FGD-ASH control building, flue gas stack, guardhouse, fencing, internal roads, pipe supports, landscape and greenery.

Consulting services:

  • Review and approval of technical design documents.
  • Review and approval of detailed design documents.
  • Preparation of construction method documents and inspection and acceptance plans.
  • Preparation of commissioning process documents.
  • Construction supervision and installation of equipment in terms of quality, progress, and quantity management
  • Environmental management and supervision, occupational health and safety (HSE) on the construction site.
  • Monitoring and participating in explanations with the Investor regarding loan agreements.
  • Supporting and participating in explanations with the relevant authorities on tax-related issues, procedures, and customs clearance reports.
  • Checking documents and records for payment purposes.
  • Monitoring and inspecting goods at the port.
  • Monitoring and evaluating the training and technology transfer activities of the EPC contractor.
  • Supervising and managing procurement activities.
  • Testing and conducting trials at the workshop.
  • Supervising the testing, commissioning, and handover of equipment.
  • Monitoring the resolution of outstanding issues, warranty work, and completion report documentation.

Related article

APPRECIATION LETTER 50 YEARS OF COMPANIONSHIP - TRUST BUILDING

APPRECIATION LETTER 50 YEARS OF COMPANIONSHIP - TRUST BUILDING

Dear Valued Clients, Partners and Shareholders On the occasion of the 50th Anniversary of Power Engineering Consulting Joint Stock Company 4 (PECC4), We would like to extend our heartfelt gratitude for your trust, partnership, and invaluable support throughout our journey of growth and development.

French Embassy and AFD visited 500kV Binh Duong 1 substation, recognizing successful cooperation with EVNNPT

French Embassy and AFD visited 500kV Binh Duong 1 substation, recognizing successful cooperation with EVNNPT

Recently, a delegation from the French Embassy in Vietnam and the French Development Agency (AFD) held a working session with the National Power Transmission Corporation (EVNNPT) and visited the 500kV Binh Duong 1 Substation.

Training on the BIM Software Ecosystem for EVNPECC4's Professional Consulting Engineers

Training on the BIM Software Ecosystem for EVNPECC4's Professional Consulting Engineers

Continuing its efforts to provide training and enhance the skills required to use software supporting surveying and engineering consulting activities, on 19th June 2026, Power Engineering Consulting Joint Stock Company No. 4 (EVNPECC4) signed a training contract with the Research and Development of Software in Construction (RDSIC) under the Hanoi University of Civil Engineering to organize Building Information Modeling (BIM) training courses for EVNPECC4's professional consulting engineers.

PRESS RELEASE

PRESS RELEASE

To: Valued Customers, Partners, Shareholders, Investors, and Employees of Power Engineering Consulting Joint Stock Company 4 (PECC4)

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

500kV Hoa Binh Substation Upgraded to 1,800MVA, Strengthening Power Supply for Northern Vietnam Ahead of This Year’s Peak Heat Season

At 20:22 on April 29th 2026, the National Power Transmission Corporation (EVNNPT), in coordination with the Power Transmission Project Management Board (NPTPMB) and the National Power System and Market Operation Co., Ltd. (NSMO), successfully energized the project to upgrade the capacity of the 500kV Hoa Binh Substation, increasing its capacity from 1,350MVA to 1,800MVA.

Power Engineering Consulting Joint Stock Company 4

11 Hoang Hoa Tham St, Nha Trang Ward, Khanh Hoa Province, Vietnam

(+84) 258 - 3563999

(+84) 258 - 3563888

tv4@pecc4.vn

Northern Affiliate

Lot 3, TT4, Alley 183, Hoang Van Thai St, Phuong Liet Ward, Ha Noi City

(+84) 24 - 22183 870

(+84) 24 - 62855759

cnpb@pecc4.vn

Number of visits: 2927297

Copyright © 2022 Power Engineering Consulting Joint Stock Company 4

server-notice